3552 E 7TH ST 90023

Certificate Information: 3552 E 7TH ST 90023

Application / Permit
19010-70000-02973
Plan Check / Job No.
B19SL00916
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY SINGLE FAMILY DWELLINF AT FRONT OF LOT( 1 OF 3 ) NFPA-13 R System require.
Permit Issued
Issued on 2/4/2021
Issuing Office
Current Status
CofO Issued on 4/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2019 APPLICANT
Assigned to Plan Check Engineer 8/1/2019 ZAW HAN
Corrections Issued 8/5/2019 ZAW HAN
Quality Review Completed 8/15/2019 HERNAN ARREOLA
Green Plans Picked Up 4/1/2020 APPLICANT
Applicant returned to address corrections 10/2/2020 ZAW HAN
Applicant returned to address corrections 11/10/2020 ZAW HAN
Plan Check Approved 11/12/2020 ZAW HAN
Issued 2/4/2021 APPLICANT
Building Plans Picked Up 3/18/2021 APPLICANT
CofO in Progress 4/5/2022 KATHRYN BUTTERWORTH
Permit Finaled 4/13/2022 DEROLD HAUFF
CofO Issued 4/13/2022 DEROLD HAUFF
Permit Finaled 4/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Clean Up Green Up Cleared 2/24/2020 ANNA VIDAL
Permit Cleared 2/24/2020 CELINA MORENO
Address approval Cleared 2/25/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 2/25/2020 THOMAS LANG
Sewer availability Cleared 2/25/2020 THOMAS LANG
Frnt yard landscape/Water mgmt Cleared 3/18/2020 KENTON TRINH
Green Code Cleared 4/1/2020 ZAW HAN
Low Impact Development Cleared 4/16/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 4/24/2020 JUAN ASHTON
Hydrant and Access approval Cleared 10/8/2020 MATTHEW CRAIG

Contact Information

Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/19/2021 Not Ready for Inspection ROBERT VORHIS
Underground Mechanical 3/19/2021 Partial Inspection ROBERT VORHIS
Footing/Foundation/Slab 3/30/2021 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 4/8/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 4/13/2021 Not Ready for Inspection ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 5/11/2021 Corrections Issued ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 5/18/2021 Not Ready for Inspection ROBERT VORHIS
HVAC-Rough 5/18/2021 Not Ready for Inspection ROBERT VORHIS
PLUMBING-Rough 5/18/2021 Not Ready for Inspection ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 5/24/2021 Approved OSVALDO PARAMO
HVAC-Rough 5/24/2021 Corrections Issued OSVALDO PARAMO
BUILDING-Rough-Frame 6/25/2021 Not Ready for Inspection OSVALDO PARAMO
Green Building Rough 6/25/2021 Not Ready for Inspection OSVALDO PARAMO
MERV13>=Rough 6/25/2021 Approved OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 6/25/2021 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 6/25/2021 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 7/15/2021 Corrections Issued ROBERT VORHIS
Green Building Rough 7/15/2021 Not Ready for Inspection ROBERT VORHIS
Verify Sprinkler Sign Off 7/15/2021 Not Ready for Inspection ROBERT VORHIS
BUILDING-Rough-Frame 7/16/2021 Approved ROBERT VORHIS
Green Building Rough 7/16/2021 Approved ROBERT VORHIS
Interior/Exterior Lathing 7/16/2021 Partial Approval ROBERT VORHIS
Verify Sprinkler Sign Off 7/16/2021 Approved ROBERT VORHIS
Insulation 7/23/2021 Approved ROBERT VORHIS
Drywall Nailing 7/30/2021 Approved ROBERT VORHIS
Interior/Exterior Lathing 7/30/2021 Approved ROBERT VORHIS
Gas Test 9/22/2021 Not Ready for Inspection ROBERT VORHIS
Sewer 9/22/2021 Approved ROBERT VORHIS
Underground Mechanical 9/22/2021 Approved ROBERT VORHIS
Gas Test 9/29/2021 Approved ROBERT VORHIS
ELECTRICAL-Final 1/18/2022 Approved ALIZAH MAYAGOITIA
Gas Test 1/18/2022 Approved ALIZAH MAYAGOITIA
HVAC-Final 1/24/2022 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Final 1/24/2022 Approved JOAQUIN GREENOUGH
Final 1/26/2022 Corrections Issued ADAM ESCOTO
Green Building Final 1/26/2022 Not Ready for Inspection ADAM ESCOTO
HVAC-Final 1/26/2022 Not Ready for Inspection ADAM ESCOTO
MERV13>=Final 1/26/2022 Not Ready for Inspection ADAM ESCOTO
PLUMBING-Final 1/26/2022 Not Ready for Inspection ADAM ESCOTO
SGSOV-Seismic Gas S/O Valve 1/26/2022 SGSOV Not Ready ADAM ESCOTO
Service/Power Release 1/26/2022 Not Ready for Inspection ADAM ESCOTO
Smoke Detectors 1/26/2022 Not Ready for Inspection ADAM ESCOTO
Final 3/22/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Gas Test 3/22/2022 Approved KATHRYN BUTTERWORTH
Green Building Final 3/22/2022 Approved KATHRYN BUTTERWORTH
HVAC-Final 3/22/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
MERV13>=Final 3/22/2022 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 3/22/2022 SGSOV Approved KATHRYN BUTTERWORTH
Smoke Detectors 3/22/2022 Approved KATHRYN BUTTERWORTH
Final 3/25/2022 Corrections Issued KATHRYN BUTTERWORTH
Service/Power Release 4/1/2022 Approved KATHRYN BUTTERWORTH
Final 4/6/2022 OK to Issue CofO KATHRYN BUTTERWORTH