1752 N VAN TRESS AVE 90744
Certificate Information: 1752 N VAN TRESS AVE 90744
- Application / Permit
- 19010-40000-01367
- Plan Check / Job No.
- B19SP00531
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- New det. 2-car garage (20' x 20') in rear of the lot. per engineering design.
- Permit Issued
- Issued on 1/8/2020
- Issuing Office
- San Pedro
- Current Status
- Issued on 1/8/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2019 | REZA HAGHIGHAT |
| Corrections Issued | 5/1/2019 | REZA HAGHIGHAT |
| Quality Review Completed | 5/10/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 5/13/2019 | APPLICANT |
| Green Plans Picked Up | 5/21/2019 | APPLICANT |
| Applicant returned to address corrections | 12/23/2019 | REZA HAGHIGHAT |
| Plan Check Approved | 1/7/2020 | REZA HAGHIGHAT |
| Issued | 1/8/2020 | LADBS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2019 | TRACY TATE |
| Green Code | Cleared | 12/13/2019 | RICHARD GARCIA |
| Roof/Waste drainage to street | Cleared | 12/13/2019 | TRACY TATE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Assink,, Aart; Lic. No.: C39390 | 1611 EL PRADO AVE TORRANCE, CA 90501 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Barrier | 7/30/2020 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 7/30/2020 | Approved | JOHN KLARIN |
| Pre-Inspection | 7/30/2020 | Approved | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 9/4/2020 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/4/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 9/16/2020 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 9/16/2020 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/5/2020 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 11/5/2020 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 11/5/2020 | Approved | JOHN KLARIN |
| METHANE-Rough | 11/5/2020 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 3/30/2021 | Approved | JOHN KLARIN |
| Drywall Nailing | 3/30/2021 | Approved | JOHN KLARIN |
| Final | 3/30/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 3/30/2021 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 3/30/2021 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 3/30/2021 | Approved | JOHN KLARIN |
| Smoke Detectors | 3/30/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 4/8/2021 | Approved | JOHN KLARIN |
| Final | 4/8/2021 | Corrections Issued | JOHN KLARIN |
| HVAC-Final | 4/8/2021 | Approved | JOHN KLARIN |
| PLUMBING-Final | 4/8/2021 | Approved | JOHN KLARIN |