2540-2540 1/2 E HOUSTON ST 90033
Certificate Information: 2540-2540 1/2 E HOUSTON ST 90033
- Application / Permit
- 19010-70000-04290
- Plan Check / Job No.
- B19SL01327
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW DUPLEX WITH ATTACHED GARAGE AT REAR OF LOT ( 2 OF 2)
- Permit Issued
- Issued on 1/24/2020
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 11/9/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2019 | LUKE GONZALES |
| Corrections Issued | 10/8/2019 | LUKE GONZALES |
| Quality Review Completed | 10/10/2019 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 10/15/2019 | APPLICANT |
| Green Plans Picked Up | 10/17/2019 | APPLICANT |
| Applicant returned to address corrections | 1/16/2020 | LUKE GONZALES |
| Plan Check Approved | 1/17/2020 | LUKE GONZALES |
| Issued | 1/24/2020 | LADBS |
| CofO in Progress | 11/9/2020 | OSVALDO PARAMO |
| CofO in Progress | 11/9/2020 | OSVALDO PARAMO |
| CofO in Progress | 11/9/2020 | OSVALDO PARAMO |
| Permit Finaled | 11/9/2020 | DEROLD HAUFF |
| CofO Issued | 11/9/2020 | DEROLD HAUFF |
| Permit Finaled | 11/9/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/17/2019 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2019 | EMIL KYUPELYAN |
| Highway dedication | Cleared | 10/17/2019 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 10/17/2019 | EMIL KYUPELYAN |
| Hydrant and Access approval | Cleared | 11/14/2019 | JOHN CONNEALLY |
| Clean Up Green Up | Cleared | 11/15/2019 | ANNA VAN |
| Frnt yard landscape/Water mgmt | Cleared | 11/15/2019 | ANNA VAN |
| Miscellaneous | Cleared | 11/15/2019 | ANNA VAN |
| Green Code | Cleared | 11/19/2019 | COLIN LOREDO |
| Low Impact Development | Cleared | 12/5/2019 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 12/5/2019 | THOMAS LANG |
| GPI Written Notices | Cleared | 1/16/2020 | LUKE GONZALES |
| Grading Pre-Inspection | Cleared | 1/16/2020 | LUKE GONZALES |
Contact Information
| Contractor | California Realty & Investment Group Inc; Lic. No.: 929543-B | 9215 GARNISH DR DOWNEY, CA 90240 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/19/2020 | Approved | OSVALDO PARAMO |
| Special/Order Compliance | 2/19/2020 | Partial Inspection | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2020 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 3/3/2020 | Corrections Issued | OSVALDO PARAMO |
| Insulation | 3/4/2020 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2020 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2020 | Partial Approval | OSVALDO PARAMO |
| Green Building Rough | 3/20/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 3/20/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2020 | Partial Approval | OSVALDO PARAMO |
| Green Building Rough | 4/10/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 4/10/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 5/1/2020 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 5/1/2020 | Corrections Issued | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 5/4/2020 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 5/5/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Rough | 5/5/2020 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 5/5/2020 | Approved | OSVALDO PARAMO |
| Wood Frame | 5/8/2020 | Conditional Approval | JOSEPH MCGARRY |
| Insulation | 5/11/2020 | Conditional Approval | THOMAS LOGRASSO |
| Drywall Nailing | 5/20/2020 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 5/20/2020 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 7/29/2020 | Approved | OSVALDO PARAMO |
| Gas Test | 7/29/2020 | Approved | OSVALDO PARAMO |
| HVAC-Final | 7/29/2020 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Final | 7/29/2020 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 7/30/2020 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Final | 7/30/2020 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Final | 8/3/2020 | Corrections Issued | ROBERT VORHIS |
| HVAC-Final | 8/3/2020 | Approved | ROBERT VORHIS |
| ELECTRICAL-Final | 8/10/2020 | Approved | OSVALDO PARAMO |
| Final | 8/10/2020 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 8/10/2020 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 8/10/2020 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 8/10/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 11/6/2020 | OK to Issue CofO | OSVALDO PARAMO |
| Service/Power Release | 11/6/2020 | Approved | OSVALDO PARAMO |
| Smoke Detectors | 11/6/2020 | Approved | OSVALDO PARAMO |