10960 S AVALON BLVD 90061

Certificate Information: 10960 S AVALON BLVD 90061

Application / Permit
19010-70000-00028
Plan Check / Job No.
B19SL00014
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY SINGLE FAMILY DWELLING IN FRONT OF LOT. 1 OF 2 TV=379,381 , BPV=144,870
Permit Issued
Issued on 11/27/2019
Issuing Office
Metro
Current Status
CofO Issued on 12/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2019 APPLICANT
Assigned to Plan Check Engineer 1/17/2019 SAMUEL GONZALEZ
Corrections Issued 2/5/2019 SAMUEL GONZALEZ
Quality Review Completed 2/6/2019 MOHAMMAD FIROUZBAKHT
Plan Check Approved 4/4/2019 SAMUEL GONZALEZ
Issued 11/27/2019 LADBS
CofO in Progress 11/10/2021 EUGENE CASSIDY
Permit Finaled 12/1/2021 DEROLD HAUFF
CofO Issued 12/1/2021 DEROLD HAUFF
Permit Finaled 12/1/2021 DEROLD HAUFF

Permit Application Clearance Information

Hold Cleared 1/29/2019 LOURDES RAMIRO
Hold Cleared 2/1/2019 SAMUEL GONZALEZ
Address approval Cleared 2/22/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 2/22/2019 JEANETTE VONG
Permit Cleared 2/22/2019 JEANETTE VONG
Hydrant and Access approval Cleared 3/1/2019 GEORGE SUCHAND
Sewer availability Cleared 3/13/2019 JEANETTE VONG
ZI Cleared 3/14/2019 STEVE GARCIA
Green Code Cleared 3/29/2019 COLIN LOREDO
Green Code Cleared 3/29/2019 SAMUEL GONZALEZ
Low Impact Development Cleared 3/29/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 3/29/2019 ELENA LOPEZ

Contact Information

Contractor Precision Construction Experts Inc; Lic. No.: 1026997-B 16656 CALLE ARBOLADA      PACIFIC PALISADES, CA 90272
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/3/2019 Not Ready for Inspection WILLIAM ROSE
PLUMBING-Rough 12/9/2019 Partial Inspection WILLIAM ROSE
Underground Mechanical 12/9/2019 Not Ready for Inspection WILLIAM ROSE
Excavation/Setback/Form/Re-Bar 12/12/2019 Not Ready for Inspection WILLIAM ROSE
Footing/Foundation/Slab 12/12/2019 Not Ready for Inspection WILLIAM ROSE
Excavation/Setback/Form/Re-Bar 12/16/2019 Not Ready for Inspection WILLIAM ROSE
Excavation/Setback/Form/Re-Bar 12/17/2019 Approved WILLIAM ROSE
BUILDING-Rough-Frame 1/8/2020 Partial Approval WILLIAM ROSE
Green Building Rough 1/8/2020 Not Ready for Inspection WILLIAM ROSE
Verify Sprinkler Sign Off 1/8/2020 Not Ready for Inspection WILLIAM ROSE
BUILDING-Rough-Frame 1/22/2020 Not Ready for Inspection WILLIAM ROSE
ELECTRICAL-Rough 1/22/2020 Not Ready for Inspection WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 1/22/2020 Not Ready for Inspection WILLIAM ROSE
Green Building Rough 1/22/2020 Not Ready for Inspection WILLIAM ROSE
PLUMBING-Rough 1/22/2020 Not Ready for Inspection WILLIAM ROSE
Verify Sprinkler Sign Off 1/22/2020 Not Ready for Inspection WILLIAM ROSE
BUILDING-Rough-Frame 1/29/2020 Conditional Approval WILLIAM ROSE
ELECTRICAL-Rough 1/29/2020 Partial Approval WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 1/29/2020 Partial Approval WILLIAM ROSE
Green Building Rough 1/29/2020 Not Ready for Inspection WILLIAM ROSE
HVAC-Rough 1/29/2020 Not Ready for Inspection WILLIAM ROSE
PLUMBING-Rough 1/29/2020 Partial Approval WILLIAM ROSE
Rough-Elec/Plmb/HVAC 1/29/2020 Not Ready for Inspection WILLIAM ROSE
Verify Sprinkler Sign Off 1/29/2020 Not Ready for Inspection WILLIAM ROSE
Deputy Wood Construction 2/3/2020 Conditional Approval WILLIAM ROSE
ELECTRICAL-Rough 2/3/2020 Corrections Issued WILLIAM ROSE
HVAC-Rough 2/3/2020 No Access for Inspection WILLIAM ROSE
PLUMBING-Rough 2/3/2020 No Access for Inspection WILLIAM ROSE
BUILDING-Rough-Frame 2/24/2020 Conditional Approval WILLIAM ROSE
ELECTRICAL-Rough 2/24/2020 Approved WILLIAM ROSE
Green Building Rough 2/24/2020 Approved WILLIAM ROSE
HVAC-Rough 2/24/2020 Approved WILLIAM ROSE
Interior/Exterior Lathing 2/24/2020 Partial Approval WILLIAM ROSE
PLUMBING-Rough 2/24/2020 Approved WILLIAM ROSE
Verify Sprinkler Sign Off 2/24/2020 Approved WILLIAM ROSE
Insulation 2/26/2020 Conditional Approval WILLIAM ROSE
Interior/Exterior Lathing 2/26/2020 Partial Approval WILLIAM ROSE
BUILDING-Rough-Frame 3/11/2020 Approved WILLIAM ROSE
HVAC-Rough 3/11/2020 Approved WILLIAM ROSE
Insulation 3/11/2020 Approved WILLIAM ROSE
Drywall Nailing 3/18/2020 Approved JOHN KLARIN
Gas Test 5/28/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 5/28/2020 SGSOV Approved EUGENE CASSIDY
Sewer 5/28/2020 Not Ready for Inspection EUGENE CASSIDY
Underground Mechanical 5/28/2020 Approved EUGENE CASSIDY
PLUMBING-Final 6/4/2020 Not Ready for Inspection BRIAN CHRISTIAN
Sewer 6/4/2020 Approved BRIAN CHRISTIAN
ELECTRICAL-Final 10/26/2020 Not Ready for Inspection EUGENE CASSIDY
Final 10/26/2020 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 10/26/2020 Approved EUGENE CASSIDY
Gas Test 10/26/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 10/26/2020 Corrections Issued EUGENE CASSIDY
HVAC-Final 10/26/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 10/26/2020 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 10/26/2020 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 10/26/2020 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 12/1/2020 No Access for Inspection EUGENE CASSIDY
Final 12/1/2020 No Access for Inspection EUGENE CASSIDY
Gas Test 12/1/2020 No Access for Inspection EUGENE CASSIDY
Green Building Final 12/1/2020 Corrections Issued EUGENE CASSIDY
HVAC-Final 12/1/2020 No Access for Inspection EUGENE CASSIDY
PLUMBING-Final 12/1/2020 No Access for Inspection EUGENE CASSIDY
Service/Power Release 12/1/2020 No Access for Inspection EUGENE CASSIDY
Smoke Detectors 12/1/2020 No Access for Inspection EUGENE CASSIDY
ELECTRICAL-Final 12/7/2020 Not Ready for Inspection EUGENE CASSIDY
Gas Test 12/7/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 12/7/2020 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 12/7/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 12/7/2020 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 12/7/2020 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 12/7/2020 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 12/14/2020 Not Ready for Inspection EUGENE CASSIDY
Final 12/14/2020 Not Ready for Inspection EUGENE CASSIDY
Gas Test 12/14/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 12/14/2020 Corrections Issued EUGENE CASSIDY
HVAC-Final 12/14/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 12/14/2020 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 12/14/2020 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 12/14/2020 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 2/2/2021 Not Ready for Inspection EUGENE CASSIDY
Final 2/2/2021 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 2/2/2021 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 2/2/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 2/2/2021 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 2/2/2021 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 2/2/2021 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 9/3/2021 Not Ready for Inspection EUGENE CASSIDY
Final 9/3/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 9/3/2021 Approved EUGENE CASSIDY
HVAC-Final 9/3/2021 Approved EUGENE CASSIDY
PLUMBING-Final 9/3/2021 Approved EUGENE CASSIDY
Service/Power Release 9/3/2021 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 9/3/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 9/7/2021 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 9/8/2021 Not Ready for Inspection EUGENE CASSIDY
Final 9/8/2021 Corrections Issued EUGENE CASSIDY
HVAC-Final 9/8/2021 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 9/8/2021 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 9/10/2021 Approved EUGENE CASSIDY
Final 9/10/2021 Corrections Issued EUGENE CASSIDY
Service/Power Release 9/10/2021 Not Ready for Inspection EUGENE CASSIDY
Final 11/5/2021 Corrections Issued EUGENE CASSIDY
Service/Power Release 11/5/2021 Not Ready for Inspection EUGENE CASSIDY
Verify Rec and Parks Fee Memo 11/5/2021 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 11/8/2021 Not Ready for Inspection EUGENE CASSIDY
Verify Rec and Parks Fee Memo 11/8/2021 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 11/9/2021 Approved EUGENE CASSIDY
Final 11/9/2021 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 11/9/2021 Approved EUGENE CASSIDY
PLUMBING-Final 11/9/2021 Approved EUGENE CASSIDY
Service/Power Release 11/9/2021 Approved EUGENE CASSIDY
Verify Rec and Parks Fee Memo 11/9/2021 Approved EUGENE CASSIDY