1637-1639 W 36TH PL 90018

Certificate Information: 1637-1639 W 36TH PL 90018

Application / Permit
19010-70000-03857
Plan Check / Job No.
B19SL01183
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW THREE STORY DUPLEX WITH ATTACHED GARAGE. TYPE VB FULLY SPRINKLERED
Permit Issued
Issued on 1/8/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 11/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/30/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 RICARDO RAMIREZ
Corrections Issued 9/10/2019 RICARDO RAMIREZ
Quality Review Completed 9/12/2019 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 9/17/2019 APPLICANT
Green Plans Picked Up 10/17/2019 APPLICANT
Plan Check Approved 12/5/2019 RICARDO RAMIREZ
Issued 1/8/2020 LADBS
CofO in Progress 10/27/2021 SABAS ALONSO
Permit Finaled 11/10/2021 DEROLD HAUFF
CofO Issued 11/10/2021 DEROLD HAUFF
Permit Finaled 11/10/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/18/2019 CELINA MORENO
Hydrant and Access approval Cleared 11/18/2019 JOHN CONNEALLY
Green Code Cleared 11/26/2019 NEGAR NEJAD
Eng Process Fee Ord 176,300 Cleared 12/4/2019 JEANIE LAM
Frnt yard landscape/Water mgmt Cleared 12/4/2019 RICHARD REASER
Highway dedication Cleared 12/4/2019 JEANIE LAM
Sewer availability Cleared 12/4/2019 JEANIE LAM
ZI Cleared 12/4/2019 RICHARD REASER
Low Impact Development Cleared 12/5/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 12/5/2019 ERIK BEASLEY

Contact Information

Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045
Engineer Sanchez,, Pablo Beltran; Lic. No.: C86223 1840 S GAFFEY ST 382      SAN PEDRO, CA 90731

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/17/2020 Not Ready for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 8/17/2020 Not Ready for Inspection ENRIQUE MIRELES
METHANE-Barrier 8/17/2020 Not Ready for Inspection ENRIQUE MIRELES
METHANE-Subgrade 8/17/2020 Not Ready for Inspection ENRIQUE MIRELES
Underground Mechanical 8/17/2020 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 8/28/2020 Approved ROBERT MCDOWELL
Footing/Foundation/Slab 8/28/2020 Not Ready for Inspection ROBERT MCDOWELL
METHANE-Barrier 8/28/2020 Not Ready for Inspection ROBERT MCDOWELL
METHANE-Subgrade 8/28/2020 Approved ROBERT MCDOWELL
Footing/Foundation/Slab 9/10/2020 Approved ROBERT MCDOWELL
METHANE-Barrier 9/10/2020 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 12/9/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 12/9/2020 Approved ROBERT MCDOWELL
Green Building Rough 12/9/2020 Approved ROBERT MCDOWELL
HVAC-Rough 12/9/2020 Order to Comply Issued ROBERT MCDOWELL
Interior/Exterior Lathing 12/9/2020 Not Ready for Inspection ROBERT MCDOWELL
METHANE-Rough 12/9/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 12/9/2020 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 12/9/2020 Approved ROBERT MCDOWELL
Drywall Nailing 12/18/2020 Approved ROBERT MCDOWELL
HVAC-Rough 12/18/2020 Approved ROBERT MCDOWELL
Insulation 12/18/2020 Approved ROBERT MCDOWELL
Masonry Wall/Backfill 8/17/2021 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/15/2021 SGSOV Not Ready SABAS ALONSO
Final 9/23/2021 Not Ready for Inspection SABAS ALONSO
Green Building Final 9/23/2021 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/23/2021 SGSOV Approved SABAS ALONSO
Service/Power Release 9/23/2021 Approved SABAS ALONSO
Smoke Detectors 9/23/2021 Approved SABAS ALONSO
Final 10/27/2021 OK to Issue CofO SABAS ALONSO