4432-4434 S MORGAN AVE 90011
Certificate Information: 4432-4434 S MORGAN AVE 90011
- Application / Permit
- 19010-70000-00440
- Plan Check / Job No.
- B19SL00116
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- New detached carport at rear. All work per WFPP
- Permit Issued
- Issued on 3/10/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2019 | MONICA RAMIREZ |
| Corrections Issued | 2/19/2019 | MONICA RAMIREZ |
| Quality Review Completed | 3/5/2019 | HERNAN ARREOLA |
| Green Plans Picked Up | 3/7/2019 | APPLICANT |
| Building Plans Picked Up | 5/29/2019 | APPLICANT |
| Applicant returned to address corrections | 12/3/2019 | MONICA RAMIREZ |
| Applicant returned to address corrections | 1/17/2020 | MONICA RAMIREZ |
| Plan Check Approved | 3/10/2020 | MONICA RAMIREZ |
| Issued | 3/10/2020 | LADBS |
| CofO in Progress | 7/20/2023 | BRENDAN MORELLI |
| Permit Finaled | 7/23/2023 | DEROLD HAUFF |
| CofO Issued | 7/23/2023 | DEROLD HAUFF |
| Permit Finaled | 7/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 7/2/2019 | MONICA RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2019 | EMIL KYUPELYAN |
| Hydrant and Access approval | Cleared | 12/3/2019 | JEREMY CARTER |
| Roof/Waste drainage to street | Cleared | 12/3/2019 | EMIL KYUPELYAN |
| ZI | Cleared | 1/17/2020 | SARAHI ORTEGA |
| Low Impact Development | Cleared | 2/27/2020 | ORVAL HERNANDEZ-MARCIAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/4/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 10/14/2022 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2022 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/22/2022 | Corrections Issued | JULIAN AMAYA |
| ELECTRICAL-Rough | 11/22/2022 | Corrections Issued | JULIAN AMAYA |
| BUILDING-Rough-Frame | 12/15/2022 | Conditional Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 12/15/2022 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 12/28/2022 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 1/27/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 3/23/2023 | Approved | STUART CHAPMAN |
| Final | 3/23/2023 | Corrections Issued | STUART CHAPMAN |
| Drywall Nailing | 7/10/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 7/19/2023 | Approved | BRENDAN MORELLI |
| Final | 7/19/2023 | OK to Issue CofO | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 7/19/2023 | SGSOV Not Required | BRENDAN MORELLI |
| Service/Power Release | 7/19/2023 | Approved | BRENDAN MORELLI |
| Smoke Detectors | 7/19/2023 | Approved | BRENDAN MORELLI |