Deputy Grading
|
6/29/2020
|
Partial Approval
|
OSVALDO PARAMO
|
|
Deputy Grading
|
7/1/2020
|
Partial Approval
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
7/1/2020
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Pre-Inspection
|
7/1/2020
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
7/9/2020
|
Partial Approval
|
OSVALDO PARAMO
|
|
Piling/Pier/Caisson
|
7/9/2020
|
Partial Approval
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
7/15/2020
|
Partial Approval
|
OSVALDO PARAMO
|
|
Piling/Pier/Caisson
|
7/15/2020
|
Approved
|
OSVALDO PARAMO
|
|
Special/Order Compliance
|
7/29/2020
|
Approved
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
8/10/2020
|
Corrections Issued
|
OSVALDO PARAMO
|
|
Footing/Foundation/Slab
|
8/10/2020
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
8/11/2020
|
Partial Approval
|
RUBEN SALAS
|
|
Deputy Reinf. Concrete
|
8/14/2020
|
Partial Approval
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
9/1/2020
|
Partial Approval
|
OSVALDO PARAMO
|
|
Underground Mechanical
|
9/21/2020
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Wood Frame
|
9/21/2020
|
Partial Approval
|
OSVALDO PARAMO
|
|
PLUMBING-Rough
|
9/22/2020
|
Partial Approval
|
OSVALDO PARAMO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/23/2020
|
Partial Approval
|
OSVALDO PARAMO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/25/2020
|
Partial Approval
|
OSVALDO PARAMO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/24/2020
|
Partial Approval
|
FREDDIE RIVERA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/2/2020
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/9/2020
|
Partial Approval
|
OSVALDO PARAMO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/30/2020
|
No Access for Inspection
|
OSVALDO PARAMO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/6/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/7/2021
|
Approved
|
OSVALDO PARAMO
|
|
BUILDING-Rough-Frame
|
1/11/2021
|
Corrections Issued
|
RUBEN SALAS
|
|
HVAC-Rough
|
1/11/2021
|
Approved
|
RUBEN SALAS
|
|
ELECTRICAL-Rough
|
1/12/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
ELECTRICAL-Rough
|
1/14/2021
|
Corrections Issued
|
OSVALDO PARAMO
|
|
PLUMBING-Rough
|
1/15/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
ELECTRICAL-Rough
|
1/20/2021
|
Approved
|
OSVALDO PARAMO
|
|
PLUMBING-Rough
|
1/20/2021
|
Corrections Issued
|
OSVALDO PARAMO
|
|
BUILDING-Rough-Frame
|
1/25/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Green Building Rough
|
1/25/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
PLUMBING-Rough
|
1/25/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Verify Sprinkler Sign Off
|
1/25/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Interior/Exterior Lathing
|
2/2/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
PLUMBING-Rough
|
2/2/2021
|
Approved
|
OSVALDO PARAMO
|
|
Wood Frame
|
2/2/2021
|
Approved
|
OSVALDO PARAMO
|
|
BUILDING-Rough-Frame
|
2/3/2021
|
Approved
|
OSVALDO PARAMO
|
|
Green Building Rough
|
2/3/2021
|
Approved
|
OSVALDO PARAMO
|
|
Interior/Exterior Lathing
|
2/3/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Verify Sprinkler Sign Off
|
2/3/2021
|
Approved
|
OSVALDO PARAMO
|
|
Interior/Exterior Lathing
|
2/4/2021
|
Approved
|
OSVALDO PARAMO
|
|
Shower Pan
|
2/4/2021
|
Approved
|
OSVALDO PARAMO
|
|
Interior/Exterior Lathing
|
2/5/2021
|
Approved
|
OSVALDO PARAMO
|
|
Insulation
|
2/8/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Insulation
|
2/9/2021
|
Approved
|
OSVALDO PARAMO
|
|
Drywall Nailing
|
2/12/2021
|
Approved
|
OSVALDO PARAMO
|
|
Special/Order Compliance
|
2/17/2021
|
Approved
|
THOMAS LOGRASSO
|
|
Special/Order Compliance
|
2/24/2021
|
Approved
|
OSVALDO PARAMO
|
|
Gas Test
|
4/5/2021
|
No Access for Inspection
|
OSVALDO PARAMO
|
|
HVAC-Final
|
6/10/2021
|
Not Ready for Inspection
|
COREY HUPP
|
|
ELECTRICAL-Final
|
6/11/2021
|
Corrections Issued
|
OSVALDO PARAMO
|
|
Gas Test
|
6/14/2021
|
Approved
|
OSVALDO PARAMO
|
|
PLUMBING-Final
|
6/14/2021
|
Approved
|
OSVALDO PARAMO
|
|
HVAC-Final
|
6/17/2021
|
Corrections Issued
|
OSVALDO PARAMO
|
|
ELECTRICAL-Final
|
6/22/2021
|
Approved
|
OSVALDO PARAMO
|
|
HVAC-Final
|
6/22/2021
|
Approved
|
OSVALDO PARAMO
|
|
Final
|
6/23/2021
|
Corrections Issued
|
OSVALDO PARAMO
|
|
Footing/Foundation/Slab
|
6/23/2021
|
Approved
|
OSVALDO PARAMO
|
|
Green Building Final
|
6/23/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
SGSOV-Seismic Gas S/O Valve
|
6/23/2021
|
SGSOV Not Ready
|
OSVALDO PARAMO
|
|
Service/Power Release
|
6/23/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Smoke Detectors
|
6/23/2021
|
Approved
|
OSVALDO PARAMO
|
|
Final
|
1/11/2022
|
Corrections Issued
|
OSVALDO PARAMO
|
|
Green Building Final
|
1/11/2022
|
Approved
|
OSVALDO PARAMO
|
|
SGSOV-Seismic Gas S/O Valve
|
1/11/2022
|
SGSOV Not Ready
|
OSVALDO PARAMO
|
|
Service/Power Release
|
1/11/2022
|
Approved
|
OSVALDO PARAMO
|
|
Final
|
1/13/2022
|
Conditional Approval
|
OSVALDO PARAMO
|
|
SGSOV-Seismic Gas S/O Valve
|
1/13/2022
|
SGSOV Approved
|
OSVALDO PARAMO
|
|
Final
|
1/24/2022
|
OK to Issue CofO
|
OSVALDO PARAMO
|