5233 1/2 W LEXINGTON AVE 90029
Certificate Information: 5233 1/2 W LEXINGTON AVE 90029
- Application / Permit
- 19010-40000-01982
- Plan Check / Job No.
- B19SP00751
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ACCESSORY DWELLING UNIT AT REAR PER AB 494 & SB 229.
- Permit Issued
- Issued on 1/16/2020
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 4/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2019 | JASON JANGADA |
| Corrections Issued | 6/7/2019 | JASON JANGADA |
| Quality Review Completed | 6/11/2019 | CHRISTOPHER KOMANCHECK |
| Applicant returned to address corrections | 7/23/2019 | JASON JANGADA |
| Building Plans Picked Up | 7/26/2019 | APPLICANT |
| Applicant returned to address corrections | 8/23/2019 | JASON JANGADA |
| Applicant returned to address corrections | 9/6/2019 | JASON JANGADA |
| Applicant returned to address corrections | 9/27/2019 | JASON JANGADA |
| Applicant returned to address corrections | 1/8/2020 | JASON JANGADA |
| Plan Check Approved | 1/16/2020 | JASON JANGADA |
| Issued | 1/16/2020 | LADBS |
| CofO in Progress | 4/5/2021 | BRIAN SULLIVAN |
| Permit Finaled | 4/14/2021 | DEROLD HAUFF |
| CofO Issued | 4/14/2021 | DEROLD HAUFF |
| Permit Finaled | 4/14/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/23/2019 | PHILLIP WILSON |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2019 | PHILLIP WILSON |
| Roof/Waste drainage to street | Cleared | 8/23/2019 | PHILLIP WILSON |
| Sewer availability | Cleared | 9/6/2019 | PHILLIP WILSON |
| Hydrant and Access approval | Cleared | 10/4/2019 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 11/4/2019 | MITESH PATEL |
| Green Code | Cleared | 11/27/2019 | JASON JANGADA |
| Disturb/Remove Protected Trees | Cleared | 12/24/2019 | STEPHEN DUPREY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ogiamien,, Ikponmwosa David; Lic. No.: C83249 | 226 PASO NOGAL RD PLEASANT HILL, CA 94523 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/6/2020 | Approved | ROBERT CORNELL |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2020 | Partial Approval | ROBERT CORNELL |
| Insulation | 2/28/2020 | Partial Approval | ROBERT CORNELL |
| PLUMBING-Rough | 2/28/2020 | Partial Approval | ROBERT CORNELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2020 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 5/5/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 5/18/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Green Building Rough | 5/18/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 5/18/2020 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 5/18/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 5/18/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 6/11/2020 | Approved | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 6/11/2020 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 6/16/2020 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 6/16/2020 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 6/16/2020 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 6/16/2020 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 6/16/2020 | Approved | BRIAN SULLIVAN |
| Insulation | 6/18/2020 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 6/30/2020 | Approved | BRIAN SULLIVAN |
| Final | 9/28/2020 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Final | 9/28/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 9/28/2020 | SGSOV Not Ready | BRIAN SULLIVAN |
| Service/Power Release | 9/28/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Smoke Detectors | 9/28/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Final | 10/7/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Green Building Final | 10/7/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 10/7/2020 | SGSOV Approved | BRIAN SULLIVAN |
| Service/Power Release | 10/7/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Smoke Detectors | 10/7/2020 | Approved | BRIAN SULLIVAN |
| Final | 3/3/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Green Building Final | 3/3/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Service/Power Release | 3/3/2021 | Approved | BRIAN SULLIVAN |
| Final | 4/5/2021 | OK to Issue CofO | BRIAN SULLIVAN |
| Green Building Final | 4/5/2021 | Approved | BRIAN SULLIVAN |