1254 N CARY AVE 90744

Certificate Information: 1254 N CARY AVE 90744

Application / Permit
19010-40000-04337
Plan Check / Job No.
B19SP01521
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New one-story, irregular-shaped Accessory Dwellling Unit (ADU) (1,101 SF) per LAMC 12.22 A.33 (c)-(d) at rear of property
Permit Issued
Issued on 5/23/2023
Issuing Office
San Pedro
Current Status
CofO Issued on 5/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 REZA HAGHIGHAT
Corrections Issued 10/28/2019 REZA HAGHIGHAT
Quality Review Completed 11/8/2019 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 11/8/2019 APPLICANT
Building Plans Picked Up 11/13/2019 APPLICANT
Plan Check Approved 3/1/2023 REZA HAGHIGHAT
Issued 5/23/2023 APPLICANT
CofO in Progress 5/21/2025 ANSON MAGLASANG
Permit Finaled 5/21/2025 ANSON MAGLASANG
CofO Issued 5/21/2025 ANSON MAGLASANG
Permit Finaled 5/21/2025 ANSON MAGLASANG

Permit Application Clearance Information

HPOZ Cleared 11/18/2019 BRADLEY FURUYA
ZA Case Cleared 11/18/2019 BRADLEY FURUYA
ZI Cleared 11/18/2019 BRADLEY FURUYA
Address approval Cleared 9/29/2020 CHINH DINH
Clean Up Green Up Cleared 9/29/2020 JOE LUCKEY
Eng Process Fee Ord 176,300 Cleared 10/7/2020 CHINH DINH
Sewer availability Cleared 10/7/2020 CHINH DINH
Low Impact Development Cleared 11/4/2021 TA ANH
Hydrant and Access approval Cleared 2/25/2022 LAURINDA MEADE
Roof/Waste drainage to street Cleared 4/1/2022 JOSE HERNANDEZ
Green Code Cleared 3/1/2023 RICHARD GARCIA
Hold Cleared 6/29/2023 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/5/2023 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/5/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Barrier 7/5/2023 Approved EUGENE CASSIDY
METHANE-Subgrade 7/5/2023 Approved EUGENE CASSIDY
Piling/Pier/Caisson 7/5/2023 Not Ready for Inspection EUGENE CASSIDY
Pre-Inspection 7/5/2023 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 7/25/2023 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/25/2023 Not Ready for Inspection EUGENE CASSIDY
Piling/Pier/Caisson 7/25/2023 Not Ready for Inspection EUGENE CASSIDY
Pre-Inspection 7/25/2023 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 7/27/2023 Approved EUGENE CASSIDY
Piling/Pier/Caisson 7/27/2023 Approved EUGENE CASSIDY
Pre-Inspection 7/27/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/4/2023 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 8/4/2023 Approved EUGENE CASSIDY
Green Building Rough 8/4/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 8/4/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 8/4/2023 Partial Approval EUGENE CASSIDY
Reinforced Concrete Frame 8/4/2023 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 8/4/2023 Approved EUGENE CASSIDY
Wood Frame 8/4/2023 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 8/8/2023 Partial Approval JOHN KLARIN
Wood Frame 8/8/2023 Partial Approval JOHN KLARIN
PLUMBING-Rough 9/15/2023 Corrections Issued EUGENE CASSIDY
Wood Frame 9/15/2023 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 9/28/2023 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 9/28/2023 Corrections Issued EUGENE CASSIDY
Wood Frame 10/12/2023 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 10/27/2023 Approved EUGENE CASSIDY
ELECTRICAL-Rough 10/27/2023 Approved EUGENE CASSIDY
Green Building Rough 10/27/2023 Approved EUGENE CASSIDY
Insulation 11/14/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 11/14/2023 Partial Approval EUGENE CASSIDY
Drywall Nailing 11/21/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 12/20/2023 Approved EUGENE CASSIDY
Shower Pan 12/20/2023 Approved EUGENE CASSIDY
Final 6/27/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 6/27/2024 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/27/2024 SGSOV Approved EUGENE CASSIDY
Service/Power Release 6/27/2024 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 6/27/2024 Approved EUGENE CASSIDY
Final 8/16/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 8/16/2024 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 8/16/2024 Not Ready for Inspection EUGENE CASSIDY
Final 3/7/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 3/7/2025 No Access for Inspection EUGENE CASSIDY
Service/Power Release 3/7/2025 No Access for Inspection EUGENE CASSIDY
Final 4/14/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 4/14/2025 Approved EUGENE CASSIDY
Service/Power Release 4/14/2025 Not Ready for Inspection EUGENE CASSIDY
Final 4/24/2025 Corrections Issued EUGENE CASSIDY
Service/Power Release 4/24/2025 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 5/9/2025 Approved EUGENE CASSIDY
Final 5/9/2025 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 5/9/2025 Approved EUGENE CASSIDY
PLUMBING-Final 5/9/2025 Approved EUGENE CASSIDY
Service/Power Release 5/9/2025 Not Required EUGENE CASSIDY