513-513 1/2 S MATHEWS ST 90033
Certificate Information: 513-513 1/2 S MATHEWS ST 90033
- Application / Permit
- 19010-70000-02660
- Plan Check / Job No.
- B19SL00788
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3 STORY DUPLEX AND ATTACHED GARAGE AT REAR. TYPE VB FULLY SPRINKLERED.
- Permit Issued
- Issued on 11/8/2019
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 1/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2019 | RICARDO RAMIREZ |
| Corrections Issued | 7/2/2019 | RICARDO RAMIREZ |
| Green Plans Picked Up | 7/2/2019 | APPLICANT |
| Quality Review Completed | 7/9/2019 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 7/18/2019 | APPLICANT |
| Applicant returned to address corrections | 8/20/2019 | RICARDO RAMIREZ |
| Plan Check Approved | 8/21/2019 | RICARDO RAMIREZ |
| Issued | 11/8/2019 | LADBS |
| CofO in Progress | 11/14/2020 | ROBERT VORHIS |
| Permit Finaled | 12/24/2020 | DEROLD HAUFF |
| Permit Finaled | 1/2/2021 | DEROLD HAUFF |
| CofO Issued | 1/2/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/26/2019 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2019 | ADRIAN SANCHEZ |
| Highway dedication | Cleared | 7/26/2019 | ADRIAN SANCHEZ |
| Permit | Cleared | 7/26/2019 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 7/26/2019 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 8/9/2019 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 8/19/2019 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 8/19/2019 | ADRIAN SANCHEZ |
| GPI Written Notices | Cleared | 8/20/2019 | RICARDO RAMIREZ |
| Grading Pre-Inspection | Cleared | 8/20/2019 | RICARDO RAMIREZ |
| Green Code | Cleared | 8/20/2019 | NEGAR NEJAD |
Contact Information
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | 4 HILLCREST MANOR ROLLING HILLS ESTATES, CA 90274 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
| Engineer | Sanchez,, Pablo Beltran; Lic. No.: C86223 | 1840 S GAFFEY ST 382 SAN PEDRO, CA 90731 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/9/2019 | Partial Approval | ROBERT VORHIS |
| Underground Mechanical | 12/9/2019 | Partial Inspection | ROBERT VORHIS |
| Footing/Foundation/Slab | 12/18/2019 | Approved | ROBERT CORNELL |
| METHANE-Barrier | 12/18/2019 | Approved | ROBERT CORNELL |
| METHANE-Subgrade | 12/18/2019 | Approved | ROBERT CORNELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2020 | Partial Approval | CHARLENE BUSTAMANTE |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2020 | Partial Approval | ROBERT CORNELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2020 | Not Ready for Inspection | ROBERT CORNELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2020 | Approved | ROBERT CORNELL |
| BUILDING-Rough-Frame | 4/23/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 4/23/2020 | Approved | FREDDIE RIVERA |
| Green Building Rough | 4/23/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Rough | 4/23/2020 | Partial Approval | FREDDIE RIVERA |
| METHANE-Rough | 4/23/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 4/23/2020 | Approved | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 4/23/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 4/23/2020 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 4/27/2020 | Approved | OSVALDO PARAMO |
| Insulation | 4/27/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 4/27/2020 | Approved | OSVALDO PARAMO |
| Insulation | 5/1/2020 | Conditional Approval | SCOTT FINNILA |
| Interior/Exterior Lathing | 5/1/2020 | Not Ready for Inspection | SCOTT FINNILA |
| Wood Frame | 5/1/2020 | Approved | SCOTT FINNILA |
| Drywall Nailing | 5/11/2020 | Partial Approval | THOMAS LOGRASSO |
| Green Building Rough | 5/11/2020 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 5/11/2020 | Approved | THOMAS LOGRASSO |
| Verify Rec and Parks Fee Memo | 8/14/2020 | Not Ready for Inspection | ROBERT VORHIS |
| BUILDING-Rough-Frame | 9/21/2020 | Approved | ROBERT VORHIS |
| Drywall Nailing | 9/21/2020 | Approved | ROBERT VORHIS |
| ELECTRICAL-Final | 9/21/2020 | Corrections Issued | ROBERT VORHIS |
| Green Building Rough | 9/21/2020 | Approved | ROBERT VORHIS |
| METHANE-Rough | 9/21/2020 | Approved | ROBERT VORHIS |
| PLUMBING-Final | 9/21/2020 | Corrections Issued | ROBERT VORHIS |
| Smoke Detectors | 9/21/2020 | Approved | ROBERT VORHIS |
| ELECTRICAL-Final | 9/28/2020 | Approved | ROBERT VORHIS |
| HVAC-Final | 9/28/2020 | Not Ready for Inspection | ROBERT VORHIS |
| PLUMBING-Final | 9/28/2020 | Not Ready for Inspection | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 9/28/2020 | SGSOV Approved | ROBERT VORHIS |
| Final | 10/6/2020 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 10/6/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| HVAC-Final | 10/6/2020 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 10/6/2020 | Approved | OSVALDO PARAMO |
| Service/Power Release | 10/13/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Final | 11/9/2020 | Partial Inspection | ROBERT VORHIS |
| Green Building Final | 11/9/2020 | Approved | ROBERT VORHIS |
| Service/Power Release | 11/9/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Final | 11/12/2020 | Conditional Approval | ROBERT VORHIS |
| Service/Power Release | 11/12/2020 | Approved | ROBERT VORHIS |