529-529 1/2 W 80TH ST 90044

Certificate Information: 529-529 1/2 W 80TH ST 90044

Application / Permit
19010-70000-04258
Plan Check / Job No.
B19SL01310
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2 STORY DUPLEX AT MIDDLE OF LOT (BUILDING #2)
Permit Issued
Issued on 5/21/2020
Issuing Office
Current Status
CofO Issued on 12/4/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 VU NGUYEN
Corrections Issued 10/17/2019 VU NGUYEN
Green Plans Picked Up 10/17/2019 APPLICANT
Quality Review Completed 10/30/2019 JOSE RODRIGUEZ
Building Plans Picked Up 10/31/2019 APPLICANT
Plan Check Approved 5/21/2020 VU NGUYEN
Issued 5/21/2020 APPLICANT
CofO in Progress 12/4/2020 JOSEPH MCGARRY
Permit Finaled 12/4/2020 DEROLD HAUFF
CofO Issued 12/4/2020 DEROLD HAUFF
Permit Finaled 12/4/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/25/2020 EMIL KYUPELYAN
Frnt yard landscape/Water mgmt Cleared 2/27/2020 SARAHI ORTEGA
Hydrant and Access approval Cleared 2/27/2020 JOHN CONNEALLY
Green Code Cleared 3/10/2020 DONALD CRICHLOW
Low Impact Development Cleared 4/16/2020 JORGE MEJIA LEMUS
Community Plan Implem. Overlay Cleared 4/20/2020 HELEN JADALI
Eng Process Fee Ord 176,300 Cleared 4/30/2020 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 4/30/2020 EMIL KYUPELYAN
Sewer availability Cleared 4/30/2020 EMIL KYUPELYAN

Contact Information

Contractor R D C S Inc; Lic. No.: 955714-B 3006 S VERMONT AVENUE #190      LOS ANGELES, CA 90007
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240
Engineer Shubeck,, Christopher Robert; Lic. No.: C66775 23705 VANOWEN ST 101      WEST HILLS, CA 91307

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/8/2020 Partial Approval EUGENE CASSIDY
Underground Mechanical 6/8/2020 Approved EUGENE CASSIDY
Deputy Reinf. Concrete 6/17/2020 Partial Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 6/17/2020 Approved EUGENE CASSIDY
Footing/Foundation/Slab 6/17/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 7/1/2020 Partial Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 8/5/2020 Approved FREDDIE RIVERA
ELECTRICAL-Rough 8/18/2020 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 8/18/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 8/20/2020 Conditional Approval ALEJANDRO DE ARTOLA
Green Building Rough 8/20/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
HVAC-Rough 8/20/2020 Conditional Approval ALEJANDRO DE ARTOLA
MERV13>=Rough 8/20/2020 Conditional Approval ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 8/20/2020 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 8/21/2020 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 8/21/2020 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 8/21/2020 Corrections Issued ALEJANDRO DE ARTOLA
Special/Order Compliance 8/21/2020 Partial Inspection DONALD CRICHLOW
BUILDING-Rough-Frame 8/26/2020 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 8/26/2020 Approved ALEJANDRO DE ARTOLA
Green Building Rough 8/26/2020 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 8/26/2020 Approved ALEJANDRO DE ARTOLA
Insulation 8/26/2020 Approved ALEJANDRO DE ARTOLA
MERV13>=Rough 8/26/2020 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 8/26/2020 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 9/1/2020 Approved FREDDIE RIVERA
Interior/Exterior Lathing 9/1/2020 Approved FREDDIE RIVERA
ELECTRICAL-Final 11/25/2020 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 11/25/2020 Approved ALEJANDRO DE ARTOLA
HVAC-Final 11/25/2020 Approved ALEJANDRO DE ARTOLA
MERV13>=Final 11/25/2020 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 11/25/2020 Corrections Issued ALEJANDRO DE ARTOLA
Final 11/30/2020 Corrections Issued DAVID FEILER
Gas Test 11/30/2020 Approved DAVID FEILER
Green Building Final 11/30/2020 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 11/30/2020 SGSOV Approved DAVID FEILER
Service/Power Release 11/30/2020 Not Ready for Inspection DAVID FEILER
Smoke Detectors 11/30/2020 Approved DAVID FEILER
Final 12/3/2020 OK to Issue CofO JOSEPH MCGARRY
Service/Power Release 12/3/2020 Not Required JOSEPH MCGARRY