5752-5752 1/2 S 10TH AVE 90043

Certificate Information: 5752-5752 1/2 S 10TH AVE 90043

Application / Permit
19010-70000-04313
Plan Check / Job No.
B19SL01336
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2 STORY DUPLEX AT REAR
Permit Issued
Issued on 11/13/2019
Issuing Office
Metro
Current Status
CofO Issued on 12/11/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/27/2019 APPLICANT
Assigned to Plan Check Engineer 10/10/2019 LUKE GONZALES
Green Plans Picked Up 10/10/2019 APPLICANT
Corrections Issued 10/18/2019 LUKE GONZALES
Quality Review Completed 10/23/2019 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 10/25/2019 APPLICANT
Plan Check Approved 11/13/2019 LUKE GONZALES
Issued 11/13/2019 LADBS
CofO in Progress 12/9/2020 DAVID FEILER
Permit Finaled 12/11/2020 DEROLD HAUFF
CofO Issued 12/11/2020 DEROLD HAUFF
Permit Finaled 12/11/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/29/2019 CELINA MORENO
Highway dedication Cleared 10/29/2019 CELINA MORENO
Hydrant and Access approval Cleared 11/4/2019 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 11/5/2019 EMIL KYUPELYAN
Green Code Cleared 11/5/2019 NEGAR NEJAD
Low Impact Development Cleared 11/5/2019 ORVAL HERNANDEZ-MARCI
Permit Cleared 11/5/2019 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 11/5/2019 EMIL KYUPELYAN
Sewer availability Cleared 11/5/2019 EMIL KYUPELYAN
Frnt yard landscape/Water mgmt Cleared 11/6/2019 ANNA VAN
Project located in CRA area Cleared 11/12/2019 GISELLE CORELLA
ZI Cleared 11/12/2019 GISELLE CORELLA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/12/2019 Not Ready for Inspection COREY HUPP
Underground Mechanical 12/12/2019 Partial Approval COREY HUPP
Footing/Foundation/Slab 12/18/2019 Approved COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 1/9/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/28/2020 Approved COREY HUPP
PLUMBING-Rough 1/28/2020 Approved COREY HUPP
HVAC-Rough 1/31/2020 Partial Approval COREY HUPP
BUILDING-Rough-Frame 2/4/2020 Approved COREY HUPP
ELECTRICAL-Rough 2/4/2020 Approved COREY HUPP
Green Building Rough 2/4/2020 Approved COREY HUPP
Verify Sprinkler Sign Off 2/4/2020 Approved COREY HUPP
Drywall Nailing 2/13/2020 Approved COREY HUPP
Gas Test 2/13/2020 Not Ready for Inspection COREY HUPP
Interior/Exterior Lathing 2/13/2020 Approved COREY HUPP
Deputy Reinf. Concrete 3/20/2020 Conditional Approval COREY HUPP
Final 5/14/2020 Not Ready for Inspection FREDDIE RIVERA
Green Building Final 5/14/2020 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/14/2020 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 5/14/2020 No Access for Inspection FREDDIE RIVERA
Smoke Detectors 5/14/2020 Not Ready for Inspection FREDDIE RIVERA
Final 5/19/2020 Corrections Issued COREY HUPP
Green Building Final 5/19/2020 Approved COREY HUPP
SGSOV-Seismic Gas S/O Valve 5/19/2020 SGSOV Approved COREY HUPP
Service/Power Release 5/19/2020 Not Ready for Inspection COREY HUPP
Smoke Detectors 5/19/2020 Approved COREY HUPP
Final 9/28/2020 Corrections Issued DAVID FEILER
Service/Power Release 9/28/2020 Not Ready for Inspection DAVID FEILER
Final 10/21/2020 Corrections Issued DAVID FEILER
Service/Power Release 10/21/2020 Not Ready for Inspection DAVID FEILER
Final 12/4/2020 OK to Issue CofO DAVID FEILER
Service/Power Release 12/7/2020 Approved DAVID FEILER