5730-5732 S VAN NESS AVE 90062
Certificate Information: 5730-5732 S VAN NESS AVE 90062
- Application / Permit
- 19010-70000-03578
- Plan Check / Job No.
- B19SL01088
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- INTERIOR REMODEL TO (E) UNIT FIRST FLOOR AND 2ND FLOOR ADDITION TO CREATE A 2ND UNIT. NEW ATTACHED 2-CAR GARAGE AT REAR.
- Permit Issued
- Issued on 12/20/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2019 | SAMUEL GONZALEZ |
| Corrections Issued | 9/10/2019 | SAMUEL GONZALEZ |
| Quality Review Completed | 9/12/2019 | QUAN NGHIEM |
| Green Plans Picked Up | 9/13/2019 | APPLICANT |
| Building Plans Picked Up | 9/17/2019 | APPLICANT |
| Plan Check Approved | 11/20/2019 | SAMUEL GONZALEZ |
| Issued | 12/20/2019 | LADBS |
| CofO in Progress | 10/7/2021 | HORACE FULTZ |
| Permit Finaled | 6/16/2022 | DEROLD HAUFF |
| CofO Issued | 6/16/2022 | DEROLD HAUFF |
| Permit Finaled | 6/16/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/19/2019 | JEANETTE VONG |
| Community Plan Implem. Overlay | Cleared | 9/19/2019 | DIANA JIMENEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 10/7/2019 | ERIK BEASLEY |
| Green Code | Cleared | 11/5/2019 | VIVIAN LAO |
| Low Impact Development | Cleared | 11/13/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/13/2019 | EMIL KYUPELYAN |
Contact Information
| Contractor | Frost Construction; Lic. No.: 580847-B | 1041 WEST 105TH STREET LOS ANGELES, CA 90044 |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/3/2020 | Conditional Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2020 | Partial Approval | ROBERT MCDOWELL |
| Green Building Rough | 2/28/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| PLUMBING-Rough | 2/28/2020 | Partial Approval | ROBERT MCDOWELL |
| Underground Mechanical | 2/28/2020 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2020 | Partial Approval | FREDDIE RIVERA |
| Insulation | 3/4/2020 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2020 | Partial Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2020 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 5/11/2020 | Corrections Issued | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 5/11/2020 | Corrections Issued | ROBERT MCDOWELL |
| Green Building Rough | 5/11/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| HVAC-Rough | 5/11/2020 | Corrections Issued | ROBERT MCDOWELL |
| PLUMBING-Rough | 5/11/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 6/17/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 6/17/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 6/17/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| HVAC-Rough | 6/17/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 6/17/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 6/23/2020 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 6/23/2020 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 6/25/2020 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 7/2/2020 | Approved | SABAS ALONSO |
| Green Building Rough | 7/2/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 7/2/2020 | Partial Approval | SABAS ALONSO |
| Shower Pan | 8/18/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 7/1/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 7/1/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 7/1/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Final | 7/1/2021 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Final | 7/1/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 7/1/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 7/1/2021 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 7/1/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 9/21/2021 | Approved | SABAS ALONSO |
| Final | 9/21/2021 | OK to Issue CofO | SABAS ALONSO |
| Footing/Foundation/Slab | 9/21/2021 | Approved | SABAS ALONSO |
| Green Building Final | 9/21/2021 | Approved | SABAS ALONSO |
| HVAC-Final | 9/21/2021 | Approved | SABAS ALONSO |
| PLUMBING-Final | 9/21/2021 | Approved | SABAS ALONSO |
| Service/Power Release | 9/21/2021 | Approved | SABAS ALONSO |