1543 W 216TH ST 90501
Certificate Information: 1543 W 216TH ST 90501
- Application / Permit
- 19010-40000-05345
- Plan Check / Job No.
- B19SP01830
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New one story detached accessory dwelling unit per AB494 and SB229
- Permit Issued
- Issued on 2/28/2020
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 10/30/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2019 | JASON JANGADA |
| Corrections Issued | 12/26/2019 | JASON JANGADA |
| Green Plans Picked Up | 12/27/2019 | APPLICANT |
| Quality Review Completed | 1/2/2020 | CHRISTOPHER KOMANCHECK |
| Building Plans Picked Up | 1/6/2020 | APPLICANT |
| Applicant returned to address corrections | 2/28/2020 | JASON JANGADA |
| Plan Check Approved | 2/28/2020 | JASON JANGADA |
| Issued | 2/28/2020 | LADBS |
| CofO in Progress | 8/25/2020 | JOHN KLARIN |
| Permit Finaled | 10/30/2020 | DEROLD HAUFF |
| CofO Issued | 10/30/2020 | DEROLD HAUFF |
| Permit Finaled | 10/30/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/28/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2020 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 2/3/2020 | JOHN CONNEALLY |
| Sewer availability | Cleared | 2/3/2020 | WALLIE JONG |
| Low Impact Development | Cleared | 2/14/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 2/14/2020 | ROSA SILVA |
| Green Code | Cleared | 2/26/2020 | DONALD CRICHLOW |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Donlong Peter; Lic. No.: S3948 | 8748 E VALLEY BLVD L ROSEMEAD, CA 91770 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/19/2020 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 3/19/2020 | Corrections Issued | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 4/1/2020 | Conditional Approval | EUGENE CASSIDY |
| Pre-Inspection | 4/1/2020 | Conditional Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2020 | Corrections Issued | EUGENE CASSIDY |
| Underground Mechanical | 4/14/2020 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/16/2020 | Partial Inspection | JOHN KLARIN |
| PLUMBING-Rough | 4/16/2020 | Partial Inspection | JOHN KLARIN |
| Insulation | 4/20/2020 | Corrections Issued | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2020 | Partial Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2020 | Partial Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 5/14/2020 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 5/14/2020 | Approved | JOHN KLARIN |
| Insulation | 5/18/2020 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 5/18/2020 | Approved | JOHN KLARIN |
| Drywall Nailing | 5/21/2020 | Approved | JOHN KLARIN |
| Green Building Rough | 5/21/2020 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 5/27/2020 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/20/2020 | Approved | JOHN KLARIN |
| Final | 7/20/2020 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 7/20/2020 | Approved | JOHN KLARIN |
| Green Building Final | 7/20/2020 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 7/20/2020 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 7/20/2020 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 7/20/2020 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 7/20/2020 | Approved | JOHN KLARIN |
| Final | 7/27/2020 | Corrections Issued | JOHN KLARIN |
| Service/Power Release | 7/27/2020 | Not Ready for Inspection | JOHN KLARIN |
| Final | 8/24/2020 | OK to Issue CofO | JOHN KLARIN |
| Service/Power Release | 8/24/2020 | Approved | JOHN KLARIN |