2651 N RICH ST 90039
Certificate Information: 2651 N RICH ST 90039
- Application / Permit
- 19010-70000-01421
- Plan Check / Job No.
- B19SL00424
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SINGLE FAMILY DWELLING WITH ROOF TOP DECK AND ATTACHED 1 CAR GARAGE.
- Permit Issued
- Issued on 9/12/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2019 | APPLICANT |
| Green Plans Picked Up | 4/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2019 | ZAW HAN |
| Corrections Issued | 4/29/2019 | ZAW HAN |
| Quality Review Completed | 5/8/2019 | BILL STUTSMAN |
| Building Plans Picked Up | 5/10/2019 | APPLICANT |
| Plan Check Approved | 8/29/2019 | ZAW HAN |
| Issued | 9/12/2019 | LADBS |
| CofO in Progress | 2/15/2022 | THOMAS LOGRASSO |
| CofO in Progress | 2/16/2022 | RUBEN SALAS |
| No Progress | 3/3/2022 | RUBEN SALAS |
| CofO in Progress | 4/2/2022 | RUBEN SALAS |
| Permit Finaled | 4/6/2022 | RONALD MYRICK |
| CofO Issued | 4/6/2022 | RONALD MYRICK |
| Permit Finaled | 4/6/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 4/30/2019 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2019 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 4/30/2019 | ROBERT DUFF |
| Permit | Cleared | 4/30/2019 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 4/30/2019 | ADRIAN SANCHEZ |
| Trees in Parkway | Cleared | 4/30/2019 | ADRIAN SANCHEZ |
| Green Code | Cleared | 8/13/2019 | NEGAR NEJAD |
| Low Impact Development | Cleared | 8/13/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 8/13/2019 | JEANETTE VONG |
| Frnt yard landscape/Water mgmt | Cleared | 8/16/2019 | KIT AWAKUNI |
| ZI | Cleared | 8/16/2019 | KIT AWAKUNI |
Contact Information
| Contractor | Bae Andrew; Lic. No.: 1047363-B | 3910 FRANKLIN ST LA CRESCENTA, CA 91214 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/23/2019 | Conditional Approval | DAVID CHAN |
| Footing/Foundation/Slab | 10/16/2019 | Conditional Approval | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 10/22/2019 | Approved | DAVID CHAN |
| Deputy Wood Construction | 12/12/2019 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2019 | Partial Approval | CHARLENE BUSTAMANTE |
| BUILDING-Rough-Frame | 1/28/2020 | Corrections Issued | MICHAEL FAUNCE |
| Green Building Rough | 1/28/2020 | Conditional Approval | MICHAEL FAUNCE |
| MERV13>=Rough | 1/28/2020 | Not Ready for Inspection | MICHAEL FAUNCE |
| PLUMBING-Rough | 1/28/2020 | Conditional Approval | MICHAEL FAUNCE |
| Rough-Elec/Plmb/HVAC | 1/28/2020 | Corrections Issued | MICHAEL FAUNCE |
| Verify Sprinkler Sign Off | 1/28/2020 | Approved | MICHAEL FAUNCE |
| ELECTRICAL-Rough | 1/30/2020 | Corrections Issued | AJA COLLAY |
| HVAC-Rough | 1/30/2020 | Corrections Issued | AJA COLLAY |
| PLUMBING-Rough | 1/30/2020 | Corrections Issued | AJA COLLAY |
| BUILDING-Rough-Frame | 2/4/2020 | Approved | AJA COLLAY |
| ELECTRICAL-Rough | 2/4/2020 | Approved | AJA COLLAY |
| Green Building Rough | 2/4/2020 | Approved | AJA COLLAY |
| HVAC-Rough | 2/4/2020 | Partial Approval | AJA COLLAY |
| MERV13>=Rough | 2/4/2020 | Approved | AJA COLLAY |
| PLUMBING-Rough | 2/4/2020 | Approved | AJA COLLAY |
| Insulation | 2/10/2020 | Conditional Approval | AJA COLLAY |
| Drywall Nailing | 2/20/2020 | Conditional Approval | AJA COLLAY |
| ELECTRICAL-Final | 4/23/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Underground Mechanical | 4/23/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 6/23/2021 | Corrections Issued | RICHARD STEINBACH |
| Final | 6/23/2021 | Corrections Issued | RICHARD STEINBACH |
| Footing/Foundation/Slab | 6/23/2021 | Approved | RICHARD STEINBACH |
| Green Building Final | 6/23/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| HVAC-Final | 6/23/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| MERV13>=Final | 6/23/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| PLUMBING-Final | 6/23/2021 | Corrections Issued | RICHARD STEINBACH |
| SGSOV-Seismic Gas S/O Valve | 6/23/2021 | SGSOV Approved | RICHARD STEINBACH |
| Service/Power Release | 6/23/2021 | Corrections Issued | RICHARD STEINBACH |
| Smoke Detectors | 6/23/2021 | Approved | RICHARD STEINBACH |
| Final | 7/20/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Final | 7/20/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Final | 7/20/2021 | Approved | KATHRYN BUTTERWORTH |
| Service/Power Release | 7/20/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 8/25/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 8/25/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 8/25/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Final | 8/25/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Final | 8/25/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Service/Power Release | 8/25/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 1/11/2022 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 1/11/2022 | Approved | THOMAS LOGRASSO |
| Service/Power Release | 1/11/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 2/14/2022 | OK to Issue CofO | THOMAS LOGRASSO |
| Service/Power Release | 2/14/2022 | Approved | THOMAS LOGRASSO |