1203 W G ST 90744

Certificate Information: 1203 W G ST 90744

Application / Permit
19010-40000-05034
Plan Check / Job No.
B19SP01733
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached accessory dwelling unit per AB494 and SB229 at rear of property. All work per WFPP.
Permit Issued
Issued on 8/10/2020
Issuing Office
Current Status
CofO Issued on 6/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 KAVIAN REFAHI
Corrections Issued 12/5/2019 KAVIAN REFAHI
Quality Review Completed 12/12/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 12/18/2019 APPLICANT
Green Plans Picked Up 12/18/2019 APPLICANT
Applicant returned to address corrections 4/14/2020 KAVIAN REFAHI
Plan Check Approved 8/4/2020 KAVIAN REFAHI
Issued 8/10/2020 APPLICANT
CofO in Progress 6/21/2025 MICHAEL PELHAM
Permit Finaled 6/23/2025 RICHARD STEINBACH
CofO Issued 6/23/2025 RICHARD STEINBACH
Permit Finaled 6/23/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 2/4/2020 YEGANEH SADEGHI
Eng Process Fee Ord 176,300 Cleared 2/4/2020 YEGANEH SADEGHI
Sewer availability Cleared 2/4/2020 YEGANEH SADEGHI
Hydrant and Access approval Cleared 3/3/2020 GEORGE SUCHAND
Low Impact Development Cleared 3/3/2020 MARTIN FRAGOSO
Green Code Cleared 3/4/2020 DONALD CRICHLOW
Roof/Waste drainage to street Cleared 3/9/2020 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/12/2021 Partial Approval JOHN KLARIN
Footing/Foundation/Slab 2/2/2021 Corrections Issued JOHN KLARIN
METHANE-Barrier 2/2/2021 Not Ready for Inspection JOHN KLARIN
METHANE-Subgrade 2/2/2021 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 2/9/2021 Approved JOHN KLARIN
METHANE-Barrier 2/9/2021 Approved JOHN KLARIN
METHANE-Subgrade 2/9/2021 Approved JOHN KLARIN
PLUMBING-Rough 2/18/2021 Partial Approval JOHN KLARIN
Insulation 2/25/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/4/2021 Partial Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 3/31/2021 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 4/9/2021 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 4/9/2021 Corrections Issued JOHN KLARIN
Green Building Rough 4/9/2021 Not Ready for Inspection JOHN KLARIN
HVAC-Rough 4/9/2021 Corrections Issued JOHN KLARIN
METHANE-Rough 4/9/2021 Approved JOHN KLARIN
PLUMBING-Rough 4/9/2021 Corrections Issued JOHN KLARIN
Verify Sprinkler Sign Off 4/9/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 4/29/2021 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 4/29/2021 Corrections Issued JOHN KLARIN
Green Building Rough 4/29/2021 Approved JOHN KLARIN
HVAC-Rough 4/29/2021 Partial Inspection JOHN KLARIN
PLUMBING-Rough 4/29/2021 Partial Approval JOHN KLARIN
ELECTRICAL-Rough 5/5/2021 Approved JOHN KLARIN
Insulation 5/10/2021 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 5/10/2021 Partial Approval SABAS ALONSO
Insulation 5/14/2021 Approved ANSON MAGLASANG
Drywall Nailing 5/20/2021 Approved JOHN KLARIN
ELECTRICAL-Final 7/20/2021 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 8/24/2021 Approved JOHN KLARIN
Final 8/24/2021 Corrections Issued JOHN KLARIN
Green Building Final 8/24/2021 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 8/24/2021 SGSOV Approved JOHN KLARIN
Service/Power Release 8/24/2021 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 8/24/2021 Approved JOHN KLARIN
Final 6/21/2025 OK to Issue CofO MICHAEL PELHAM
Green Building Final 6/21/2025 Approved MICHAEL PELHAM
Service/Power Release 6/21/2025 Not Required MICHAEL PELHAM