3423 N REYNOLDS AVE 90032

Certificate Information: 3423 N REYNOLDS AVE 90032

Application / Permit
19010-70000-02864
Plan Check / Job No.
B19SL00870
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. TYPE VB FULLY SPRINKLERED.
Permit Issued
Issued on 6/24/2020
Issuing Office
Current Status
CofO Issued on 2/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/3/2019 APPLICANT
Assigned to Plan Check Engineer 7/18/2019 RICARDO RAMIREZ
Corrections Issued 7/22/2019 RICARDO RAMIREZ
Quality Review Completed 7/25/2019 TEODORO DIAZ RODRIGUEZ
Green Plans Picked Up 7/26/2019 APPLICANT
Plan Check Approved 9/11/2019 RICARDO RAMIREZ
Issued 6/24/2020 APPLICANT
CofO in Progress 1/26/2022 OSVALDO PARAMO
CofO in Progress 1/26/2022 OSVALDO PARAMO
Permit Finaled 2/3/2022 RONALD MYRICK
CofO Issued 2/3/2022 RONALD MYRICK
Permit Finaled 2/3/2022 RONALD MYRICK

Permit Application Clearance Information

Hydrant and Access approval Cleared 8/1/2019 GILBERT URREA
Low Impact Development Cleared 8/2/2019 JORGE MEJIA LEMUS
BHO/Hillside ordinance Cleared 8/7/2019 ELENA LOPEZ
BHO/Hillside ordinance Cleared 8/7/2019 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 8/7/2019 CELINA MORENO
Green Code Cleared 8/7/2019 COLIN LOREDO
Roof/Waste drainage to street Cleared 8/7/2019 ELENA LOPEZ
Sewer availability Cleared 8/7/2019 CELINA MORENO
"D" conditions Cleared 8/14/2019 ANNA VIDAL
"Q" conditions Cleared 8/14/2019 ANNA VIDAL
ZI Cleared 8/14/2019 ANNA VIDAL
BHO/Hillside ordinance Cleared 8/27/2019 ELAINE LEI
Encroachment in public way Cleared 8/29/2019 ELENA LOPEZ
GPI Written Notices Cleared 9/11/2019 RICARDO RAMIREZ
Grading Pre-Inspection Cleared 9/11/2019 RICARDO RAMIREZ

Contact Information

Contractor L A Green Designs; Lic. No.: 988980-B P O BOX 411603      LOS ANGELES, CA 90041
Engineer Mahn,, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381
Engineer Nguyen,, Tuan Minh; Lic. No.: S5883 5552 W 123RD PLACE      HAWTHORNE, CA 90250
Geologist Pongracz-Bartha,, Ed; Lic. No.: EG2370 10501 COLLETT AVE      GRANADA HILLS, CA 91344

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 6/29/2020 Partial Approval OSVALDO PARAMO
Deputy Grading 7/1/2020 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 7/1/2020 Not Ready for Inspection OSVALDO PARAMO
Pre-Inspection 7/1/2020 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 7/9/2020 Partial Approval OSVALDO PARAMO
Piling/Pier/Caisson 7/9/2020 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 7/15/2020 Partial Approval OSVALDO PARAMO
Piling/Pier/Caisson 7/15/2020 Approved OSVALDO PARAMO
Special/Order Compliance 7/29/2020 Approved OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 8/10/2020 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 8/10/2020 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 8/11/2020 Partial Approval RUBEN SALAS
Deputy Reinf. Concrete 8/14/2020 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 9/1/2020 Partial Approval OSVALDO PARAMO
Underground Mechanical 9/21/2020 Not Ready for Inspection OSVALDO PARAMO
Wood Frame 9/21/2020 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 9/22/2020 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 9/23/2020 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 9/25/2020 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 11/24/2020 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 12/2/2020 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 12/9/2020 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 12/30/2020 No Access for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 1/6/2021 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 1/7/2021 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 1/11/2021 Corrections Issued RUBEN SALAS
HVAC-Rough 1/11/2021 Approved RUBEN SALAS
ELECTRICAL-Rough 1/12/2021 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 1/14/2021 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 1/15/2021 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 1/20/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 1/20/2021 Corrections Issued OSVALDO PARAMO
BUILDING-Rough-Frame 1/25/2021 Not Ready for Inspection OSVALDO PARAMO
Green Building Rough 1/25/2021 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 1/25/2021 Not Ready for Inspection OSVALDO PARAMO
Verify Sprinkler Sign Off 1/25/2021 Not Ready for Inspection OSVALDO PARAMO
Interior/Exterior Lathing 2/2/2021 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 2/2/2021 Approved OSVALDO PARAMO
Wood Frame 2/2/2021 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 2/3/2021 Approved OSVALDO PARAMO
Green Building Rough 2/3/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 2/3/2021 Partial Approval OSVALDO PARAMO
Verify Sprinkler Sign Off 2/3/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 2/4/2021 Approved OSVALDO PARAMO
Shower Pan 2/4/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 2/5/2021 Approved OSVALDO PARAMO
Insulation 2/8/2021 Not Ready for Inspection OSVALDO PARAMO
Insulation 2/9/2021 Approved OSVALDO PARAMO
Drywall Nailing 2/12/2021 Approved OSVALDO PARAMO
Special/Order Compliance 2/17/2021 Approved THOMAS LOGRASSO
Special/Order Compliance 2/24/2021 Approved OSVALDO PARAMO
Gas Test 4/5/2021 No Access for Inspection OSVALDO PARAMO
HVAC-Final 6/10/2021 Not Ready for Inspection COREY HUPP
ELECTRICAL-Final 6/11/2021 Corrections Issued OSVALDO PARAMO
Gas Test 6/14/2021 Approved OSVALDO PARAMO
PLUMBING-Final 6/14/2021 Approved OSVALDO PARAMO
HVAC-Final 6/17/2021 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Final 6/22/2021 Approved OSVALDO PARAMO
HVAC-Final 6/22/2021 Approved OSVALDO PARAMO
Final 6/23/2021 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 6/23/2021 Approved OSVALDO PARAMO
Green Building Final 6/23/2021 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 6/23/2021 SGSOV Not Ready OSVALDO PARAMO
Service/Power Release 6/23/2021 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 6/23/2021 Approved OSVALDO PARAMO
Final 1/11/2022 Corrections Issued OSVALDO PARAMO
Green Building Final 1/11/2022 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 1/11/2022 SGSOV Not Ready OSVALDO PARAMO
Service/Power Release 1/11/2022 Approved OSVALDO PARAMO
Final 1/13/2022 Conditional Approval OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 1/13/2022 SGSOV Approved OSVALDO PARAMO
Final 1/24/2022 OK to Issue CofO OSVALDO PARAMO