10511 W ILONA AVE 90064

Certificate Information: 10511 W ILONA AVE 90064

Application / Permit
19010-40000-00824
Plan Check / Job No.
B19SP00292
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2 story SFD with basement and attached garage.
Permit Issued
Issued on 9/4/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2019 APPLICANT
Assigned to Plan Check Engineer 3/14/2019 MANUEL GARCIA
Corrections Issued 3/18/2019 MANUEL GARCIA
Quality Review Completed 3/28/2019 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 3/28/2019 APPLICANT
Building Plans Picked Up 4/2/2019 APPLICANT
Applicant returned to address corrections 8/1/2019 MANUEL GARCIA
Plan Check Approved 8/30/2019 MANUEL GARCIA
Issued 9/4/2019 LADBS
CofO in Progress 7/15/2024 STEPHANIE SWANSON
Permit Finaled 7/16/2024 DANIEL ORRANTE
CofO Issued 7/16/2024 DANIEL ORRANTE
Permit Finaled 7/16/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/15/2019 CHRISTOPHER LAW
Eng Process Fee Ord 176,300 Cleared 4/15/2019 CHRISTOPHER LAW
Sewer availability Cleared 4/15/2019 CHRISTOPHER LAW
Hydrant and Access approval Cleared 7/16/2019 JEREMY CARTER
Low Impact Development Cleared 7/17/2019 SARAH YOUSSEF
Green Code Cleared 7/26/2019 RICHARD GARCIA
Excavation more than 5-ft deep Cleared 8/1/2019 CALOSHA APPROVED
GPI Written Notices Cleared 8/1/2019 MANUEL GARCIA
Grading Pre-Inspection Cleared 8/1/2019 MANUEL GARCIA

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Kook & Associates Construction Inc; Lic. No.: 820560-B 12444 VENTURA BLVD STE 105      STUDIO CITY, CA 91604
Engineer Namdar,, Mansour Tom; Lic. No.: S2976 16867 SEVERO PLACE      ENCINO, CA 91436

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 9/11/2019 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 9/12/2019 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 9/16/2019 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 9/19/2019 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 10/4/2019 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 1/8/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 1/14/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
METHANE-Barrier 1/14/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
METHANE-Subgrade 1/14/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 1/15/2020 Conditional Approval CARLOS MATAMOROS
Deputy Methane Barrier 1/30/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Methane Barrier 1/31/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Methane Barrier 2/3/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Methane Barrier 2/4/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Methane Barrier 2/5/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Shotcrete 2/11/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Shotcrete 2/26/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Shotcrete 3/2/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 3/3/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Shotcrete 3/4/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 3/17/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 3/17/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 3/19/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Methane Barrier 3/26/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Methane Barrier 3/27/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Masonry Wall/Backfill 3/27/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Methane Barrier 4/1/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Methane Barrier 4/2/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Methane Barrier 4/7/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Methane Barrier 4/15/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Methane Barrier 4/16/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Methane Barrier 4/17/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Methane Barrier 4/20/2020 Approved KEVIN SARGSYAN
METHANE-Subgrade 4/20/2020 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 4/24/2020 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Barrier 4/24/2020 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 4/28/2020 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 7/31/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 8/4/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 8/4/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 9/10/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 9/30/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Green Building Rough 9/30/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 9/30/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 9/30/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 11/17/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 1/12/2021 Not Ready for Inspection ANTHONY MCDOWALL
HVAC-Rough 1/12/2021 Not Ready for Inspection ANTHONY MCDOWALL
PLUMBING-Rough 1/12/2021 Not Ready for Inspection ANTHONY MCDOWALL
Rough-Elec/Plmb/HVAC 1/12/2021 Corrections Issued ANTHONY MCDOWALL
ELECTRICAL-Rough 1/20/2021 Not Ready for Inspection PIERRE VEGA
Floor/Roof Diaphrgm/Shear Wall 1/20/2021 Partial Approval PIERRE VEGA
HVAC-Rough 1/20/2021 Not Ready for Inspection PIERRE VEGA
PLUMBING-Rough 1/20/2021 Not Ready for Inspection PIERRE VEGA
ELECTRICAL-Rough 2/17/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 2/17/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 2/17/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Sewer 2/18/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 2/18/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 2/19/2021 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 2/19/2021 Approved GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 3/9/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 4/8/2021 Approved GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 4/8/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Green Building Rough 4/8/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 4/8/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 4/8/2021 Approved GERMAN RODRIGUEZ MENDOZA
Sewer 4/8/2021 Approved GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 4/8/2021 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 4/14/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 4/14/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 4/15/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 4/27/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Green Building Rough 4/27/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 4/27/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 5/28/2021 Approved GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 6/7/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 8/30/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Green Building Rough 8/30/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 8/30/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 8/30/2021 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Rough 9/24/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 9/24/2021 Approved GERMAN RODRIGUEZ MENDOZA
Shower Pan 10/14/2021 Not Ready for Inspection KENNETH NAGLE
Shower Pan 10/18/2021 Corrections Issued BRENDAN LOONEY
METHANE-Rough 11/24/2021 No Access for Inspection BRENDAN LOONEY
Shower Pan 11/24/2021 No Access for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 12/10/2021 Corrections Issued BRENDAN LOONEY
METHANE-Rough 12/10/2021 Corrections Issued BRENDAN LOONEY
Shower Pan 12/10/2021 Corrections Issued BRENDAN LOONEY
Green Building Rough 12/16/2021 Not Ready for Inspection BRENDAN LOONEY
Pre-Inspection 12/16/2021 Not Ready for Inspection BRENDAN LOONEY
Shower Pan 12/16/2021 Not Ready for Inspection BRENDAN LOONEY
Interior/Exterior Lathing 12/20/2021 Approved BRENDAN LOONEY
Shower Pan 12/20/2021 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 12/22/2021 Partial Approval BRENDAN LOONEY
Green Building Rough 12/22/2021 Approved BRENDAN LOONEY
Shower Pan 12/22/2021 Approved BRENDAN LOONEY
Deputy Steel/Welding 12/28/2021 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 1/7/2022 Conditional Approval BRENDAN LOONEY
METHANE-Rough 1/7/2022 Not Ready for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 1/18/2022 Corrections Issued OGANES TARAKHCHYAN
METHANE-Rough 1/18/2022 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 1/24/2022 Approved BRENDAN LOONEY
Insulation 3/1/2022 Corrections Issued OGANES TARAKHCHYAN
Drywall Nailing 3/7/2022 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 3/7/2022 Approved GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 6/23/2022 Partial Inspection BRENDAN LOONEY
Special/Order Compliance 6/27/2022 Partial Inspection MICHAEL PELHAM
Interior/Exterior Lathing 6/30/2022 Approved STEPHANIE SWANSON
Pre-Inspection 9/9/2022 Partial Inspection MICHAEL PELHAM
Gas Test 11/10/2022 Approved STEPHANIE SWANSON
ELECTRICAL-Final 12/2/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Final 12/2/2022 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 12/6/2022 Approved STEPHANIE SWANSON
Smoke Detectors 12/6/2022 Approved STEPHANIE SWANSON
Pre-Inspection 3/8/2023 Partial Inspection MICHAEL PELHAM
Service/Power Release 3/8/2023 Approved MICHAEL PELHAM
Underground Mechanical 4/26/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 6/29/2023 Corrections Issued STEPHANIE SWANSON
Special/Order Compliance 7/20/2023 Partial Inspection MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 7/31/2023 SGSOV Approved STEPHANIE SWANSON
HVAC-Final 9/18/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Final 9/18/2023 Partial Approval STEPHANIE SWANSON
HVAC-Final 9/25/2023 Partial Approval STEPHANIE SWANSON
Final 10/3/2023 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 10/3/2023 Approved STEPHANIE SWANSON
Green Building Final 10/3/2023 Approved STEPHANIE SWANSON
Final 5/29/2024 Not Ready for Inspection MICHAEL PELHAM
HVAC-Final 5/29/2024 Approved MICHAEL PELHAM
Final 7/5/2024 Not Ready for Inspection MICHAEL PELHAM
PLUMBING-Final 7/5/2024 Approved MICHAEL PELHAM
Final 7/15/2024 OK to Issue CofO STEPHANIE SWANSON