1323-1323 1/2 N BATES AVE 90027

Certificate Information: 1323-1323 1/2 N BATES AVE 90027

Application / Permit
19010-30000-06531
Plan Check / Job No.
B19WL07410
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 3-story duplex with attached 2-car garage at rear of lot. NFPA-13D fully sprinklered thru-out.
Permit Issued
Issued on 10/7/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2019 APPLICANT
Green Plans Picked Up 1/15/2020 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 ALFREDO JARA
Corrections Issued 2/3/2020 ALFREDO JARA
Quality Review Completed 2/14/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 6/15/2020 ALFREDO JARA
No Progress 6/29/2020 ALFREDO JARA
Plan Check Approved 9/2/2020 ALFREDO JARA
Building Plans Picked Up 9/3/2020 APPLICANT
Issued 10/7/2020 APPLICANT
CofO in Progress 5/25/2022 JOSEPH MCGARRY
No Progress 8/16/2022 JULIAN AMAYA
CofO in Progress 9/7/2022 JULIAN AMAYA
Permit Finaled 9/13/2022 DEROLD HAUFF
Permit Finaled 9/13/2022 DEROLD HAUFF
CofO Issued 9/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/25/2020 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 2/25/2020 JEANETTE VONG
Highway dedication Cleared 2/25/2020 JEANETTE VONG
Hydrant and Access approval Cleared 2/25/2020 GEORGE SUCHAND
Permit Cleared 2/25/2020 JEANETTE VONG
Sewer availability Cleared 2/25/2020 JEANETTE VONG
Green Code Cleared 3/5/2020 DONALD CRICHLOW
Low Impact Development Cleared 3/10/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 3/12/2020 ANTHONY MAINEZ
Trees in Parkway Cleared 4/14/2020 JOHN KIM
GPI Written Notices Cleared 6/15/2020 ALFREDO JARA
Grading Pre-Inspection Cleared 6/15/2020 ALFREDO JARA

Contact Information

Contractor Baksh Construction Inc; Lic. No.: 910533-B 4 HILLCREST MANOR      ROLLING HILLS ESTATES, CA 90274
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/2/2021 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 3/22/2021 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 4/21/2021 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 5/3/2021 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/25/2021 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/27/2021 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 7/28/2021 Corrections Issued JOSEPH MCGARRY
PLUMBING-Rough 7/28/2021 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 7/29/2021 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 7/29/2021 Approved JOSEPH MCGARRY
Green Building Rough 7/29/2021 Approved JOSEPH MCGARRY
HVAC-Rough 7/29/2021 Approved JOSEPH MCGARRY
PLUMBING-Rough 7/29/2021 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 7/29/2021 Approved JOSEPH MCGARRY
Insulation 8/9/2021 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 8/9/2021 Partial Approval JOSEPH MCGARRY
Drywall Nailing 8/16/2021 Not Ready for Inspection JOSEPH MCGARRY
Interior/Exterior Lathing 8/16/2021 Not Ready for Inspection JOSEPH MCGARRY
Drywall Nailing 8/20/2021 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 8/20/2021 Not Ready for Inspection JOSEPH MCGARRY
Interior/Exterior Lathing 9/1/2021 Approved JOSEPH MCGARRY
Shower Pan 9/1/2021 Approved JOSEPH MCGARRY
PLUMBING-Final 1/3/2022 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 1/3/2022 SGSOV Approved JOSEPH MCGARRY
Final 1/4/2022 Not Ready for Inspection JOSEPH MCGARRY
Green Building Final 1/4/2022 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Final 1/4/2022 Not Ready for Inspection JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 1/4/2022 SGSOV Approved JOSEPH MCGARRY
Service/Power Release 1/4/2022 Not Required JOSEPH MCGARRY
Smoke Detectors 1/4/2022 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Final 3/7/2022 Approved CHRIS CHRISTENSEN
Final 3/7/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 3/7/2022 Approved CHRIS CHRISTENSEN
HVAC-Final 3/7/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 3/7/2022 Approved CHRIS CHRISTENSEN
Smoke Detectors 3/7/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 3/14/2022 Approved JOSEPH MCGARRY
Final 3/14/2022 Corrections Issued JOSEPH MCGARRY
HVAC-Final 3/14/2022 Approved JOSEPH MCGARRY
PLUMBING-Final 3/14/2022 Approved JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 4/11/2022 No Access for Inspection CRAIG DAVIS
Final 5/20/2022 OK to Issue CofO JOSEPH MCGARRY
Special/Order Compliance 6/2/2022 Corrections Issued JOSEPH MCGARRY