1575-1575 1/2 W 37TH PL 90018

Certificate Information: 1575-1575 1/2 W 37TH PL 90018

Application / Permit
19010-70000-04669
Plan Check / Job No.
B19SL01457
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3 STORY DUPLEX WITH ATTACHED 4 CAR GARAGE
Permit Issued
Issued on 2/24/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 7/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 LUKE GONZALES
Corrections Issued 11/5/2019 LUKE GONZALES
Green Plans Picked Up 11/6/2019 APPLICANT
Quality Review Completed 11/7/2019 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 12/3/2019 APPLICANT
Plan Check Approved 2/14/2020 LUKE GONZALES
Issued 2/24/2020 LADBS
CofO in Progress 6/17/2021 ROBERT MCDOWELL
Permit Finaled 7/3/2021 DEROLD HAUFF
CofO Issued 7/3/2021 DEROLD HAUFF
Permit Finaled 7/3/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/9/2019 EMIL KYUPELYAN
Permit Cleared 12/9/2019 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 12/23/2019 EMIL KYUPELYAN
Green Code Cleared 12/23/2019 VIVIAN LAO
Hydrant and Access approval Cleared 12/23/2019 JEREMY CARTER
Sewer availability Cleared 12/23/2019 EMIL KYUPELYAN
ZA Case Cleared 12/24/2019 JOE LUCKEY
ZI Cleared 12/24/2019 JOE LUCKEY
Trees in Parkway Cleared 1/2/2020 JOHN KIM
Low Impact Development Cleared 1/14/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/14/2020 JEANIE LAM

Contact Information

Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045
Engineer Sanchez,, Pablo Beltran; Lic. No.: C86223 1840 S GAFFEY ST 382      SAN PEDRO, CA 90731

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/5/2020 Approved ROBERT MCDOWELL
Underground Mechanical 5/5/2020 Approved ROBERT MCDOWELL
Deputy Reinf. Concrete 5/7/2020 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 5/12/2020 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 5/22/2020 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 6/30/2020 Partial Approval ROBERT MCDOWELL
ELECTRICAL-Rough 6/30/2020 Corrections Issued ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 6/30/2020 Approved ROBERT MCDOWELL
Green Building Rough 6/30/2020 Not Ready for Inspection ROBERT MCDOWELL
HVAC-Rough 6/30/2020 Corrections Issued ROBERT MCDOWELL
PLUMBING-Rough 6/30/2020 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 6/30/2020 Approved ROBERT MCDOWELL
Wood Frame 6/30/2020 Approved ROBERT MCDOWELL
Drywall Nailing 8/3/2020 Approved ROBERT MCDOWELL
HVAC-Rough 8/3/2020 Approved ROBERT MCDOWELL
Insulation 8/3/2020 Approved ROBERT MCDOWELL
Drywall Nailing 8/10/2020 Approved SABAS ALONSO
HVAC-Rough 8/10/2020 Approved SABAS ALONSO
Insulation 8/10/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 8/10/2020 Conditional Approval SABAS ALONSO
BUILDING-Rough-Frame 4/21/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Final 4/21/2021 Approved ROBERT MCDOWELL
Final 4/21/2021 Corrections Issued ROBERT MCDOWELL
Green Building Final 4/21/2021 Approved ROBERT MCDOWELL
Green Building Rough 4/21/2021 Approved ROBERT MCDOWELL
HVAC-Final 4/21/2021 Approved ROBERT MCDOWELL
PLUMBING-Final 4/21/2021 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 4/21/2021 SGSOV Approved ROBERT MCDOWELL
Service/Power Release 4/21/2021 Approved ROBERT MCDOWELL
Smoke Detectors 4/21/2021 Approved ROBERT MCDOWELL
Final 5/26/2021 Not Ready for Inspection ROBERT MCDOWELL
Final 6/3/2021 Conditional Approval ROBERT MCDOWELL