1137 N MARINE AVE 90744
Certificate Information: 1137 N MARINE AVE 90744
- Application / Permit
- 19010-40000-01660
- Plan Check / Job No.
- B19SP00645
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New SFD with attached garage 2-car garage and covered patio.
- Permit Issued
- Issued on 5/12/2020
- Issuing Office
- Current Status
- CofO Issued on 10/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2019 | MANUEL GARCIA |
| Corrections Issued | 5/24/2019 | MANUEL GARCIA |
| Quality Review Completed | 5/30/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 6/3/2019 | APPLICANT |
| Green Plans Picked Up | 6/3/2019 | APPLICANT |
| Plan Check Approved | 12/19/2019 | MANUEL GARCIA |
| Issued | 5/12/2020 | APPLICANT |
| CofO in Progress | 9/28/2023 | EUGENE CASSIDY |
| Permit Finaled | 10/10/2023 | DANIEL ORRANTE |
| CofO Issued | 10/10/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/10/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Abandoned oil well | Cleared | 12/5/2019 | JEREMY CARTER |
| Abandoned oil well approval | Cleared | 12/5/2019 | JEREMY CARTER |
| Address approval | Cleared | 12/5/2019 | CELINA MORENO |
| Clean Up Green Up | Cleared | 12/5/2019 | SOPHIE GABEL-SCHEINBAU |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2019 | CELINA MORENO |
| Green Code | Cleared | 12/5/2019 | RICHARD GARCIA |
| Hydrant and Access approval | Cleared | 12/5/2019 | JEREMY CARTER |
| Low Impact Development | Cleared | 12/5/2019 | ORVAL HERNANDEZ-MARCIAL |
| Permit | Cleared | 12/5/2019 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 12/5/2019 | CELINA MORENO |
| Sewer availability | Cleared | 12/5/2019 | CELINA MORENO |
| Trees in Parkway | Cleared | 12/10/2019 | JOHN KIM |
Contact Information
| Contractor | Global One Construction Incorporated; Lic. No.: 1010376-B | 1361 HYATT AVENUE WILMINGTON, CA 90744 |
| Engineer | Zelada,, Mynor Anibal; Lic. No.: C48666 | 14545 VICTORY BLVD 405 VAN NUYS, CA 91411 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/30/2020 | Partial Approval | JOHN KLARIN |
| Deputy Methane Barrier | 7/1/2020 | Approved | JOHN KLARIN |
| Deputy Methane Barrier | 7/2/2020 | Partial Approval | JOHN KLARIN |
| Deputy Methane Barrier | 7/10/2020 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 7/10/2020 | Approved | JOHN KLARIN |
| METHANE-Barrier | 7/10/2020 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 7/10/2020 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2020 | Partial Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 10/9/2020 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 10/9/2020 | Corrections Issued | JOHN KLARIN |
| METHANE-Rough | 10/9/2020 | Approved | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 10/9/2020 | Corrections Issued | JOHN KLARIN |
| Verify Sprinkler Sign Off | 10/9/2020 | Not Ready for Inspection | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 10/21/2020 | Approved | JOHN KLARIN |
| Insulation | 11/5/2020 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 11/5/2020 | Approved | JOHN KLARIN |
| Drywall Nailing | 11/16/2020 | Approved | JOHN KLARIN |
| Sewer | 11/17/2021 | Corrections Issued | JOHN KLARIN |
| Sewer | 11/22/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/10/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 7/10/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 7/10/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 7/10/2023 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 7/10/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 7/10/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 7/10/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/21/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 7/21/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 7/21/2023 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 7/21/2023 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 7/21/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 7/21/2023 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 7/21/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/9/2023 | Approved | EUGENE CASSIDY |
| Final | 8/9/2023 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 8/9/2023 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 8/9/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 8/9/2023 | Approved | EUGENE CASSIDY |
| Final | 9/7/2023 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 9/7/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 9/22/2023 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 9/22/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 9/27/2023 | Approved | EUGENE CASSIDY |
| Final | 9/27/2023 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 9/27/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 9/27/2023 | Approved | EUGENE CASSIDY |
| Service/Power Release | 9/27/2023 | Approved | EUGENE CASSIDY |