834 E 102ND ST 90002

Certificate Information: 834 E 102ND ST 90002

Application / Permit
19010-70000-03299
Plan Check / Job No.
B19SL01021
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER AB 494 AND SB 229
Permit Issued
Issued on 7/17/2020
Issuing Office
Metro
Current Status
CofO Issued on 7/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2019 APPLICANT
Assigned to Plan Check Engineer 8/8/2019 LUKE GONZALES
Corrections Issued 8/13/2019 LUKE GONZALES
Quality Review Completed 8/15/2019 TEODORO DIAZ RODRIGUEZ
Green Plans Picked Up 9/4/2019 APPLICANT
Applicant returned to address corrections 4/17/2020 LUKE GONZALES
Applicant returned to address corrections 5/5/2020 LUKE GONZALES
Plan Check Approved 5/21/2020 LUKE GONZALES
Issued 7/17/2020 APPLICANT
CofO in Progress 6/21/2021 EUGENE CASSIDY
CofO Issued 7/1/2021 DEROLD HAUFF
Permit Finaled 7/1/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/4/2019 JEANETTE VONG
ZI Cleared 9/5/2019 JOE LUCKEY
Green Code Cleared 11/6/2019 LUKE GONZALES
Construction near power lines Cleared 1/11/2020 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 3/6/2020 ELAINE LEI
Hydrant and Access approval Cleared 3/6/2020 ROBERT DUFF
Low Impact Development Cleared 3/6/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 3/6/2020 ELAINE LEI
Sewer availability Cleared 5/6/2020 WALLIE JONG

Contact Information

Contractor Orendain Building Contracting Corp; Lic. No.: 1036707-B 650 S 4TH AVE      LA PUENTE, CA 91746
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/5/2020 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 8/10/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/21/2020 Partial Approval EUGENE CASSIDY
Green Building Rough 8/21/2020 Not Ready for Inspection EUGENE CASSIDY
Underground Mechanical 8/21/2020 Partial Approval EUGENE CASSIDY
Verify Sprinkler Sign Off 8/21/2020 Approved EUGENE CASSIDY
Insulation 8/26/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 9/1/2020 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 10/5/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/5/2020 Partial Approval EUGENE CASSIDY
Gas Test 10/5/2020 Approved EUGENE CASSIDY
HVAC-Rough 10/5/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 10/5/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 11/4/2020 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/4/2020 Approved EUGENE CASSIDY
Green Building Rough 11/4/2020 Not Ready for Inspection EUGENE CASSIDY
Deputy Wood Construction 11/5/2020 No Access for Inspection ELMER BLAND
Shower Pan 11/5/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 11/13/2020 Approved EUGENE CASSIDY
Green Building Rough 11/13/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 11/13/2020 Approved EUGENE CASSIDY
Wood Frame 11/13/2020 Approved EUGENE CASSIDY
Insulation 11/17/2020 Approved ANSON MAGLASANG
Drywall Nailing 11/24/2020 Approved EUGENE CASSIDY
ELECTRICAL-Final 2/26/2021 Corrections Issued EUGENE CASSIDY
Final 2/26/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 2/26/2021 Approved EUGENE CASSIDY
Green Building Final 2/26/2021 Corrections Issued EUGENE CASSIDY
HVAC-Final 2/26/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 2/26/2021 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/26/2021 SGSOV Approved EUGENE CASSIDY
Service/Power Release 2/26/2021 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 2/26/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 3/17/2021 Corrections Issued EUGENE CASSIDY
Gas Test 3/17/2021 Approved EUGENE CASSIDY
HVAC-Final 3/17/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Final 3/17/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 4/9/2021 Approved EUGENE CASSIDY
Final 4/9/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 4/9/2021 Approved EUGENE CASSIDY
HVAC-Final 4/9/2021 Approved EUGENE CASSIDY
PLUMBING-Final 4/9/2021 Approved EUGENE CASSIDY
Service/Power Release 4/9/2021 Not Ready for Inspection EUGENE CASSIDY
Final 4/29/2021 OK to Issue CofO EUGENE CASSIDY
Service/Power Release 4/29/2021 Approved EUGENE CASSIDY