235 E 103RD ST 90003

Certificate Information: 235 E 103RD ST 90003

Application / Permit
19010-70000-01442
Plan Check / Job No.
B19SL00428
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 PER WOOD FRAME PRESPECTIVE PROVISIONS
Permit Issued
Issued on 2/21/2020
Issuing Office
Metro
Current Status
CofO Issued on 8/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2019 APPLICANT
Assigned to Plan Check Engineer 5/16/2019 EMMANUEL MARTINEZ
Corrections Issued 5/23/2019 MONICA RAMIREZ
Quality Review Completed 5/31/2019 HERNAN ARREOLA
Green Plans Picked Up 6/3/2019 APPLICANT
Building Plans Picked Up 8/21/2019 APPLICANT
Plan Check Approved 2/21/2020 MONICA RAMIREZ
Issued 2/21/2020 LADBS
CofO in Progress 4/8/2022 JOHN KLARIN
Permit Finaled 8/20/2022 DEROLD HAUFF
CofO Issued 8/20/2022 DEROLD HAUFF
Permit Finaled 8/20/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/23/2019 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 10/23/2019 THOMAS LANG
Sewer availability Cleared 10/23/2019 THOMAS LANG
Low Impact Development Cleared 10/24/2019 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 10/24/2019 CELINA MORENO
ZI Cleared 10/24/2019 ANNA VIDAL
Green Code Cleared 10/30/2019 SARAH ABOULHOSN
Hydrant and Access approval Cleared 10/30/2019 JEREMY CARTER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/6/2020 Partial Approval WILLIAM ROSE
Excavation/Setback/Form/Re-Bar 5/12/2020 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 5/14/2020 Approved EUGENE CASSIDY
ELECTRICAL-Rough 6/25/2020 Corrections Issued BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 6/25/2020 Partial Approval BRIAN CHRISTIAN
PLUMBING-Rough 6/25/2020 Approved BRIAN CHRISTIAN
ELECTRICAL-Rough 8/6/2020 Approved EUGENE CASSIDY
HVAC-Rough 8/6/2020 Approved EUGENE CASSIDY
Wood Frame 8/6/2020 Approved EUGENE CASSIDY
Insulation 8/24/2020 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 8/24/2020 Approved SABAS ALONSO
Green Building Rough 9/8/2020 Approved EUGENE CASSIDY
Insulation 9/8/2020 Corrections Issued EUGENE CASSIDY
Verify Sprinkler Sign Off 9/8/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 11/9/2020 Partial Approval EUGENE CASSIDY
Underground Mechanical 11/9/2020 Partial Approval EUGENE CASSIDY
Insulation 1/22/2021 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 1/22/2021 Approved EUGENE CASSIDY
Sewer 1/27/2021 Corrections Issued EUGENE CASSIDY
Drywall Nailing 2/1/2021 Approved EUGENE CASSIDY
Sewer 2/1/2021 Approved EUGENE CASSIDY
ELECTRICAL-Rough 4/20/2021 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 9/28/2021 Approved EUGENE CASSIDY
Final 9/28/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 9/28/2021 Approved EUGENE CASSIDY
Green Building Final 9/28/2021 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/28/2021 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 9/28/2021 Approved EUGENE CASSIDY
Smoke Detectors 9/28/2021 Not Ready for Inspection EUGENE CASSIDY
Final 10/21/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 10/21/2021 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/21/2021 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 10/21/2021 Approved EUGENE CASSIDY
Green Building Final 12/2/2021 Approved EUGENE CASSIDY
PLUMBING-Final 12/2/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 12/9/2021 Approved EUGENE CASSIDY
Final 12/9/2021 Corrections Issued EUGENE CASSIDY
Final 1/20/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 2/28/2022 Not Ready for Inspection JOHN KLARIN
Final 3/11/2022 Corrections Issued JOHN KLARIN
Final 3/17/2022 No Access for Inspection JOHN KLARIN
ELECTRICAL-Final 3/25/2022 Approved JOHN KLARIN
Final 3/25/2022 Not Ready for Inspection JOHN KLARIN
HVAC-Final 3/25/2022 Approved JOHN KLARIN
PLUMBING-Final 3/25/2022 Approved JOHN KLARIN
Final 4/7/2022 OK to Issue CofO JOHN KLARIN