4830 S 4TH AVE 90043
Certificate Information: 4830 S 4TH AVE 90043
- Application / Permit
- 19010-70000-01235
- Plan Check / Job No.
- B19SL00366
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) Detached 1-story Accessory Dwelling Unit per AB 494 and SB 229.
- Permit Issued
- Issued on 11/2/2020
- Issuing Office
- Current Status
- CofO Issued on 9/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2019 | APPLICANT |
| Green Plans Picked Up | 4/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2019 | HELEN NGUYEN |
| Corrections Issued | 4/22/2019 | HELEN NGUYEN |
| Quality Review Completed | 4/30/2019 | FELIX FIGUEROA |
| Applicant returned to address corrections | 6/14/2019 | HELEN NGUYEN |
| Plan Check Approved | 11/26/2019 | HELEN NGUYEN |
| Issued | 11/2/2020 | APPLICANT |
| Building Plans Picked Up | 11/5/2020 | APPLICANT |
| CofO in Progress | 9/21/2021 | DAVID FEILER |
| Permit Finaled | 9/22/2021 | DEROLD HAUFF |
| CofO Issued | 9/22/2021 | DEROLD HAUFF |
| Permit Finaled | 9/22/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/14/2019 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2019 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 5/14/2019 | GILBERT URREA |
| Sewer availability | Cleared | 5/14/2019 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 5/23/2019 | JEANETTE VONG |
| Construction near power lines | Cleared | 8/17/2019 | RIDWAN HARDY |
| Green Code | Cleared | 11/15/2019 | HELEN NGUYEN |
| Low Impact Development | Cleared | 11/15/2019 | RYAN HUDSON |
| Low Impact Development | Cleared | 11/15/2019 | RYAN HUDSON |
| Hydrant and Access approval | Cleared | 9/23/2020 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 10/22/2020 | THOMAS LANG |
| Sewer availability | Cleared | 10/22/2020 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 26851 GRAYSLAKE ROAD RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/7/2020 | Partial Inspection | DAVID FEILER |
| PLUMBING-Rough | 1/5/2021 | Partial Approval | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 1/11/2021 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/11/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/29/2021 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2021 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 2/25/2021 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 2/25/2021 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 2/25/2021 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 2/25/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 2/25/2021 | Not Ready for Inspection | DAVID FEILER |
| Verify Sprinkler Sign Off | 2/25/2021 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 3/5/2021 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 3/5/2021 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 3/5/2021 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 3/5/2021 | Approved | SCOTT FINNILA |
| PLUMBING-Rough | 3/5/2021 | Approved | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 3/5/2021 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 3/11/2021 | Approved | DAVID FEILER |
| Green Building Rough | 3/11/2021 | Approved | DAVID FEILER |
| Insulation | 3/11/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 3/11/2021 | Not Ready for Inspection | DAVID FEILER |
| Drywall Nailing | 3/16/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 3/16/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 5/19/2021 | Partial Inspection | DAVID FEILER |
| Underground Mechanical | 5/19/2021 | Approved | DAVID FEILER |
| Sewer | 5/26/2021 | Approved | SABAS ALONSO |
| Final | 7/22/2021 | Corrections Issued | DAVID FEILER |
| Green Building Final | 7/22/2021 | Not Ready for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 7/22/2021 | SGSOV Not Ready | DAVID FEILER |
| Service/Power Release | 7/22/2021 | Not Required | DAVID FEILER |
| Smoke Detectors | 7/22/2021 | Approved | DAVID FEILER |
| Final | 8/18/2021 | Partial Inspection | DAVID FEILER |
| Green Building Final | 8/18/2021 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 8/18/2021 | SGSOV Approved | DAVID FEILER |
| Final | 9/10/2021 | OK to Issue CofO | DAVID FEILER |