1324 S LELAND ST 90731

Certificate Information: 1324 S LELAND ST 90731

Application / Permit
19010-40000-00566
Plan Check / Job No.
B19SP00196
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2 story 640 SF detached accessory dwelling unit per AB494 and SB229.
Permit Issued
Issued on 9/17/2020
Issuing Office
Current Status
CofO Issued on 10/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2019 APPLICANT
Assigned to Plan Check Engineer 3/1/2019 JASON JANGADA
Corrections Issued 3/20/2019 JASON JANGADA
Green Plans Picked Up 3/21/2019 APPLICANT
Quality Review Completed 4/1/2019 CHRISTOPHER KOMANCHECK
Applicant returned to address corrections 9/10/2019 JASON JANGADA
Applicant returned to address corrections 10/9/2019 JASON JANGADA
Plan Check Approved 10/17/2019 JASON JANGADA
Issued 9/17/2020 APPLICANT
Building Plans Picked Up 9/21/2020 APPLICANT
CofO in Progress 9/21/2021 JOHN KLARIN
Permit Finaled 10/20/2021 DEROLD HAUFF
CofO Issued 10/20/2021 DEROLD HAUFF
Permit Finaled 10/20/2021 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 8/23/2019 JOHN CONNEALLY
Green Code Cleared 8/29/2019 RICHARD GARCIA
Address approval Cleared 9/10/2019 PHILLIP WILSON
Eng Process Fee Ord 176,300 Cleared 9/10/2019 PHILLIP WILSON
Roof/Waste drainage to street Cleared 9/10/2019 PHILLIP WILSON
GPI Written Notices Cleared 10/9/2019 JASON JANGADA
Grading Pre-Inspection Cleared 10/9/2019 JASON JANGADA
Sewer availability Cleared 10/9/2019 PHILLIP WILSON

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/16/2020 Approved JOHN KLARIN
Excavation/Setback/Form/Re-Bar 11/6/2020 Approved JOHN KLARIN
Footing/Foundation/Slab 11/6/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 12/1/2020 Partial Inspection JOHN KLARIN
PLUMBING-Rough 12/1/2020 Partial Inspection JOHN KLARIN
BUILDING-Rough-Frame 12/16/2020 Partial Inspection JOHN KLARIN
Green Building Rough 12/16/2020 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 12/16/2020 Partial Inspection JOHN KLARIN
Verify Sprinkler Sign Off 12/16/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 12/28/2020 Partial Approval JOHN KLARIN
Green Building Rough 12/28/2020 Not Ready for Inspection JOHN KLARIN
Sewer 1/12/2021 Approved JOHN KLARIN
ELECTRICAL-Rough 2/10/2021 Approved JOHN KLARIN
PLUMBING-Final 2/10/2021 Partial Approval JOHN KLARIN
Wood Frame 2/10/2021 Corrections Issued JOHN KLARIN
Wood Frame 2/25/2021 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 3/10/2021 Approved JOHN KLARIN
Insulation 3/10/2021 Approved JOHN KLARIN
Interior/Exterior Lathing 3/10/2021 Approved JOHN KLARIN
Drywall Nailing 3/25/2021 Conditional Approval JOHN KLARIN
HVAC-Rough 3/25/2021 Approved JOHN KLARIN
HVAC-Final 5/10/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 9/3/2021 Approved ANSON MAGLASANG
Drywall Nailing 9/3/2021 Approved ANSON MAGLASANG
ELECTRICAL-Final 9/3/2021 Approved ANSON MAGLASANG
Final 9/3/2021 Corrections Issued ANSON MAGLASANG
Green Building Final 9/3/2021 Approved ANSON MAGLASANG
Green Building Rough 9/3/2021 Approved ANSON MAGLASANG
HVAC-Final 9/3/2021 Approved ANSON MAGLASANG
PLUMBING-Final 9/3/2021 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 9/3/2021 SGSOV Approved ANSON MAGLASANG
Service/Power Release 9/3/2021 Corrections Issued ANSON MAGLASANG
Smoke Detectors 9/3/2021 Approved ANSON MAGLASANG
Final 9/20/2021 OK to Issue CofO JOHN KLARIN
Service/Power Release 9/20/2021 Approved JOHN KLARIN