4208 S WESTERN AVE 90062
Certificate Information: 4208 S WESTERN AVE 90062
- Application / Permit
- 19010-70000-02630
- Plan Check / Job No.
- B19SL00784
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 PER WOOD FRAME PRESPECTIVE
- Permit Issued
- Issued on 2/3/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2019 | DANIEL SANJUAN |
| Corrections Issued | 8/1/2019 | DANIEL SANJUAN |
| Green Plans Picked Up | 8/7/2019 | APPLICANT |
| Building Plans Picked Up | 8/9/2019 | APPLICANT |
| Quality Review Completed | 8/15/2019 | HERNAN ARREOLA |
| Plan Check Approved | 1/30/2020 | DANIEL SANJUAN |
| Issued | 2/3/2020 | LADBS |
| CofO in Progress | 8/8/2022 | HORACE FULTZ |
| Permit Finaled | 8/13/2022 | DEROLD HAUFF |
| Permit Finaled | 8/13/2022 | DEROLD HAUFF |
| CofO Issued | 8/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/9/2019 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 8/9/2019 | ADRIAN SANCHEZ |
| Community Plan Implem. Overlay | Cleared | 8/14/2019 | JOHN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2019 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 8/16/2019 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 10/16/2019 | JOHN CONNEALLY |
| Community Plan Implem. Overlay | Cleared | 10/19/2019 | RIDWAN HARDY |
| Green Code | Cleared | 12/19/2019 | VIVIAN LAO |
| Community Plan Implem. Overlay | Cleared | 1/14/2020 | EDUARDO HERMOSO |
| Community Plan Implem. Overlay | Cleared | 1/24/2020 | HELEN JADALI |
| Community Plan Implem. Overlay | Cleared | 1/29/2020 | LEE GUILBEAUX |
| Permit | Cleared | 1/30/2020 | EMIL KYUPELYAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/12/2020 | Corrections Issued | ROBERT MCDOWELL |
| Pre-Inspection | 6/26/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 12/28/2020 | Partial Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2021 | Partial Approval | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 3/16/2021 | No Access for Inspection | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 3/16/2021 | No Access for Inspection | ROBERT MCDOWELL |
| Green Building Rough | 3/16/2021 | No Access for Inspection | ROBERT MCDOWELL |
| PLUMBING-Rough | 3/16/2021 | No Access for Inspection | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 3/16/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 3/23/2021 | Conditional Approval | ROBERT MCDOWELL |
| Drywall Nailing | 3/23/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 3/23/2021 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 3/23/2021 | Approved | ROBERT MCDOWELL |
| Underground Mechanical | 3/23/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2021 | Approved | ROBERT MCDOWELL |
| Insulation | 4/8/2021 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 4/8/2021 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 6/1/2021 | Approved | SABAS ALONSO |
| Green Building Rough | 6/1/2021 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 6/1/2021 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/21/2021 | Not Ready for Inspection | SABAS ALONSO |
| Final | 10/21/2021 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 10/21/2021 | Approved | SABAS ALONSO |
| Green Building Final | 10/21/2021 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 10/21/2021 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 10/21/2021 | Not Required | SABAS ALONSO |
| Smoke Detectors | 10/21/2021 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 10/21/2021 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/13/2022 | Approved | SABAS ALONSO |
| Final | 5/13/2022 | Corrections Issued | SABAS ALONSO |
| Verify Sprinkler Sign Off | 5/13/2022 | Approved | SABAS ALONSO |
| Final | 8/5/2022 | OK to Issue CofO | SABAS ALONSO |