13206 W DEWEY ST 90066

Certificate Information: 13206 W DEWEY ST 90066

Application / Permit
19010-30000-06491
Plan Check / Job No.
B19WL07386
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(n) 2-story SFD with attached garage.
Permit Issued
Issued on 3/11/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2019 APPLICANT
Green Plans Picked Up 1/15/2020 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 KAVIAN REFAHI
Corrections Issued 2/3/2020 KAVIAN REFAHI
Quality Review Completed 2/13/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 2/20/2020 APPLICANT
Plan Check Approved 3/11/2020 KAVIAN REFAHI
Issued 3/11/2020 LADBS
CofO in Progress 7/30/2021 ENRIQUE MIRELES
CofO Issued 9/7/2021 RONALD MYRICK
Permit Finaled 9/7/2021 RONALD MYRICK

Permit Application Clearance Information

GPI Written Notices Cleared 2/1/2020 KAVIAN REFAHI
Grading Pre-Inspection Cleared 2/1/2020 KAVIAN REFAHI
Low Impact Development Cleared 2/24/2020 MARTIN FRAGOSO
Address approval Cleared 2/25/2020 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 2/25/2020 DENNIS BRAGIN
Hydrant and Access approval Cleared 2/25/2020 DOMINIQUE MEDINA
Permit Cleared 2/25/2020 DENNIS BRAGIN
Roof/Waste drainage to street Cleared 2/25/2020 DENNIS BRAGIN
Sewer availability Cleared 2/25/2020 DENNIS BRAGIN
Green Code Cleared 2/27/2020 DONALD CRICHLOW
Trees in Parkway Cleared 3/10/2020 JOHN KIM

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Haddad,, Raymond Mounir; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/15/2020 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 9/18/2020 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 10/13/2020 Partial Approval JOHNNY MIRANDA
Underground Mechanical 10/13/2020 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 10/22/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 11/9/2020 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 12/17/2020 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 12/21/2020 No Access for Inspection ENRIQUE MIRELES
PLUMBING-Rough 12/23/2020 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 12/24/2020 No Access for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/31/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 1/6/2021 Corrections Issued ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 1/20/2021 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 1/25/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 2/2/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 2/2/2021 Not Ready for Inspection ENRIQUE MIRELES
Green Building Final 2/3/2021 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 2/3/2021 Approved ENRIQUE MIRELES
HVAC-Final 2/3/2021 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 2/3/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 3/17/2021 Approved DAVID HEINE
Interior/Exterior Lathing 3/17/2021 Partial Approval DAVID HEINE
Verify Sprinkler Sign Off 3/17/2021 Approved DAVID HEINE
Drywall Nailing 4/5/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 6/16/2021 Approved ENRIQUE MIRELES
HVAC-Final 6/30/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 6/30/2021 Not Ready for Inspection ENRIQUE MIRELES
Final 7/16/2021 No Access for Inspection ENRIQUE MIRELES
Green Building Final 7/16/2021 No Access for Inspection ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 7/16/2021 SGSOV Not Ready ENRIQUE MIRELES
Service/Power Release 7/16/2021 No Access for Inspection ENRIQUE MIRELES
Smoke Detectors 7/16/2021 No Access for Inspection ENRIQUE MIRELES
Final 7/30/2021 OK to Issue CofO ENRIQUE MIRELES
Green Building Final 7/30/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 7/30/2021 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 7/30/2021 Approved ENRIQUE MIRELES
Smoke Detectors 7/30/2021 Approved ENRIQUE MIRELES