10817 W PEACH GROVE ST 91601

Certificate Information: 10817 W PEACH GROVE ST 91601

Application / Permit
19010-70000-03112
Plan Check / Job No.
B19SL00950
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW THREE STORY DUPLEX WITH ATTACHED CARPORT
Permit Issued
Issued on 8/6/2020
Issuing Office
Metro
Current Status
CofO Issued on 3/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2019 APPLICANT
Assigned to Plan Check Engineer 8/15/2019 MANUEL MONTUFAR
Corrections Issued 8/20/2019 MANUEL MONTUFAR
Quality Review Completed 8/26/2019 KESETE HAREGOT
Green Plans Picked Up 8/26/2019 APPLICANT
Plan Check Approved 1/29/2020 MANUEL MONTUFAR
Issued 8/6/2020 APPLICANT
CofO in Progress 1/25/2022 MATT KELLERMAN
Permit Finaled 3/23/2022 RONALD MYRICK
CofO Issued 3/23/2022 RONALD MYRICK
Permit Finaled 3/23/2022 RONALD MYRICK

Permit Application Clearance Information

Green Code Cleared 12/5/2019 SARAH ABOULHOSN
Hydrant and Access approval Cleared 12/10/2019 ROBERT DUFF
Address approval Cleared 12/19/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 12/19/2019 ERIK BEASLEY
Low Impact Development Cleared 12/19/2019 AMMAR ELTAWIL
Permit Cleared 12/19/2019 ERIK BEASLEY
Roof/Waste drainage to street Cleared 12/19/2019 ERIK BEASLEY
Sewer availability Cleared 12/19/2019 ERIK BEASLEY
Frnt yard landscape/Water mgmt Cleared 12/20/2019 TERRI OSBORNE
Trees in Parkway Cleared 1/3/2020 JOHN KIM

Contact Information

Architect Tavasci,, Robert J; Lic. No.: C26023 3351 ORANGEWOOD AVENUE      ROSSMOOR, CA 90720
Contractor Legaspi Jose Luis; Lic. No.: 1064179-B 1863 GARDENIA AVE      LONG BEACH, CA 90806
Engineer Saleh,, Zouheir Toufic; Lic. No.: C42881 1304 CORTE MALTERA      COSTA MESA, CA 92626

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/13/2020 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 8/20/2020 Not Ready for Inspection THOMAS FINNILA
Underground Mechanical 8/20/2020 Partial Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 8/25/2020 No Access for Inspection THOMAS FINNILA
Footing/Foundation/Slab 9/16/2020 Corrections Issued THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 9/22/2020 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/22/2020 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/18/2020 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/18/2020 Conditional Approval BEAU COLLINS
PLUMBING-Rough 2/24/2021 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 3/2/2021 Approved THOMAS FINNILA
HVAC-Rough 4/5/2021 Corrections Issued DAVID MATSON
ELECTRICAL-Rough 4/14/2021 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 4/20/2021 Corrections Issued THOMAS FINNILA
HVAC-Rough 4/20/2021 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 4/27/2021 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/27/2021 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/4/2021 Partial Approval THOMAS FINNILA
Green Building Rough 5/4/2021 Not Ready for Inspection THOMAS FINNILA
Verify Sprinkler Sign Off 5/4/2021 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 5/11/2021 Partial Inspection THOMAS FINNILA
Insulation 5/14/2021 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 5/14/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 5/17/2021 Conditional Approval THOMAS FINNILA
Green Building Rough 5/17/2021 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 5/17/2021 Approved THOMAS FINNILA
Insulation 5/26/2021 Approved THOMAS FINNILA
Interior/Exterior Lathing 5/26/2021 Partial Approval THOMAS FINNILA
Drywall Nailing 6/14/2021 Approved THOMAS FINNILA
Interior/Exterior Lathing 6/14/2021 Approved THOMAS FINNILA
Sewer 8/18/2021 Approved LILIANA PORTILLO
ELECTRICAL-Final 12/3/2021 Conditional Approval THOMAS FINNILA
HVAC-Final 12/22/2021 Corrections Issued CALEB MEISTER
PLUMBING-Final 12/22/2021 Partial Inspection CALEB MEISTER
BUILDING-Rough-Frame 1/3/2022 Approved THOMAS FINNILA
Final 1/3/2022 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 1/3/2022 Approved THOMAS FINNILA
HVAC-Final 1/7/2022 Not Ready for Inspection MATT KELLERMAN
PLUMBING-Final 1/7/2022 Approved MATT KELLERMAN
Special/Order Compliance 1/7/2022 Partial Inspection CALEB MEISTER
Green Building Final 1/10/2022 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 1/10/2022 SGSOV Approved THOMAS FINNILA
Smoke Detectors 1/10/2022 Approved THOMAS FINNILA
Final 1/14/2022 Not Ready for Inspection THOMAS FINNILA
Service/Power Release 1/14/2022 Not Ready for Inspection THOMAS FINNILA
Service/Power Release 1/20/2022 Corrections Issued MISAEL ESPARZA
Final 1/24/2022 Conditional Approval MATT KELLERMAN
Final 2/17/2022 Conditional Approval MATT KELLERMAN
Service/Power Release 2/17/2022 Approved MATT KELLERMAN