3526-3526 1/2 E HUNTER ST 90023

Certificate Information: 3526-3526 1/2 E HUNTER ST 90023

Application / Permit
19010-70000-02135
Plan Check / Job No.
B19SL00649
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW TWO STORY DUPLEX. TYPE V-B FULLY SPRINKLERED.
Permit Issued
Issued on 3/3/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 3/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2019 APPLICANT
Assigned to Plan Check Engineer 6/6/2019 RICARDO RAMIREZ
Corrections Issued 6/11/2019 RICARDO RAMIREZ
Quality Review Completed 6/25/2019 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 6/26/2019 APPLICANT
Green Plans Picked Up 6/27/2019 APPLICANT
Applicant returned to address corrections 8/8/2019 RICARDO RAMIREZ
Plan Check Approved 12/10/2019 RICARDO RAMIREZ
Issued 3/3/2020 LADBS
CofO in Progress 2/1/2021 RUBEN SALAS
Permit Finaled 3/15/2021 DEROLD HAUFF
CofO Issued 3/15/2021 DEROLD HAUFF
Permit Finaled 3/15/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/27/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 8/28/2019 JEANIE LAM
Green Code Cleared 8/28/2019 COLIN LOREDO
Hydrant and Access approval Cleared 8/28/2019 GEORGE SUCHAND
Sewer availability Cleared 8/28/2019 JEANIE LAM
Low Impact Development Cleared 12/6/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 12/6/2019 JAMES MORALEZ
Zoning Information File Cleared 12/10/2019 RICARDO RAMIREZ

Contact Information

Engineer Sanchez,, Pablo Beltran; Lic. No.: C86223 1840 S GAFFEY ST 382      SAN PEDRO, CA 90731

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/14/2020 Corrections Issued ROBERT VORHIS
PLUMBING-Rough 4/14/2020 Partial Approval ROBERT VORHIS
Footing/Foundation/Slab 4/20/2020 Approved ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 5/5/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/29/2020 Partial Approval ROBERT VORHIS
Interior/Exterior Lathing 6/19/2020 Partial Approval ENRIQUE MIRELES
ELECTRICAL-Rough 7/1/2020 Approved ROBERT VORHIS
PLUMBING-Rough 7/1/2020 Approved ROBERT VORHIS
BUILDING-Rough-Frame 7/13/2020 Approved ROBERT VORHIS
Green Building Rough 7/13/2020 Approved ROBERT VORHIS
HVAC-Rough 7/13/2020 Approved ROBERT VORHIS
Interior/Exterior Lathing 7/13/2020 Partial Approval ROBERT VORHIS
Verify Sprinkler Sign Off 7/13/2020 Approved ROBERT VORHIS
Insulation 7/16/2020 Approved THOMAS LOGRASSO
Insulation 7/16/2020 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Drywall Nailing 7/21/2020 Approved ROBERT VORHIS
ELECTRICAL-Final 1/20/2021 Approved FREDDIE RIVERA
HVAC-Final 1/20/2021 Approved FREDDIE RIVERA
PLUMBING-Final 1/20/2021 Approved FREDDIE RIVERA
Final 1/29/2021 OK to Issue CofO RUBEN SALAS
Green Building Final 1/29/2021 Approved RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 1/29/2021 SGSOV Approved RUBEN SALAS
Service/Power Release 1/29/2021 Approved RUBEN SALAS
Smoke Detectors 1/29/2021 Approved RUBEN SALAS