8943 S ST ANDREWS PL 90047
Certificate Information: 8943 S ST ANDREWS PL 90047
- Application / Permit
- 19010-40000-04292
- Plan Check / Job No.
- B19SP01494
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) One-story Accessory Dwelling Unit per SB229 and AB494. All work per WFPP.
- Permit Issued
- Issued on 5/24/2022
- Issuing Office
- Current Status
- Issued on 5/24/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2019 | JASON JANGADA |
| Corrections Issued | 10/23/2019 | JASON JANGADA |
| Quality Review Completed | 11/7/2019 | CHRISTOPHER KOMANCHECK |
| Building Plans Picked Up | 2/25/2020 | APPLICANT |
| Green Plans Picked Up | 2/28/2020 | APPLICANT |
| Applicant returned to address corrections | 6/16/2021 | JASON JANGADA |
| Applicant returned to address corrections | 10/20/2021 | JASON JANGADA |
| Applicant returned to address corrections | 10/21/2021 | JASON JANGADA |
| Plan Check Approved | 11/5/2021 | JASON JANGADA |
| Issued | 5/24/2022 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 3/24/2020 | RICHARD GARCIA |
| Low Impact Development | Cleared | 10/9/2020 | MITESH PATEL |
| Address approval | Cleared | 1/14/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 2/4/2021 | MATTHEW CRAIG |
| Sewer availability | Cleared | 2/4/2021 | CECILIO NAVARRO |
| Construction near power lines | Cleared | 3/17/2021 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 4/8/2021 | THAN WIN |
Contact Information
| Contractor | Trinity Contracting Concepts Inc; Lic. No.: 1001565-B | 6709 LA TIJERA BLVD #134 LOS ANGELES, CA 90045 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/29/2022 | Approved | RYAN SALAZAR |
| Insulation | 9/29/2022 | Corrections Issued | ENRIQUE MIRELES |
| Sewer | 9/29/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/13/2022 | Corrections Issued | ENRIQUE MIRELES |
| METHANE-Barrier | 11/29/2022 | Approved | ENRIQUE MIRELES |
| METHANE-Subgrade | 11/29/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/29/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 12/8/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 2/27/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 2/27/2023 | Approved | ENRIQUE MIRELES |
| METHANE-Rough | 2/27/2023 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 2/27/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 3/6/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/6/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 3/14/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/14/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/11/2023 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/25/2023 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/3/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 3/15/2024 | Corrections Issued | MICHAEL LEWIS |
| Insulation | 3/15/2024 | Corrections Issued | MICHAEL LEWIS |
| Drywall Nailing | 5/31/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 5/31/2024 | Corrections Issued | JOSE MACIAS |
| HVAC-Rough | 6/18/2024 | Approved | JOSE MACIAS |
| Insulation | 6/18/2024 | Not Ready for Inspection | JOSE MACIAS |
| Shower Pan | 6/18/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 4/2/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Gas Test | 4/2/2025 | Approved | WAYNE REGESTER |
| Service/Power Release | 4/2/2025 | Approved | WAYNE REGESTER |