1323-1323 1/2 N BATES AVE 90027
Certificate Information: 1323-1323 1/2 N BATES AVE 90027
- Application / Permit
- 19010-30000-06531
- Plan Check / Job No.
- B19WL07410
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 3-story duplex with attached 2-car garage at rear of lot. NFPA-13D fully sprinklered thru-out.
- Permit Issued
- Issued on 10/7/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2019 | APPLICANT |
| Green Plans Picked Up | 1/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | ALFREDO JARA |
| Corrections Issued | 2/3/2020 | ALFREDO JARA |
| Quality Review Completed | 2/14/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 6/15/2020 | ALFREDO JARA |
| No Progress | 6/29/2020 | ALFREDO JARA |
| Plan Check Approved | 9/2/2020 | ALFREDO JARA |
| Building Plans Picked Up | 9/3/2020 | APPLICANT |
| Issued | 10/7/2020 | APPLICANT |
| CofO in Progress | 5/25/2022 | JOSEPH MCGARRY |
| No Progress | 8/16/2022 | JULIAN AMAYA |
| CofO in Progress | 9/7/2022 | JULIAN AMAYA |
| Permit Finaled | 9/13/2022 | DEROLD HAUFF |
| Permit Finaled | 9/13/2022 | DEROLD HAUFF |
| CofO Issued | 9/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/25/2020 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2020 | JEANETTE VONG |
| Highway dedication | Cleared | 2/25/2020 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 2/25/2020 | GEORGE SUCHAND |
| Permit | Cleared | 2/25/2020 | JEANETTE VONG |
| Sewer availability | Cleared | 2/25/2020 | JEANETTE VONG |
| Green Code | Cleared | 3/5/2020 | DONALD CRICHLOW |
| Low Impact Development | Cleared | 3/10/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 3/12/2020 | ANTHONY MAINEZ |
| Trees in Parkway | Cleared | 4/14/2020 | JOHN KIM |
| GPI Written Notices | Cleared | 6/15/2020 | ALFREDO JARA |
| Grading Pre-Inspection | Cleared | 6/15/2020 | ALFREDO JARA |
Contact Information
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | 4 HILLCREST MANOR ROLLING HILLS ESTATES, CA 90274 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/2/2021 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 3/22/2021 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2021 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/28/2021 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/28/2021 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/29/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/29/2021 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 7/29/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 7/29/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/29/2021 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 7/29/2021 | Approved | JOSEPH MCGARRY |
| Insulation | 8/9/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/9/2021 | Partial Approval | JOSEPH MCGARRY |
| Drywall Nailing | 8/16/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/16/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Drywall Nailing | 8/20/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/20/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 9/1/2021 | Approved | JOSEPH MCGARRY |
| Shower Pan | 9/1/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 1/3/2022 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 1/3/2022 | SGSOV Approved | JOSEPH MCGARRY |
| Final | 1/4/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Final | 1/4/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Final | 1/4/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 1/4/2022 | SGSOV Approved | JOSEPH MCGARRY |
| Service/Power Release | 1/4/2022 | Not Required | JOSEPH MCGARRY |
| Smoke Detectors | 1/4/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Final | 3/7/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 3/7/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 3/7/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 3/7/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 3/7/2022 | Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 3/7/2022 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 3/14/2022 | Approved | JOSEPH MCGARRY |
| Final | 3/14/2022 | Corrections Issued | JOSEPH MCGARRY |
| HVAC-Final | 3/14/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 3/14/2022 | Approved | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 4/11/2022 | No Access for Inspection | CRAIG DAVIS |
| Final | 5/20/2022 | OK to Issue CofO | JOSEPH MCGARRY |
| Special/Order Compliance | 6/2/2022 | Corrections Issued | JOSEPH MCGARRY |