1752 N VAN TRESS AVE 90744

Certificate Information: 1752 N VAN TRESS AVE 90744

Application / Permit
19010-40000-01367
Plan Check / Job No.
B19SP00531
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
New det. 2-car garage (20' x 20') in rear of the lot. per engineering design.
Permit Issued
Issued on 1/8/2020
Issuing Office
San Pedro
Current Status
Issued on 1/8/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/3/2019 APPLICANT
Assigned to Plan Check Engineer 4/18/2019 REZA HAGHIGHAT
Corrections Issued 5/1/2019 REZA HAGHIGHAT
Quality Review Completed 5/10/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 5/13/2019 APPLICANT
Green Plans Picked Up 5/21/2019 APPLICANT
Applicant returned to address corrections 12/23/2019 REZA HAGHIGHAT
Plan Check Approved 1/7/2020 REZA HAGHIGHAT
Issued 1/8/2020 LADBS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/13/2019 TRACY TATE
Green Code Cleared 12/13/2019 RICHARD GARCIA
Roof/Waste drainage to street Cleared 12/13/2019 TRACY TATE

Contact Information

Contractor Owner-Builder       ,
Engineer Assink,, Aart; Lic. No.: C39390 1611 EL PRADO AVE      TORRANCE, CA 90501

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Barrier 7/30/2020 Approved JOHN KLARIN
METHANE-Subgrade 7/30/2020 Approved JOHN KLARIN
Pre-Inspection 7/30/2020 Approved JOHN KLARIN
Excavation/Setback/Form/Re-Bar 9/4/2020 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 9/4/2020 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 9/16/2020 Approved JOHN KLARIN
Footing/Foundation/Slab 9/16/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 11/5/2020 Partial Approval JOHN KLARIN
ELECTRICAL-Rough 11/5/2020 Not Ready for Inspection JOHN KLARIN
Green Building Rough 11/5/2020 Approved JOHN KLARIN
METHANE-Rough 11/5/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 3/30/2021 Approved JOHN KLARIN
Drywall Nailing 3/30/2021 Approved JOHN KLARIN
Final 3/30/2021 Corrections Issued JOHN KLARIN
Green Building Final 3/30/2021 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 3/30/2021 SGSOV Approved JOHN KLARIN
Service/Power Release 3/30/2021 Approved JOHN KLARIN
Smoke Detectors 3/30/2021 Approved JOHN KLARIN
ELECTRICAL-Final 4/8/2021 Approved JOHN KLARIN
Final 4/8/2021 Corrections Issued JOHN KLARIN
HVAC-Final 4/8/2021 Approved JOHN KLARIN
PLUMBING-Final 4/8/2021 Approved JOHN KLARIN