529-529 1/2 W 80TH ST 90044
Certificate Information: 529-529 1/2 W 80TH ST 90044
- Application / Permit
- 19010-70000-04258
- Plan Check / Job No.
- B19SL01310
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX AT MIDDLE OF LOT (BUILDING #2)
- Permit Issued
- Issued on 5/21/2020
- Issuing Office
- Current Status
- CofO Issued on 12/4/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2019 | VU NGUYEN |
| Corrections Issued | 10/17/2019 | VU NGUYEN |
| Green Plans Picked Up | 10/17/2019 | APPLICANT |
| Quality Review Completed | 10/30/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 10/31/2019 | APPLICANT |
| Plan Check Approved | 5/21/2020 | VU NGUYEN |
| Issued | 5/21/2020 | APPLICANT |
| CofO in Progress | 12/4/2020 | JOSEPH MCGARRY |
| Permit Finaled | 12/4/2020 | DEROLD HAUFF |
| CofO Issued | 12/4/2020 | DEROLD HAUFF |
| Permit Finaled | 12/4/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/25/2020 | EMIL KYUPELYAN |
| Frnt yard landscape/Water mgmt | Cleared | 2/27/2020 | SARAHI ORTEGA |
| Hydrant and Access approval | Cleared | 2/27/2020 | JOHN CONNEALLY |
| Green Code | Cleared | 3/10/2020 | DONALD CRICHLOW |
| Low Impact Development | Cleared | 4/16/2020 | JORGE MEJIA LEMUS |
| Community Plan Implem. Overlay | Cleared | 4/20/2020 | HELEN JADALI |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2020 | EMIL KYUPELYAN |
| Roof/Waste drainage to street | Cleared | 4/30/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 4/30/2020 | EMIL KYUPELYAN |
Contact Information
| Contractor | R D C S Inc; Lic. No.: 955714-B | 3006 S VERMONT AVENUE #190 LOS ANGELES, CA 90007 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
| Engineer | Shubeck,, Christopher Robert; Lic. No.: C66775 | 23705 VANOWEN ST 101 WEST HILLS, CA 91307 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/8/2020 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 6/8/2020 | Approved | EUGENE CASSIDY |
| Deputy Reinf. Concrete | 6/17/2020 | Partial Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 6/17/2020 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/17/2020 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2020 | Partial Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2020 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 8/18/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/18/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/20/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/20/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/20/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 8/20/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 8/20/2020 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/21/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 8/21/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/21/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Special/Order Compliance | 8/21/2020 | Partial Inspection | DONALD CRICHLOW |
| BUILDING-Rough-Frame | 8/26/2020 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/26/2020 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/26/2020 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/26/2020 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 8/26/2020 | Approved | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 8/26/2020 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/26/2020 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 9/1/2020 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 9/1/2020 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 11/25/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 11/25/2020 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 11/25/2020 | Approved | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 11/25/2020 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 11/25/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 11/30/2020 | Corrections Issued | DAVID FEILER |
| Gas Test | 11/30/2020 | Approved | DAVID FEILER |
| Green Building Final | 11/30/2020 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 11/30/2020 | SGSOV Approved | DAVID FEILER |
| Service/Power Release | 11/30/2020 | Not Ready for Inspection | DAVID FEILER |
| Smoke Detectors | 11/30/2020 | Approved | DAVID FEILER |
| Final | 12/3/2020 | OK to Issue CofO | JOSEPH MCGARRY |
| Service/Power Release | 12/3/2020 | Not Required | JOSEPH MCGARRY |