755-757 E 84TH ST 90001

Certificate Information: 755-757 E 84TH ST 90001

Application / Permit
19010-40000-03342
Plan Check / Job No.
B19SP01245
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) Two-Story Duplex (3,605 SF) with deck over attached two-car garage (400 SF). Provide two open-air stalls on site. All work per engineered design.
Permit Issued
Issued on 1/30/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/15/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2019 APPLICANT
Assigned to Plan Check Engineer 8/22/2019 JASON JANGADA
Corrections Issued 8/26/2019 JASON JANGADA
Quality Review Completed 8/29/2019 CHRISTOPHER KOMANCHECK
Building Plans Picked Up 9/3/2019 APPLICANT
Green Plans Picked Up 9/20/2019 APPLICANT
Applicant returned to address corrections 10/25/2019 JASON JANGADA
Plan Check Approved 11/4/2019 JASON JANGADA
Issued 1/30/2020 LADBS
CofO in Progress 8/3/2020 FREDDIE RIVERA
Permit Finaled 8/15/2020 DEROLD HAUFF
CofO Issued 8/15/2020 DEROLD HAUFF
Permit Finaled 8/15/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/10/2019 THOMAS LANG
Highway dedication Cleared 9/10/2019 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 10/8/2019 JEANETTE VONG
Hydrant and Access approval Cleared 10/8/2019 JEREMY CARTER
Low Impact Development Cleared 10/8/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 10/8/2019 JEANETTE VONG
Sewer availability Cleared 10/8/2019 JEANETTE VONG
Green Code Cleared 10/10/2019 RICHARD GARCIA

Contact Information

Contractor Advanced Construction; Lic. No.: 801955-B 18841 PASADERO DRIVE      TARZANA, CA 91356
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/4/2020 Corrections Issued EUGENE CASSIDY
Underground Mechanical 2/4/2020 Conditional Approval EUGENE CASSIDY
Deputy Other (see comments) 2/11/2020 Approved EUGENE CASSIDY
Deputy Reinf. Concrete 2/11/2020 Approved EUGENE CASSIDY
Footing/Foundation/Slab 2/11/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 3/5/2020 Corrections Issued EUGENE CASSIDY
Green Building Rough 3/5/2020 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 3/5/2020 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/6/2020 Partial Approval JOAQUIN GREENOUGH
Deputy Wood Construction 3/18/2020 Conditional Approval BOB DUNN
Wood Frame 3/19/2020 Partial Approval EUGENE CASSIDY
Insulation 3/24/2020 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 4/10/2020 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 4/10/2020 Partial Approval JOSEPH MCGARRY
Green Building Rough 4/10/2020 Approved JOSEPH MCGARRY
HVAC-Rough 4/10/2020 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 4/10/2020 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 4/10/2020 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 4/10/2020 Approved JOSEPH MCGARRY
Insulation 4/14/2020 Approved BRIAN CHRISTIAN
Sewer 4/14/2020 Approved BRIAN CHRISTIAN
Drywall Nailing 4/21/2020 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 4/27/2020 Approved BRIAN CHRISTIAN
PLUMBING-Rough 6/19/2020 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 6/19/2020 Corrections Issued ALEJANDRO DE ARTOLA
Final 7/28/2020 Corrections Issued FREDDIE RIVERA
Green Building Final 7/28/2020 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 7/28/2020 SGSOV Approved FREDDIE RIVERA
Service/Power Release 7/28/2020 Not Ready for Inspection FREDDIE RIVERA
Smoke Detectors 7/28/2020 Not Ready for Inspection FREDDIE RIVERA
Final 7/31/2020 OK for TCO FREDDIE RIVERA
Service/Power Release 7/31/2020 Approved FREDDIE RIVERA