4012 S HOBART BLVD 90062
Certificate Information: 4012 S HOBART BLVD 90062
- Application / Permit
- 19010-70000-01598
- Plan Check / Job No.
- B19SL00478
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 37'-4" X 33'-10" IRREGULAR ACCESSORY DWELLING UNIT WITH 5' X 4' COVERED PORCH AT FRONT AND 11' X 8' OPEN PORCH AT REAR PER AB 494 AND SB 229
- Permit Issued
- Issued on 12/23/2020
- Issuing Office
- Current Status
- CofO Issued on 7/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2019 | ROSENDO MEDINA |
| Corrections Issued | 6/3/2019 | ROSENDO MEDINA |
| Green Plans Picked Up | 6/4/2019 | APPLICANT |
| Quality Review Completed | 6/5/2019 | OMID HEDAYAT |
| Applicant returned to address corrections | 9/13/2019 | ROSENDO MEDINA |
| Plan Check Approved | 9/27/2019 | ROSENDO MEDINA |
| Issued | 12/23/2020 | APPLICANT |
| Building Plans Picked Up | 12/24/2020 | APPLICANT |
| CofO in Progress | 7/16/2024 | SABAS ALONSO |
| CofO Issued | 7/22/2024 | DEROLD HAUFF |
| Permit Finaled | 7/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/2/2019 | KARAN PATEL |
| ZI | Cleared | 7/8/2019 | HELEN JADALI |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2019 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 8/1/2019 | GEORGE SUCHAND |
| Sewer availability | Cleared | 8/1/2019 | CELINA MORENO |
| Low Impact Development | Cleared | 8/21/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 8/21/2019 | ERIK BEASLEY |
| Green Code | Cleared | 9/20/2019 | NEGAR NEJAD |
Contact Information
| Contractor | A B C Advance Builder & Constructor Inc; Lic. No.: 989468-B | 18017 CHATSWORTH STREET #140 GRANADA HILLS, CA 91344 |
| Engineer | Tsai,, Yu-Chin; Lic. No.: S3441 | 427 DOYLE DR SAN GABRIEL, CA 91775 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/30/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Pre-Inspection | 12/30/2020 | Approved | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 1/8/2021 | Conditional Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2021 | Partial Approval | ROBERT MCDOWELL |
| PLUMBING-Rough | 1/20/2021 | Partial Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2021 | Partial Approval | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 5/6/2021 | Conditional Approval | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 5/6/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 5/6/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| HVAC-Rough | 5/6/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 5/6/2021 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 5/6/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 5/21/2021 | Corrections Issued | JESUS PINEDA |
| Insulation | 6/1/2021 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 6/1/2021 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 6/9/2021 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 6/9/2021 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 6/9/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Shower Pan | 6/9/2021 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 5/6/2022 | Corrections Issued | SABAS ALONSO |
| Service/Power Release | 5/11/2022 | Approved | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 6/21/2022 | Not Ready for Inspection | SABAS ALONSO |
| Pre-Inspection | 6/21/2022 | Not Ready for Inspection | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 8/1/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/29/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 12/29/2023 | Approved | SABAS ALONSO |
| Final | 12/29/2023 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 12/29/2023 | Approved | SABAS ALONSO |
| Green Building Final | 12/29/2023 | Approved | SABAS ALONSO |
| HVAC-Final | 12/29/2023 | Approved | SABAS ALONSO |
| PLUMBING-Final | 12/29/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/29/2023 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 12/29/2023 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 12/29/2023 | Approved | SABAS ALONSO |
| Final | 7/9/2024 | Corrections Issued | SABAS ALONSO |
| Final | 7/15/2024 | OK to Issue CofO | SABAS ALONSO |