2540-2540 1/2 E HOUSTON ST 90033

Certificate Information: 2540-2540 1/2 E HOUSTON ST 90033

Application / Permit
19010-70000-04290
Plan Check / Job No.
B19SL01327
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW DUPLEX WITH ATTACHED GARAGE AT REAR OF LOT ( 2 OF 2)
Permit Issued
Issued on 1/24/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 11/9/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 LUKE GONZALES
Corrections Issued 10/8/2019 LUKE GONZALES
Quality Review Completed 10/10/2019 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 10/15/2019 APPLICANT
Green Plans Picked Up 10/17/2019 APPLICANT
Applicant returned to address corrections 1/16/2020 LUKE GONZALES
Plan Check Approved 1/17/2020 LUKE GONZALES
Issued 1/24/2020 LADBS
CofO in Progress 11/9/2020 OSVALDO PARAMO
CofO in Progress 11/9/2020 OSVALDO PARAMO
CofO in Progress 11/9/2020 OSVALDO PARAMO
Permit Finaled 11/9/2020 DEROLD HAUFF
CofO Issued 11/9/2020 DEROLD HAUFF
Permit Finaled 11/9/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/17/2019 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 10/17/2019 EMIL KYUPELYAN
Highway dedication Cleared 10/17/2019 EMIL KYUPELYAN
Sewer availability Cleared 10/17/2019 EMIL KYUPELYAN
Hydrant and Access approval Cleared 11/14/2019 JOHN CONNEALLY
Clean Up Green Up Cleared 11/15/2019 ANNA VAN
Frnt yard landscape/Water mgmt Cleared 11/15/2019 ANNA VAN
Miscellaneous Cleared 11/15/2019 ANNA VAN
Green Code Cleared 11/19/2019 COLIN LOREDO
Low Impact Development Cleared 12/5/2019 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 12/5/2019 THOMAS LANG
GPI Written Notices Cleared 1/16/2020 LUKE GONZALES
Grading Pre-Inspection Cleared 1/16/2020 LUKE GONZALES

Contact Information

Contractor California Realty & Investment Group Inc; Lic. No.: 929543-B 9215 GARNISH DR      DOWNEY, CA 90240

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/19/2020 Approved OSVALDO PARAMO
Special/Order Compliance 2/19/2020 Partial Inspection RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 3/3/2020 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 3/3/2020 Corrections Issued OSVALDO PARAMO
Insulation 3/4/2020 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 3/6/2020 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 3/20/2020 Partial Approval OSVALDO PARAMO
Green Building Rough 3/20/2020 Not Ready for Inspection OSVALDO PARAMO
Verify Sprinkler Sign Off 3/20/2020 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/8/2020 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/10/2020 Partial Approval OSVALDO PARAMO
Green Building Rough 4/10/2020 Not Ready for Inspection OSVALDO PARAMO
Verify Sprinkler Sign Off 4/10/2020 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 5/1/2020 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 5/1/2020 Corrections Issued OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 5/4/2020 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 5/5/2020 Not Ready for Inspection OSVALDO PARAMO
Green Building Rough 5/5/2020 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 5/5/2020 Approved OSVALDO PARAMO
Wood Frame 5/8/2020 Conditional Approval JOSEPH MCGARRY
Insulation 5/11/2020 Conditional Approval THOMAS LOGRASSO
Drywall Nailing 5/20/2020 Approved OSVALDO PARAMO
Interior/Exterior Lathing 5/20/2020 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 7/29/2020 Approved OSVALDO PARAMO
Gas Test 7/29/2020 Approved OSVALDO PARAMO
HVAC-Final 7/29/2020 Corrections Issued OSVALDO PARAMO
PLUMBING-Final 7/29/2020 Approved OSVALDO PARAMO
ELECTRICAL-Final 7/30/2020 Corrections Issued OSVALDO PARAMO
HVAC-Final 7/30/2020 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Final 8/3/2020 Corrections Issued ROBERT VORHIS
HVAC-Final 8/3/2020 Approved ROBERT VORHIS
ELECTRICAL-Final 8/10/2020 Approved OSVALDO PARAMO
Final 8/10/2020 Corrections Issued OSVALDO PARAMO
Green Building Final 8/10/2020 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 8/10/2020 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 8/10/2020 Not Ready for Inspection OSVALDO PARAMO
Final 11/6/2020 OK to Issue CofO OSVALDO PARAMO
Service/Power Release 11/6/2020 Approved OSVALDO PARAMO
Smoke Detectors 11/6/2020 Approved OSVALDO PARAMO