1416 S ORANGE DR 90019
Certificate Information: 1416 S ORANGE DR 90019
- Application / Permit
- 19010-70000-02822
- Plan Check / Job No.
- B19SL00856
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AT FRONT OF LOT ( 1 OF 3 )
- Permit Issued
- Issued on 9/11/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2019 | LUKE GONZALES |
| Green Plans Picked Up | 7/19/2019 | APPLICANT |
| Corrections Issued | 7/24/2019 | LUKE GONZALES |
| Quality Review Completed | 7/25/2019 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 7/29/2019 | APPLICANT |
| Plan Check Approved | 10/4/2019 | LUKE GONZALES |
| Issued | 9/11/2020 | APPLICANT |
| CofO in Progress | 3/30/2022 | STUART CHAPMAN |
| No Progress | 3/30/2022 | STUART CHAPMAN |
| CofO in Progress | 4/15/2022 | SCOTT FINNILA |
| Permit Finaled | 4/19/2022 | DEROLD HAUFF |
| CofO Issued | 4/19/2022 | DEROLD HAUFF |
| Permit Finaled | 4/19/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 7/30/2019 | JOHN KIM |
| Address approval | Cleared | 8/2/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2019 | ERIK BEASLEY |
| Highway dedication | Cleared | 8/2/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 8/2/2019 | ERIK BEASLEY |
| Frnt yard landscape/Water mgmt | Cleared | 8/5/2019 | SARAHI ORTEGA |
| Hydrant and Access approval | Cleared | 8/5/2019 | ROBERT DUFF |
| Green Code | Cleared | 8/12/2019 | LUKE GONZALES |
| Low Impact Development | Cleared | 9/25/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/25/2019 | JEANETTE VONG |
Contact Information
| Contractor | Safe Quake Construction; Lic. No.: 571102-B | 2168 S ATLANTIC BL PMB 291 MONTEREY PARK, CA 91754 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/8/2020 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 12/22/2020 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/22/2020 | Approved | STUART CHAPMAN |
| METHANE-Barrier | 12/22/2020 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 12/22/2020 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2021 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2021 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2021 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2021 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 4/28/2021 | Corrections Issued | STUART CHAPMAN |
| HVAC-Rough | 4/28/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 4/28/2021 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Rough | 5/5/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 5/5/2021 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 5/5/2021 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/10/2021 | Conditional Approval | STUART CHAPMAN |
| PLUMBING-Rough | 5/10/2021 | Approved | STUART CHAPMAN |
| Insulation | 5/14/2021 | Approved | STUART CHAPMAN |
| Drywall Nailing | 6/1/2021 | Approved | RUBEN SALAS |
| Green Building Rough | 6/1/2021 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 6/16/2021 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 2/28/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 2/28/2022 | Corrections Issued | STUART CHAPMAN |
| Final | 2/28/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 2/28/2022 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 2/28/2022 | Corrections Issued | STUART CHAPMAN |
| METHANE-Final | 2/28/2022 | Approved | STUART CHAPMAN |
| METHANE-Rough | 2/28/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 2/28/2022 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 2/28/2022 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 2/28/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 2/28/2022 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 2/28/2022 | Approved | STUART CHAPMAN |
| Final | 3/18/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 3/18/2022 | Approved | STUART CHAPMAN |
| Service/Power Release | 3/18/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 3/25/2022 | Partial Approval | STUART CHAPMAN |
| Service/Power Release | 3/25/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 3/29/2022 | Approved | STUART CHAPMAN |
| Final | 3/29/2022 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 3/29/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 3/29/2022 | Approved | STUART CHAPMAN |