3677-3679 S HALLDALE AVE 90018

Certificate Information: 3677-3679 S HALLDALE AVE 90018

Application / Permit
19010-70000-03771
Plan Check / Job No.
B19SL01147
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX WITH ATTACHED GARAGE.
Permit Issued
Issued on 2/24/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 9/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 SALVADOR QUINTANILLA
Corrections Issued 9/9/2019 SALVADOR QUINTANILLA
Quality Review Completed 9/16/2019 GARO TELMI
Green Plans Picked Up 10/17/2019 APPLICANT
Building Plans Picked Up 10/18/2019 APPLICANT
Applicant returned to address corrections 2/11/2020 SALVADOR QUINTANILLA
Plan Check Approved 2/13/2020 SALVADOR QUINTANILLA
Issued 2/24/2020 LADBS
CofO in Progress 7/12/2021 HORACE FULTZ
Permit Finaled 9/16/2021 DEROLD HAUFF
CofO Issued 9/16/2021 DEROLD HAUFF
Permit Finaled 9/16/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/18/2019 CELINA MORENO
Permit Cleared 10/18/2019 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/27/2019 CELINA MORENO
Sewer availability Cleared 12/27/2019 CELINA MORENO
Green Code Cleared 1/28/2020 COLIN LOREDO
Hydrant and Access approval Cleared 1/28/2020 ROBERT DUFF
Low Impact Development Cleared 2/6/2020 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 2/6/2020 JEANETTE VONG

Contact Information

Engineer Nuno,, Arnulfo; Lic. No.: C88425 7057 DWIGHT WAY      SAN BERNARDINO, CA 92404
Engineer Sanchez,, Pablo Beltran; Lic. No.: C86223 1840 S GAFFEY ST 382      SAN PEDRO, CA 90731

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/26/2020 Corrections Issued JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 4/1/2020 Approved DAVID CHAN
Footing/Foundation/Slab 4/1/2020 Approved DAVID CHAN
METHANE-Barrier 4/1/2020 Approved DAVID CHAN
METHANE-Subgrade 4/1/2020 Approved DAVID CHAN
Underground Mechanical 4/1/2020 Approved DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 5/5/2020 Partial Approval ROBERT MCDOWELL
BUILDING-Rough-Frame 6/23/2020 Corrections Issued ROBERT MCDOWELL
ELECTRICAL-Rough 6/23/2020 Corrections Issued ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 6/23/2020 Approved ROBERT MCDOWELL
HVAC-Rough 6/23/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 6/23/2020 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 6/30/2020 Approved ROBERT MCDOWELL
Green Building Rough 6/30/2020 Approved ROBERT MCDOWELL
METHANE-Rough 6/30/2020 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 6/30/2020 Approved ROBERT MCDOWELL
Wood Frame 6/30/2020 Approved ROBERT MCDOWELL
Drywall Nailing 7/13/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 7/13/2020 Approved ROBERT MCDOWELL
Insulation 7/13/2020 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 7/13/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Final 8/25/2020 Approved ROBERT MCDOWELL
Gas Test 8/25/2020 Approved ROBERT MCDOWELL
PLUMBING-Final 8/25/2020 Approved ROBERT MCDOWELL
Final 8/28/2020 OK to Issue CofO ROBERT MCDOWELL
Green Building Final 8/28/2020 Approved ROBERT MCDOWELL
HVAC-Final 8/28/2020 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 8/28/2020 SGSOV Approved ROBERT MCDOWELL
Service/Power Release 8/28/2020 Approved ROBERT MCDOWELL
Smoke Detectors 8/28/2020 Approved ROBERT MCDOWELL
Service/Power Release 9/4/2020 Approved ROBERT MCDOWELL
Final 7/8/2021 Not Ready for Inspection JOAQUIN GREENOUGH