2426-2426 1/2 E BOULDER ST 90033
Certificate Information: 2426-2426 1/2 E BOULDER ST 90033
- Application / Permit
- 19010-40000-06470
- Plan Check / Job No.
- B19SP01962
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- **1 of 2** New, three-story duplex at the front of the lot. All work per engineered design.
- Permit Issued
- Issued on 10/16/2020
- Issuing Office
- Current Status
- CofO Issued on 12/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | JASON JANGADA |
| Corrections Issued | 1/22/2020 | JASON JANGADA |
| Quality Review Completed | 1/28/2020 | CHRISTOPHER KOMANCHECK |
| Green Plans Picked Up | 4/2/2020 | APPLICANT |
| Applicant returned to address corrections | 6/4/2020 | JASON JANGADA |
| Applicant returned to address corrections | 6/30/2020 | JASON JANGADA |
| Plan Check Approved | 7/2/2020 | JASON JANGADA |
| Issued | 10/16/2020 | APPLICANT |
| Building Plans Picked Up | 10/22/2020 | APPLICANT |
| CofO in Progress | 11/29/2021 | OSVALDO PARAMO |
| CofO in Progress | 11/29/2021 | OSVALDO PARAMO |
| Permit Finaled | 12/1/2021 | DEROLD HAUFF |
| CofO Issued | 12/1/2021 | DEROLD HAUFF |
| Permit Finaled | 12/1/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/11/2020 | EMIL KYUPELYAN |
| Clean Up Green Up | Cleared | 3/11/2020 | KENTON TRINH |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2020 | EMIL KYUPELYAN |
| Highway dedication | Cleared | 3/11/2020 | EMIL KYUPELYAN |
| Permit | Cleared | 3/11/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 3/11/2020 | EMIL KYUPELYAN |
| ZI | Cleared | 3/11/2020 | KENTON TRINH |
| Trees in Parkway | Cleared | 4/8/2020 | JOHN KIM |
| Low Impact Development | Cleared | 4/27/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 4/28/2020 | EMIL KYUPELYAN |
| Green Code | Cleared | 5/8/2020 | RICHARD GARCIA |
| Hydrant and Access approval | Cleared | 5/14/2020 | KURT CORRAL |
| Frnt yard landscape/Water mgmt | Cleared | 5/22/2020 | DANIEL CORONADO |
| GPI Written Notices | Cleared | 6/4/2020 | JASON JANGADA |
| Grading Pre-Inspection | Cleared | 6/4/2020 | JASON JANGADA |
Contact Information
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/13/2020 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 11/13/2020 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/19/2020 | Approved | OSVALDO PARAMO |
| METHANE-Barrier | 11/19/2020 | Approved | OSVALDO PARAMO |
| METHANE-Subgrade | 11/19/2020 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2020 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2020 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2020 | Partial Inspection | OSVALDO PARAMO |
| Deputy Wood Construction | 2/17/2021 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2021 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 3/8/2021 | Partial Approval | OSVALDO PARAMO |
| HVAC-Rough | 3/8/2021 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Rough | 3/9/2021 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 3/9/2021 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 3/9/2021 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 3/12/2021 | Approved | OSVALDO PARAMO |
| Green Building Rough | 3/12/2021 | Approved | OSVALDO PARAMO |
| METHANE-Rough | 3/12/2021 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 3/12/2021 | Approved | OSVALDO PARAMO |
| Wood Frame | 3/12/2021 | Approved | OSVALDO PARAMO |
| Insulation | 3/18/2021 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 3/24/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 3/24/2021 | Approved | OSVALDO PARAMO |
| Gas Test | 4/29/2021 | Partial Approval | OSVALDO PARAMO |
| Sewer | 4/29/2021 | Approved | OSVALDO PARAMO |
| Verify Rec and Parks Fee Memo | 7/12/2021 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 10/21/2021 | Approved | OSVALDO PARAMO |
| Final | 10/21/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Gas Test | 10/21/2021 | Approved | OSVALDO PARAMO |
| Green Building Final | 10/21/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 10/21/2021 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 10/21/2021 | Approved | OSVALDO PARAMO |
| HVAC-Final | 10/26/2021 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 10/26/2021 | Approved | OSVALDO PARAMO |
| Final | 10/27/2021 | OK to Issue CofO | OSVALDO PARAMO |
| Green Building Final | 10/27/2021 | Approved | OSVALDO PARAMO |
| Service/Power Release | 10/27/2021 | Approved | OSVALDO PARAMO |