1837 W 80TH ST 90047

Certificate Information: 1837 W 80TH ST 90047

Application / Permit
19010-70000-04492
Plan Check / Job No.
B19SL01378
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 WITH ATTACHED 1 CAR GARAGE
Permit Issued
Issued on 8/3/2020
Issuing Office
Current Status
CofO Issued on 6/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2019 APPLICANT
Green Plans Picked Up 10/17/2019 APPLICANT
Assigned to Plan Check Engineer 10/18/2019 LUKE GONZALES
Corrections Issued 10/19/2019 LUKE GONZALES
Quality Review Completed 10/23/2019 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 3/5/2020 LUKE GONZALES
Issued 8/3/2020 APPLICANT
CofO in Progress 6/10/2021 FREDDIE RIVERA
CofO in Progress 6/10/2021 FREDDIE RIVERA
Permit Finaled 6/17/2021 DEROLD HAUFF
CofO Issued 6/17/2021 DEROLD HAUFF
Permit Finaled 6/17/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/6/2019 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 11/6/2019 CELINA MORENO
Sewer availability Cleared 11/6/2019 CELINA MORENO
ZI Cleared 11/15/2019 HELEN JADALI
Hydrant and Access approval Cleared 12/10/2019 JEREMY CARTER
Green Code Cleared 12/17/2019 VIVIAN LAO
Construction near power lines Cleared 1/29/2020 OSCAR CASTRO
Low Impact Development Cleared 2/27/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 2/27/2020 THOMAS LANG

Contact Information

Contractor L A Construction Group Inc; Lic. No.: 873259-B 8100 RESEDA BLVD #219      NORTHRIDGE, CA 91324
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/12/2020 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 8/19/2020 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 8/26/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 8/26/2020 Partial Approval FREDDIE RIVERA
Drywall Nailing 9/4/2020 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 9/4/2020 Not Ready for Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/4/2020 Partial Approval FREDDIE RIVERA
Green Building Rough 9/4/2020 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 9/4/2020 Not Ready for Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 9/14/2020 Approved FREDDIE RIVERA
ELECTRICAL-Rough 9/14/2020 Approved FREDDIE RIVERA
Green Building Rough 9/14/2020 Approved FREDDIE RIVERA
HVAC-Rough 9/14/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 9/14/2020 Approved FREDDIE RIVERA
Sewer 9/14/2020 Approved FREDDIE RIVERA
Underground Mechanical 9/14/2020 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 9/14/2020 Approved FREDDIE RIVERA
Insulation 9/28/2020 Approved FREDDIE RIVERA
Interior/Exterior Lathing 9/28/2020 Approved FREDDIE RIVERA
Drywall Nailing 9/30/2020 Approved FREDDIE RIVERA
Interior/Exterior Lathing 10/2/2020 Not Ready for Inspection FREDDIE RIVERA
Shower Pan 10/2/2020 Approved FREDDIE RIVERA
Interior/Exterior Lathing 10/9/2020 Approved FREDDIE RIVERA
Final 10/30/2020 Corrections Issued FREDDIE RIVERA
Green Building Final 10/30/2020 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/30/2020 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 10/30/2020 Not Ready for Inspection FREDDIE RIVERA
Smoke Detectors 10/30/2020 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/24/2020 SGSOV Not Ready FREDDIE RIVERA
Final 12/7/2020 Not Ready for Inspection FREDDIE RIVERA
Green Building Final 12/7/2020 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 12/7/2020 SGSOV Approved FREDDIE RIVERA
Service/Power Release 12/7/2020 Approved FREDDIE RIVERA
Smoke Detectors 12/7/2020 Approved FREDDIE RIVERA
Final 6/10/2021 OK to Issue CofO FREDDIE RIVERA