1637-1639 W 36TH PL 90018
Certificate Information: 1637-1639 W 36TH PL 90018
- Application / Permit
- 19010-70000-03857
- Plan Check / Job No.
- B19SL01183
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW THREE STORY DUPLEX WITH ATTACHED GARAGE. TYPE VB FULLY SPRINKLERED
- Permit Issued
- Issued on 1/8/2020
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 11/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2019 | RICARDO RAMIREZ |
| Corrections Issued | 9/10/2019 | RICARDO RAMIREZ |
| Quality Review Completed | 9/12/2019 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 9/17/2019 | APPLICANT |
| Green Plans Picked Up | 10/17/2019 | APPLICANT |
| Plan Check Approved | 12/5/2019 | RICARDO RAMIREZ |
| Issued | 1/8/2020 | LADBS |
| CofO in Progress | 10/27/2021 | SABAS ALONSO |
| Permit Finaled | 11/10/2021 | DEROLD HAUFF |
| CofO Issued | 11/10/2021 | DEROLD HAUFF |
| Permit Finaled | 11/10/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/18/2019 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 11/18/2019 | JOHN CONNEALLY |
| Green Code | Cleared | 11/26/2019 | NEGAR NEJAD |
| Eng Process Fee Ord 176,300 | Cleared | 12/4/2019 | JEANIE LAM |
| Frnt yard landscape/Water mgmt | Cleared | 12/4/2019 | RICHARD REASER |
| Highway dedication | Cleared | 12/4/2019 | JEANIE LAM |
| Sewer availability | Cleared | 12/4/2019 | JEANIE LAM |
| ZI | Cleared | 12/4/2019 | RICHARD REASER |
| Low Impact Development | Cleared | 12/5/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 12/5/2019 | ERIK BEASLEY |
Contact Information
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
| Engineer | Sanchez,, Pablo Beltran; Lic. No.: C86223 | 1840 S GAFFEY ST 382 SAN PEDRO, CA 90731 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/17/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/17/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| METHANE-Barrier | 8/17/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| METHANE-Subgrade | 8/17/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Underground Mechanical | 8/17/2020 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 8/28/2020 | Approved | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 8/28/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| METHANE-Barrier | 8/28/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| METHANE-Subgrade | 8/28/2020 | Approved | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 9/10/2020 | Approved | ROBERT MCDOWELL |
| METHANE-Barrier | 9/10/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 12/9/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 12/9/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 12/9/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 12/9/2020 | Order to Comply Issued | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 12/9/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| METHANE-Rough | 12/9/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 12/9/2020 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 12/9/2020 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 12/18/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 12/18/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 12/18/2020 | Approved | ROBERT MCDOWELL |
| Masonry Wall/Backfill | 8/17/2021 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/15/2021 | SGSOV Not Ready | SABAS ALONSO |
| Final | 9/23/2021 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 9/23/2021 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/23/2021 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 9/23/2021 | Approved | SABAS ALONSO |
| Smoke Detectors | 9/23/2021 | Approved | SABAS ALONSO |
| Final | 10/27/2021 | OK to Issue CofO | SABAS ALONSO |