10033 W ROSSBURY PL 90064

Certificate Information: 10033 W ROSSBURY PL 90064

Application / Permit
19010-30000-06360
Plan Check / Job No.
B19WL07344
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-story SFD with basement & attached garage.
Permit Issued
Issued on 3/4/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 VLADIMIR ARUTYUNYAN
Green Plans Picked Up 1/23/2020 APPLICANT
Corrections Issued 1/27/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 2/7/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 3/4/2020 VLADIMIR ARUTYUNYAN
Issued 3/4/2020 LADBS
Building Plans Picked Up 7/8/2021 APPLICANT
CofO in Progress 5/2/2024 OGANES TARAKHCHYAN
Permit Finaled 5/4/2024 DANIEL ORRANTE
Permit Finaled 5/4/2024 DANIEL ORRANTE
CofO Issued 5/4/2024 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 2/24/2020 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 2/25/2020 DENNIS BRAGIN
Green Code Cleared 2/25/2020 RICHARD GARCIA
Hydrant and Access approval Cleared 2/25/2020 DOMINIQUE MEDINA
Permit Cleared 2/25/2020 DENNIS BRAGIN
Roof/Waste drainage to street Cleared 2/25/2020 DENNIS BRAGIN
GPI Written Notices Cleared 3/4/2020 VLADIMIR ARUTYUNYAN
Grading Pre-Inspection Cleared 3/4/2020 VLADIMIR ARUTYUNYAN

Contact Information

Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Haddad,, Raymond Mounir; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/21/2020 Partial Inspection KENNETH NAGLE
Underground Mechanical 7/28/2020 Approved KEVIN SARGSYAN
PLUMBING-Rough 10/30/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 11/9/2020 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 11/19/2020 Corrections Issued KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 11/20/2020 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 11/23/2020 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 12/11/2020 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 1/15/2021 Partial Approval EVAN COOPER
Deputy Reinf. Concrete 1/19/2021 No Result Entered RONALD WEBER
Excavation/Setback/Form/Re-Bar 2/9/2021 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 2/11/2021 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 4/9/2021 Partial Approval KEVIN SARGSYAN
Sewer 4/28/2021 Approved KEVIN SARGSYAN
Special/Order Compliance 5/5/2021 Not Ready for Inspection KEVIN SARGSYAN
Deputy Drilled-In Anchors 5/21/2021 No Result Entered RONALD WEBER
Deputy Steel/Welding 5/21/2021 No Result Entered RONALD WEBER
Floor/Roof Diaphrgm/Shear Wall 5/24/2021 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/6/2021 Conditional Approval KEVIN SARGSYAN
Deputy Wood Construction 7/8/2021 Conditional Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 8/10/2021 Not Ready for Inspection EVAN COOPER
Excavation/Setback/Form/Re-Bar 8/24/2021 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 8/24/2021 Not Ready for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 8/25/2021 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 8/25/2021 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 10/22/2021 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 10/26/2021 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/19/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 4/7/2022 Approved KEVIN SARGSYAN
Shower Pan 6/1/2022 Approved KEVIN SARGSYAN
PLUMBING-Rough 6/8/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 6/14/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Final 7/20/2022 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Rough 7/20/2022 Approved OGANES TARAKHCHYAN
HVAC-Rough 7/25/2022 Corrections Issued JOHN KIDWELL
BUILDING-Rough-Frame 8/2/2022 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 8/2/2022 Approved OGANES TARAKHCHYAN
Green Building Rough 8/4/2022 Approved CLAYTON GRAHAM
Insulation 8/16/2022 Corrections Issued OGANES TARAKHCHYAN
Insulation 8/18/2022 Approved JOHN KIDWELL
Drywall Nailing 8/23/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Drywall Nailing 8/29/2022 Approved OGANES TARAKHCHYAN
Drywall Nailing 8/30/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/15/2022 Partial Approval JOHNNY MIRANDA
Interior/Exterior Lathing 9/19/2022 Partial Approval JOHN KIDWELL
ELECTRICAL-Final 7/11/2023 Corrections Issued CLAYTON GRAHAM
Gas Test 9/13/2023 Approved CLAYTON GRAHAM
PLUMBING-Final 9/13/2023 Corrections Issued CLAYTON GRAHAM
ELECTRICAL-Final 9/20/2023 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Final 10/5/2023 Approved CLAYTON GRAHAM
PLUMBING-Final 10/5/2023 Approved CLAYTON GRAHAM
HVAC-Final 10/17/2023 Corrections Issued MEL KHACHATOURIAN
HVAC-Final 11/8/2023 Corrections Issued OGANES TARAKHCHYAN
HVAC-Final 11/13/2023 Approved OGANES TARAKHCHYAN
Green Building Final 3/11/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/11/2024 SGSOV Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 3/11/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/24/2024 Approved OGANES TARAKHCHYAN
Final 4/24/2024 Corrections Issued OGANES TARAKHCHYAN
Smoke Detectors 4/24/2024 Approved OGANES TARAKHCHYAN
Final 4/26/2024 Corrections Issued OGANES TARAKHCHYAN
Service/Power Release 4/26/2024 Approved OGANES TARAKHCHYAN
Final 4/30/2024 OK to Issue CofO OGANES TARAKHCHYAN
Pre-Inspection 4/30/2024 Approved OGANES TARAKHCHYAN