11320 W MIRANDA ST 91601
Certificate Information: 11320 W MIRANDA ST 91601
- Application / Permit
- 19010-70000-03617
- Plan Check / Job No.
- B19SL01095
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3 STORY SFD WITH ATTACHED GARAGE AT REAR OF LOT ( 3 OF 3 )
- Permit Issued
- Issued on 1/22/2020
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 12/8/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2019 | LUKE GONZALES |
| Corrections Issued | 9/5/2019 | LUKE GONZALES |
| Quality Review Completed | 9/6/2019 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 9/11/2019 | APPLICANT |
| Green Plans Picked Up | 9/11/2019 | APPLICANT |
| Plan Check Approved | 1/13/2020 | LUKE GONZALES |
| Issued | 1/22/2020 | LADBS |
| CofO in Progress | 11/4/2020 | DANIEL DREW |
| CofO Issued | 12/8/2020 | MICHAEL SMITH |
| Permit Finaled | 12/8/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/4/2019 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 10/4/2019 | ELAINE LEI |
| Highway dedication | Cleared | 10/4/2019 | ELAINE LEI |
| Project located in CRA area | Cleared | 10/4/2019 | JIM URQUHART |
| Sewer availability | Cleared | 10/4/2019 | ELAINE LEI |
| Green Code | Cleared | 10/22/2019 | COLIN LOREDO |
| ZI | Cleared | 10/22/2019 | ANNA VAN |
| Hydrant and Access approval | Cleared | 11/5/2019 | JEREMY CARTER |
| Low Impact Development | Cleared | 12/13/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 12/13/2019 | CELINA MORENO |
Contact Information
| Contractor | New World Construction; Lic. No.: 864461-B | 838 E 93RD STREET LOS ANGELES, CA 90002 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
| Engineer | Shubeck,, Robert James; Lic. No.: GE773 | 60 HACKAMORE LANE BELL CANYON, CA 91307 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/25/2020 | Approved | RAYMOND KEHOE |
| Excavation/Setback/Form/Re-Bar | 3/9/2020 | Approved | RAYMOND KEHOE |
| Footing/Foundation/Slab | 3/9/2020 | Approved | RAYMOND KEHOE |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2020 | Partial Approval | RAYMOND KEHOE |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2020 | Partial Approval | RAYMOND KEHOE |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2020 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2020 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 6/5/2020 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 6/5/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2020 | Partial Approval | DANIEL DREW |
| Rough-Elec/Plmb/HVAC | 6/12/2020 | Corrections Issued | BEAU COLLINS |
| BUILDING-Rough-Frame | 6/23/2020 | Approved | RAYMOND KEHOE |
| Green Building Rough | 6/23/2020 | Approved | RAYMOND KEHOE |
| Verify Sprinkler Sign Off | 6/23/2020 | Approved | RAYMOND KEHOE |
| Insulation | 6/25/2020 | Approved | RAYMOND KEHOE |
| Interior/Exterior Lathing | 6/25/2020 | Partial Approval | RAYMOND KEHOE |
| Drywall Nailing | 7/2/2020 | Approved | RAYMOND KEHOE |
| Rough-Elec/Plmb/HVAC | 7/9/2020 | Approved | RAYMOND KEHOE |
| ELECTRICAL-Final | 10/22/2020 | Approved | DANIEL DREW |
| Final | 10/22/2020 | Corrections Issued | DANIEL DREW |
| Gas Test | 10/22/2020 | Approved | DANIEL DREW |
| Green Building Final | 10/22/2020 | Approved | DANIEL DREW |
| HVAC-Final | 10/22/2020 | Approved | DANIEL DREW |
| PLUMBING-Final | 10/22/2020 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 10/22/2020 | SGSOV Approved | DANIEL DREW |
| Service/Power Release | 10/22/2020 | Not Ready for Inspection | DANIEL DREW |
| Smoke Detectors | 10/22/2020 | Approved | DANIEL DREW |
| Final | 10/29/2020 | No Access for Inspection | DANIEL DREW |
| Service/Power Release | 10/29/2020 | No Access for Inspection | DANIEL DREW |
| Final | 11/2/2020 | OK to Issue CofO | DANIEL DREW |
| Service/Power Release | 11/2/2020 | Approved | DANIEL DREW |