5641-5641 1/2 N RIVERTON AVE 91601

Certificate Information: 5641-5641 1/2 N RIVERTON AVE 91601

Application / Permit
19010-70000-01890
Plan Check / Job No.
B19SL00548
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2 STORY DUPLEX WITH ATTACHED 4 CAR GARAGE
Permit Issued
Issued on 11/22/2019
Issuing Office
Metro
Current Status
CofO Issued on 11/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2019 APPLICANT
Assigned to Plan Check Engineer 5/10/2019 LUKE GONZALES
Corrections Issued 5/15/2019 LUKE GONZALES
Quality Review Completed 5/31/2019 WESLEY FARRELL
Building Plans Picked Up 6/5/2019 APPLICANT
Plan Check Approved 9/4/2019 LUKE GONZALES
Issued 11/22/2019 LADBS
Green Plans Picked Up 8/14/2020 APPLICANT
CofO in Progress 9/27/2021 DANIEL DREW
Permit Finaled 11/3/2021 MICHAEL SMITH
CofO Issued 11/3/2021 MICHAEL SMITH
Permit Finaled 11/3/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/20/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 6/20/2019 ELAINE LEI
Permit Cleared 6/20/2019 ELAINE LEI
Sewer availability Cleared 6/20/2019 ELAINE LEI
Trees in Parkway Cleared 8/9/2019 JOHN KIM
Hydrant and Access approval Cleared 8/12/2019 ROBERT DUFF
Low Impact Development Cleared 8/16/2019 JORGE MEJIA LEMUS
Project located in CRA area Cleared 8/16/2019 JIM URQUHART
ZI Cleared 8/16/2019 DIANA JIMENEZ
Green Code Cleared 8/20/2019 KHEDER ALRAZAA
Roof/Waste drainage to street Cleared 8/22/2019 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Elia,, Victor Anthony; Lic. No.: C64803 40912 CARLENA LN      TEMECULA, CA 92591
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/13/2020 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 1/23/2020 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 3/3/2020 Corrections Issued RAYMOND KEHOE
Footing/Foundation/Slab 9/10/2020 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 10/16/2020 Partial Approval DANIEL DREW
Green Building Rough 10/16/2020 Not Ready for Inspection DANIEL DREW
Verify Sprinkler Sign Off 10/16/2020 Not Ready for Inspection DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 12/21/2020 Approved DANIEL DREW
ELECTRICAL-Rough 1/20/2021 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 1/20/2021 Approved DANIEL DREW
Green Building Rough 1/20/2021 Not Ready for Inspection DANIEL DREW
HVAC-Rough 1/20/2021 Approved DANIEL DREW
PLUMBING-Rough 1/20/2021 Approved DANIEL DREW
Verify Sprinkler Sign Off 1/20/2021 Approved DANIEL DREW
Insulation 2/9/2021 Approved DANIEL DREW
Interior/Exterior Lathing 2/9/2021 Approved DANIEL DREW
Drywall Nailing 2/18/2021 Approved DANIEL DREW
Green Building Rough 2/18/2021 Approved DANIEL DREW
Interior/Exterior Lathing 2/18/2021 Approved DANIEL DREW
Sewer 5/3/2021 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 7/26/2021 Approved WILLIAM KUEHN
PLUMBING-Final 7/26/2021 Approved WILLIAM KUEHN
HVAC-Final 7/27/2021 Conditional Approval DANIEL DREW
BUILDING-Rough-Frame 9/9/2021 Approved DANIEL DREW
Final 9/9/2021 Corrections Issued DANIEL DREW
Green Building Final 9/9/2021 Approved DANIEL DREW
HVAC-Final 9/9/2021 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 9/9/2021 SGSOV Approved DANIEL DREW
Service/Power Release 9/9/2021 Approved DANIEL DREW
Smoke Detectors 9/9/2021 Approved DANIEL DREW
Final 9/24/2021 OK to Issue CofO DANIEL DREW