1325 S THAYER AVE 90024

Certificate Information: 1325 S THAYER AVE 90024

Application / Permit
19010-30000-06514
Plan Check / Job No.
B19WL07399
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New single family dwelling with attached garage.
Permit Issued
Issued on 5/17/2022
Issuing Office
Current Status
CofO Issued on 2/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2019 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 KAMRAN GHOTBI RAVANDI
Corrections Issued 2/3/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 2/6/2020 APPLICANT
Quality Review Completed 2/11/2020 FELIX FIGUEROA
Applicant returned to address corrections 9/10/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/11/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 10/15/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/30/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 3/25/2021 KAMRAN GHOTBI RAVANDI
Issued 5/17/2022 APPLICANT
Building Plans Picked Up 5/18/2022 APPLICANT
CofO in Progress 2/20/2026 RYAN SALAZAR
Permit Finaled 2/26/2026 RICHARD STEINBACH
CofO Issued 2/26/2026 RICHARD STEINBACH
Permit Finaled 2/26/2026 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 5/13/2020 FREDDY GARCIA
Hydrant and Access approval Cleared 5/21/2020 KURT CORRAL
Trees in Parkway Cleared 5/27/2020 JOHN KIM
Permit Cleared 6/5/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 6/9/2020 DINAH GARIN
Sewer availability Cleared 6/9/2020 DINAH GARIN
Green Code Cleared 6/16/2020 RICHARD GARCIA
Low Impact Development Cleared 6/16/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 8/18/2020 DINAH GARIN
Excavation more than 5-ft deep Cleared 11/30/2020 CALOSHA APPROVED

Contact Information

Contractor Ponderosa Pines Gen Contractors; Lic. No.: 450947-B 9616 RIESHEL STREET      PICO RIVERA, CA 90660
Engineer Mani,, Dev; Lic. No.: C62778 P O BOX 1451      DUARTE, CA 91009
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/25/2023 Not Ready for Inspection JULIAN AMAYA
METHANE-Barrier 1/25/2023 Not Ready for Inspection JULIAN AMAYA
METHANE-Subgrade 1/25/2023 Not Ready for Inspection JULIAN AMAYA
Pre-Inspection 1/25/2023 Not Ready for Inspection JULIAN AMAYA
Pre-Inspection 4/8/2024 Corrections Issued CHRISTOPHER WILSON
Deputy Reinf. Concrete 8/15/2024 Conditional Approval KIRK SANDERS
Footing/Foundation/Slab 8/15/2024 Partial Approval KIRK SANDERS
METHANE-Barrier 8/15/2024 Not Ready for Inspection KIRK SANDERS
METHANE-Subgrade 8/15/2024 Not Ready for Inspection KIRK SANDERS
Footing/Foundation/Slab 8/27/2024 Partial Approval KIRK SANDERS
METHANE-Barrier 8/27/2024 Not Ready for Inspection KIRK SANDERS
METHANE-Subgrade 8/27/2024 Not Ready for Inspection KIRK SANDERS
Special/Order Compliance 8/27/2024 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 9/17/2024 Corrections Issued ASHLEY THOMPSON
METHANE-Barrier 9/17/2024 Not Ready for Inspection ASHLEY THOMPSON
METHANE-Subgrade 9/17/2024 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 9/24/2024 Partial Approval KIRK SANDERS
METHANE-Barrier 9/24/2024 Not Ready for Inspection KIRK SANDERS
METHANE-Rough 9/24/2024 Not Ready for Inspection KIRK SANDERS
METHANE-Subgrade 9/24/2024 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 10/3/2024 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 10/3/2024 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 10/24/2024 Partial Approval STEPHANIE SWANSON
METHANE-Barrier 10/24/2024 Not Ready for Inspection STEPHANIE SWANSON
Deputy Methane Barrier 11/15/2024 Conditional Approval KIRK SANDERS
METHANE-Final 12/3/2024 Not Ready for Inspection KIRK SANDERS
METHANE-Rough 12/3/2024 Not Ready for Inspection KIRK SANDERS
METHANE-Subgrade 12/3/2024 Approved KIRK SANDERS
Deputy Methane Barrier 12/5/2024 Conditional Approval KIRK SANDERS
METHANE-Barrier 12/6/2024 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 12/13/2024 Partial Approval KIRK SANDERS
PLUMBING-Rough 12/13/2024 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 12/31/2024 Conditional Approval KIRK SANDERS
Structural Steel Frame 12/31/2024 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 1/9/2025 Partial Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 1/15/2025 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/15/2025 Conditional Approval KIRK SANDERS
METHANE-Subgrade 1/15/2025 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/17/2025 Partial Approval KIRK SANDERS
METHANE-Barrier 1/17/2025 Approved KIRK SANDERS
Structural Steel Frame 1/17/2025 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 1/22/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/24/2025 Corrections Issued KIRK SANDERS
Special/Order Compliance 1/24/2025 Corrections Issued KIRK SANDERS
Structural Steel Frame 1/24/2025 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/28/2025 Partial Approval KIRK SANDERS
PLUMBING-Rough 1/31/2025 Not Ready for Inspection KIRK SANDERS
METHANE-Subgrade 2/4/2025 Conditional Approval KIRK SANDERS
Deputy Wood Construction 2/19/2025 Conditional Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/21/2025 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Conditional Approval KIRK SANDERS
METHANE-Rough 3/11/2025 Approved DANIEL VERA
ELECTRICAL-Rough 3/19/2025 Partial Approval DANIEL VERA
Gas Test 3/19/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Rough 3/19/2025 Corrections Issued DANIEL VERA
BUILDING-Rough-Frame 3/21/2025 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/21/2025 Partial Approval KIRK SANDERS
Gas Test 3/21/2025 Partial Approval KIRK SANDERS
PLUMBING-Rough 3/21/2025 Partial Approval KIRK SANDERS
Gas Test 3/25/2025 Partial Approval KIRK SANDERS
PLUMBING-Rough 3/25/2025 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 3/27/2025 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 3/27/2025 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/27/2025 Not Ready for Inspection KIRK SANDERS
Green Building Rough 3/27/2025 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 3/27/2025 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 3/27/2025 Not Ready for Inspection KIRK SANDERS
Rough-Elec/Plmb/HVAC 3/27/2025 Not Ready for Inspection KIRK SANDERS
Verify Sprinkler Sign Off 3/27/2025 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 4/1/2025 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 4/1/2025 Not Ready for Inspection SEAN HAUPT
Deck 4/3/2025 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 4/3/2025 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 4/3/2025 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Partial Approval KIRK SANDERS
PLUMBING-Rough 4/8/2025 Partial Approval KIRK SANDERS
Special/Order Compliance 4/8/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 4/10/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 4/14/2025 Approved KIRK SANDERS
PLUMBING-Rough 4/14/2025 Approved KIRK SANDERS
Special/Order Compliance 4/14/2025 Corrections Issued KIRK SANDERS
Shower Pan 4/23/2025 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 4/24/2025 Partial Approval KIRK SANDERS
HVAC-Rough 4/24/2025 Not Ready for Inspection KIRK SANDERS
Shower Pan 4/24/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 4/25/2025 Partial Approval KIRK SANDERS
HVAC-Rough 4/30/2025 Conditional Approval KIRK SANDERS
Interior/Exterior Lathing 4/30/2025 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 5/1/2025 Approved KIRK SANDERS
Green Building Rough 5/1/2025 Approved KIRK SANDERS
Verify Sprinkler Sign Off 5/1/2025 Approved KIRK SANDERS
Insulation 5/6/2025 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 5/6/2025 Not Ready for Inspection STEPHANIE SWANSON
Interior/Exterior Lathing 5/9/2025 Partial Approval KIRK SANDERS
Special/Order Compliance 5/13/2025 Corrections Issued KIRK SANDERS
Drywall Nailing 5/16/2025 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 7/11/2025 No Access for Inspection KIRK SANDERS
Interior/Exterior Lathing 7/17/2025 Partial Approval JAYLIN GRAVITTE
Sewer 7/21/2025 Approved ARAM AVEDISIAN
Deputy Reinf. Concrete 8/27/2025 Conditional Approval ARAM AVEDISIAN
Gas Test 8/27/2025 Not Ready for Inspection JAYLIN GRAVITTE
PLUMBING-Rough 8/27/2025 Not Ready for Inspection JAYLIN GRAVITTE
ELECTRICAL-Rough 9/23/2025 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 9/30/2025 Approved ARAM AVEDISIAN
Service/Power Release 9/30/2025 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Final 10/15/2025 Not Ready for Inspection MICHAEL ALLEN
PLUMBING-Final 10/15/2025 Not Ready for Inspection MICHAEL ALLEN
PLUMBING-Final 10/17/2025 Approved MICHAEL ALLEN
PLUMBING-Final 10/21/2025 Approved MICHAEL ALLEN
HVAC-Final 11/10/2025 Corrections Issued MICHAEL ALLEN
PLUMBING-Final 11/10/2025 Approved MICHAEL ALLEN
Service/Power Release 11/19/2025 Approved MICHAEL ALLEN
Green Building Final 12/1/2025 Not Ready for Inspection MICHAEL ALLEN
Reinforced Concrete Frame 12/1/2025 Not Ready for Inspection MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 12/1/2025 SGSOV Not Ready MICHAEL ALLEN
Smoke Detectors 12/1/2025 Not Ready for Inspection MICHAEL ALLEN
Gas Test 12/4/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 12/4/2025 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 12/4/2025 Approved MICHAEL ALLEN
Final 2/13/2026 Partial Approval RYAN SALAZAR
Green Building Final 2/13/2026 Approved RYAN SALAZAR
Reinforced Concrete Frame 2/13/2026 Approved RYAN SALAZAR
Final 2/19/2026 OK to Issue CofO RYAN SALAZAR