725 E 107TH ST 90002
Certificate Information: 725 E 107TH ST 90002
- Application / Permit
- 19010-40000-03310
- Plan Check / Job No.
- B19SP01233
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) one story accessory dwelling unit per AB494 and SB229 at rear of property. All work per engineered design.
- Permit Issued
- Issued on 7/18/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2019 | JASON JANGADA |
| Corrections Issued | 9/5/2019 | JASON JANGADA |
| Quality Review Completed | 9/6/2019 | CHRISTOPHER KOMANCHECK |
| Building Plans Picked Up | 9/17/2019 | APPLICANT |
| Green Plans Picked Up | 9/17/2019 | APPLICANT |
| Applicant returned to address corrections | 12/26/2019 | JASON JANGADA |
| Applicant returned to address corrections | 3/3/2020 | JASON JANGADA |
| Applicant returned to address corrections | 3/11/2020 | JASON JANGADA |
| Plan Check Approved | 3/13/2020 | JASON JANGADA |
| Issued | 7/18/2023 | APPLICANT |
| CofO in Progress | 5/14/2024 | BEN MOLSTAD |
| Permit Finaled | 5/16/2024 | ANSON MAGLASANG |
| CofO Issued | 5/16/2024 | ANSON MAGLASANG |
| Permit Finaled | 5/16/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 10/18/2019 | BANAFSHEH BARATI |
| Construction near power lines | Cleared | 1/11/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 2/24/2020 | JORGE MEJIA LEMUS |
| Hydrant and Access approval | Cleared | 2/25/2020 | DOMINIQUE MEDINA |
| Green Code | Cleared | 2/27/2020 | RICHARD GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2020 | CHINH DINH |
| Roof/Waste drainage to street | Cleared | 3/11/2020 | YEGANEH SADEGHI |
| Sewer availability | Cleared | 3/11/2020 | YEGANEH SADEGHI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chaiprasert,, Victor V; Lic. No.: C36235 | 17703 CRENSHAW BLVD TORRANCE, CA 90504 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/25/2023 | Partial Approval | JOHN KLARIN |
| Footing/Foundation/Slab | 7/26/2023 | Approved | JOHN KLARIN |
| Pre-Inspection | 7/28/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 8/17/2023 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 8/17/2023 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2023 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 8/17/2023 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 8/17/2023 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 8/17/2023 | Approved | JOHN KLARIN |
| Wood Frame | 8/21/2023 | Corrections Issued | JOHN KLARIN |
| Gas Test | 8/24/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Insulation | 8/24/2023 | Approved | JAMES CHAVEZ |
| Gas Test | 8/28/2023 | Approved | JOHN KLARIN |
| Insulation | 8/28/2023 | Approved | JOHN KLARIN |
| Wood Frame | 8/28/2023 | Corrections Issued | JOHN KLARIN |
| Drywall Nailing | 8/31/2023 | Partial Approval | JOHN KLARIN |
| Green Building Rough | 8/31/2023 | Partial Approval | JOHN KLARIN |
| HVAC-Rough | 8/31/2023 | Corrections Issued | JOHN KLARIN |
| Interior/Exterior Lathing | 8/31/2023 | Approved | JOHN KLARIN |
| HVAC-Rough | 9/12/2023 | Approved | JOHN KLARIN |
| Shower Pan | 9/12/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/3/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 11/3/2023 | Approved | JOHN KLARIN |
| Final | 11/3/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 11/3/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Rough | 11/3/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 11/3/2023 | SGSOV Not Ready | JOHN KLARIN |
| Service/Power Release | 11/3/2023 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 11/3/2023 | Approved | JOHN KLARIN |
| Final | 11/28/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 11/28/2023 | Approved | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 11/28/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 11/28/2023 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 11/28/2023 | Not Ready for Inspection | JOHN KLARIN |
| Final | 2/2/2024 | Corrections Issued | JOHN KLARIN |
| Service/Power Release | 2/2/2024 | Not Ready for Inspection | JOHN KLARIN |
| Underground Mechanical | 2/16/2024 | Partial Approval | BEN MOLSTAD |
| ELECTRICAL-Final | 2/22/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 2/22/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 3/4/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 3/4/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Service/Power Release | 3/4/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 3/20/2024 | Corrections Issued | BEN MOLSTAD |
| Gas Test | 3/20/2024 | Approved | BEN MOLSTAD |
| Service/Power Release | 3/20/2024 | Approved | BEN MOLSTAD |
| Final | 3/29/2024 | Corrections Issued | BEN MOLSTAD |
| Special/Order Compliance | 4/5/2024 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 5/13/2024 | Approved | BEN MOLSTAD |
| Final | 5/13/2024 | OK to Issue CofO | BEN MOLSTAD |
| HVAC-Final | 5/13/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 5/13/2024 | Approved | BEN MOLSTAD |