1122 W 18TH ST 90731
Certificate Information: 1122 W 18TH ST 90731
- Application / Permit
- 19010-40000-01346
- Plan Check / Job No.
- B19SP00519
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- (N) Detached two-car garage (20' x 20') at rear of property. All work per engineered design.
- Permit Issued
- Issued on 2/28/2020
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 2/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/3/2019 | CHRISTOPHER KOMANCHECK |
| Green Plans Picked Up | 5/10/2019 | APPLICANT |
| Corrections Issued | 5/15/2019 | MUKUL GUPTA |
| Quality Review Completed | 5/22/2019 | CHRISTOPHER KOMANCHECK |
| Building Plans Picked Up | 5/22/2019 | APPLICANT |
| Applicant returned to address corrections | 1/9/2020 | CHRISTOPHER KOMANCHECK |
| Plan Check Approved | 1/16/2020 | CHRISTOPHER KOMANCHECK |
| Issued | 2/28/2020 | LADBS |
| CofO in Progress | 2/13/2024 | EUGENE CASSIDY |
| Permit Finaled | 2/22/2024 | ANSON MAGLASANG |
| CofO Issued | 2/22/2024 | ANSON MAGLASANG |
| Permit Finaled | 2/22/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/15/2019 | MUKUL GUPTA |
| Construction near power lines | Cleared | 9/3/2019 | RIDWAN HARDY |
| Low Impact Development | Cleared | 11/26/2019 | ORVAL HERNANDEZ-MARCIAL |
| Green Code | Cleared | 12/27/2019 | RICHARD GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2020 | BANAFSHEH BARATI |
| Roof/Waste drainage to street | Cleared | 1/9/2020 | BANAFSHEH BARATI |
| Sewer availability | Cleared | 1/9/2020 | BANAFSHEH BARATI |
| Hydrant and Access approval | Cleared | 1/16/2020 | GILBERT URREA |
Contact Information
| Contractor | Buscemi Construction Inc; Lic. No.: 946326-B | 1911 N GAFFEY STREET SUITE G SAN PEDRO, CA 90731 |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/26/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 5/5/2021 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 5/5/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 6/11/2021 | Off-Hour Fees Due | |
| ELECTRICAL-Final | 10/26/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Final | 10/26/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Green Building Final | 10/26/2022 | Approved | ANSON MAGLASANG |
| HVAC-Final | 10/26/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| PLUMBING-Final | 10/26/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 10/26/2022 | SGSOV Not Ready | ANSON MAGLASANG |
| Service/Power Release | 10/26/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Smoke Detectors | 10/26/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Final | 1/24/2024 | Corrections Issued | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 1/24/2024 | SGSOV Not Ready | JAMES CHAVEZ |
| Service/Power Release | 1/24/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Smoke Detectors | 1/24/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 2/7/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 2/7/2024 | SGSOV Approved | JAMES CHAVEZ |
| Service/Power Release | 2/7/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Smoke Detectors | 2/7/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 2/12/2024 | OK to Issue CofO | EUGENE CASSIDY |
| Service/Power Release | 2/12/2024 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 2/12/2024 | Approved | EUGENE CASSIDY |