1122 W 18TH ST 90731

Certificate Information: 1122 W 18TH ST 90731

Application / Permit
19010-40000-01346
Plan Check / Job No.
B19SP00519
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
(N) Detached two-car garage (20' x 20') at rear of property. All work per engineered design.
Permit Issued
Issued on 2/28/2020
Issuing Office
San Pedro
Current Status
CofO Issued on 2/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2019 APPLICANT
Assigned to Plan Check Engineer 5/3/2019 CHRISTOPHER KOMANCHECK
Green Plans Picked Up 5/10/2019 APPLICANT
Corrections Issued 5/15/2019 MUKUL GUPTA
Quality Review Completed 5/22/2019 CHRISTOPHER KOMANCHECK
Building Plans Picked Up 5/22/2019 APPLICANT
Applicant returned to address corrections 1/9/2020 CHRISTOPHER KOMANCHECK
Plan Check Approved 1/16/2020 CHRISTOPHER KOMANCHECK
Issued 2/28/2020 LADBS
CofO in Progress 2/13/2024 EUGENE CASSIDY
Permit Finaled 2/22/2024 ANSON MAGLASANG
CofO Issued 2/22/2024 ANSON MAGLASANG
Permit Finaled 2/22/2024 ANSON MAGLASANG

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/15/2019 MUKUL GUPTA
Construction near power lines Cleared 9/3/2019 RIDWAN HARDY
Low Impact Development Cleared 11/26/2019 ORVAL HERNANDEZ-MARCIAL
Green Code Cleared 12/27/2019 RICHARD GARCIA
Eng Process Fee Ord 176,300 Cleared 1/9/2020 BANAFSHEH BARATI
Roof/Waste drainage to street Cleared 1/9/2020 BANAFSHEH BARATI
Sewer availability Cleared 1/9/2020 BANAFSHEH BARATI
Hydrant and Access approval Cleared 1/16/2020 GILBERT URREA

Contact Information

Contractor Buscemi Construction Inc; Lic. No.: 946326-B 1911 N GAFFEY STREET SUITE G      SAN PEDRO, CA 90731
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/26/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 5/5/2021 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 5/5/2021 Approved JOHN KLARIN
Green Building Rough 5/5/2021 Approved JOHN KLARIN
ELECTRICAL-Rough 6/11/2021 Off-Hour Fees Due
ELECTRICAL-Final 10/26/2022 Not Ready for Inspection ANSON MAGLASANG
Final 10/26/2022 Not Ready for Inspection ANSON MAGLASANG
Green Building Final 10/26/2022 Approved ANSON MAGLASANG
HVAC-Final 10/26/2022 Not Ready for Inspection ANSON MAGLASANG
PLUMBING-Final 10/26/2022 Not Ready for Inspection ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 10/26/2022 SGSOV Not Ready ANSON MAGLASANG
Service/Power Release 10/26/2022 Not Ready for Inspection ANSON MAGLASANG
Smoke Detectors 10/26/2022 Not Ready for Inspection ANSON MAGLASANG
Final 1/24/2024 Corrections Issued JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 1/24/2024 SGSOV Not Ready JAMES CHAVEZ
Service/Power Release 1/24/2024 Not Ready for Inspection JAMES CHAVEZ
Smoke Detectors 1/24/2024 Not Ready for Inspection JAMES CHAVEZ
Final 2/7/2024 Not Ready for Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 2/7/2024 SGSOV Approved JAMES CHAVEZ
Service/Power Release 2/7/2024 Not Ready for Inspection JAMES CHAVEZ
Smoke Detectors 2/7/2024 Not Ready for Inspection JAMES CHAVEZ
Final 2/12/2024 OK to Issue CofO EUGENE CASSIDY
Service/Power Release 2/12/2024 Approved EUGENE CASSIDY
Smoke Detectors 2/12/2024 Approved EUGENE CASSIDY