6341 S ARLINGTON AVE 90043
Certificate Information: 6341 S ARLINGTON AVE 90043
- Application / Permit
- 19010-70000-03822
- Plan Check / Job No.
- B19SL01165
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 CAR GARAGE AND ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 ON SECOND STORY
- Permit Issued
- Issued on 12/10/2019
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 1/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2019 | APPLICANT |
| Green Plans Picked Up | 9/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2019 | SAMUEL GONZALEZ |
| Corrections Issued | 9/16/2019 | SAMUEL GONZALEZ |
| Quality Review Completed | 9/20/2019 | QUAN NGHIEM |
| Building Plans Picked Up | 9/27/2019 | APPLICANT |
| Plan Check Approved | 12/6/2019 | SAMUEL GONZALEZ |
| Issued | 12/10/2019 | LADBS |
| CofO in Progress | 12/24/2020 | FREDDIE RIVERA |
| Permit Finaled | 1/23/2021 | DEROLD HAUFF |
| CofO Issued | 1/23/2021 | DEROLD HAUFF |
| Permit Finaled | 1/23/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/2/2019 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 12/4/2019 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 12/4/2019 | MITESH PATEL |
| Construction near power lines | Cleared | 12/5/2019 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2019 | JEANIE LAM |
| Green Code | Cleared | 12/6/2019 | VIVIAN LAO |
| Roof/Waste drainage to street | Cleared | 12/6/2019 | JEANIE LAM |
| Sewer availability | Cleared | 12/6/2019 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/2/2020 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/2/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 1/8/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/8/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 1/14/2020 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/14/2020 | Approved | FREDDIE RIVERA |
| Wood Frame | 1/23/2020 | Partial Approval | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2020 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 2/13/2020 | Approved | FREDDIE RIVERA |
| Sewer | 2/13/2020 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/11/2020 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 3/11/2020 | Approved | FREDDIE RIVERA |
| Green Building Rough | 3/11/2020 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 3/11/2020 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 3/11/2020 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 3/26/2020 | Approved | COREY HUPP |
| PLUMBING-Rough | 3/26/2020 | Not Ready for Inspection | COREY HUPP |
| Wood Frame | 3/26/2020 | Not Ready for Inspection | COREY HUPP |
| Interior/Exterior Lathing | 4/1/2020 | Partial Approval | SABAS ALONSO |
| Green Building Rough | 4/6/2020 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 4/6/2020 | Approved | FREDDIE RIVERA |
| Insulation | 4/9/2020 | Approved | SABAS ALONSO |
| Drywall Nailing | 4/23/2020 | Conditional Approval | SABAS ALONSO |
| Shower Pan | 5/26/2020 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 5/26/2020 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 7/20/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 7/20/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 7/20/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 7/20/2020 | SGSOV No Gas | HAMIK HARTOUNIAN |
| Service/Power Release | 7/20/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 7/20/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 9/8/2020 | Conditional Approval | FREDDIE RIVERA |
| Green Building Final | 9/8/2020 | Approved | FREDDIE RIVERA |
| Service/Power Release | 9/8/2020 | Approved | FREDDIE RIVERA |
| Final | 9/9/2020 | Corrections Issued | FREDDIE RIVERA |