12212 W OCTAGON ST 90049
Certificate Information: 12212 W OCTAGON ST 90049
- Application / Permit
- 19010-30000-06358
- Plan Check / Job No.
- B19WL07339
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-story Single family dwelling with attached garage. Equipped with fire sprinkler system NFPA-13D.
- Permit Issued
- Issued on 6/24/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2020 | ALFREDO JARA |
| Corrections Issued | 1/27/2020 | ALFREDO JARA |
| Quality Review Completed | 2/7/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 5/12/2020 | APPLICANT |
| Plan Check Approved | 6/10/2020 | ALFREDO JARA |
| Issued | 6/24/2020 | LADBS |
| Building Plans Picked Up | 6/24/2020 | APPLICANT |
| CofO in Progress | 9/13/2021 | CARLOS MATAMOROS |
| Permit Finaled | 9/21/2021 | RONALD MYRICK |
| CofO Issued | 9/21/2021 | RONALD MYRICK |
| Permit Finaled | 9/21/2021 | RONALD MYRICK |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/26/2020 | OSCAR GUTIERREZ |
| BHO/Hillside ordinance | Cleared | 2/26/2020 | OSCAR GUTIERREZ |
| BHO/Hillside ordinance | Cleared | 2/26/2020 | OSCAR GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2020 | EMIL KYUPELYAN |
| Permit | Cleared | 2/26/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 2/26/2020 | EMIL KYUPELYAN |
| Green Code | Cleared | 5/6/2020 | RICHARD GARCIA |
| Hydrant and Access approval | Cleared | 5/22/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 5/22/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 5/26/2020 | HISASHI KOBAYAKAWA |
| GPI Written Notices | Cleared | 6/9/2020 | ALFREDO JARA |
| Grading Pre-Inspection | Cleared | 6/9/2020 | ALFREDO JARA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vidal,, Juan Alonso; Lic. No.: GE861 | 7438 SHIRLEY AVE RESEDA, CA 91335 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/14/2020 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 8/14/2020 | Approved | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 8/17/2020 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 8/27/2020 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 9/2/2020 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2020 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2020 | Approved | CARLOS MATAMOROS |
| Gas Test | 10/21/2020 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 10/21/2020 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 1/27/2021 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2021 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 1/27/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 1/27/2021 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 1/27/2021 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 2/18/2021 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 2/18/2021 | Approved | CARLOS MATAMOROS |
| Shower Pan | 2/18/2021 | Approved | CARLOS MATAMOROS |
| Insulation | 2/23/2021 | Partial Approval | CARLOS MATAMOROS |
| Insulation | 2/24/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 2/24/2021 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 3/8/2021 | Approved | ANTHONY MCDOWALL |
| ELECTRICAL-Final | 8/4/2021 | Corrections Issued | CARLOS MATAMOROS |
| Gas Test | 8/4/2021 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 8/4/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 8/4/2021 | Corrections Issued | CARLOS MATAMOROS |
| Service/Power Release | 8/4/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Rec and Parks Fee Memo | 8/4/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Service/Power Release | 8/6/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 8/10/2021 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 8/10/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 8/10/2021 | Approved | CARLOS MATAMOROS |
| Final | 9/1/2021 | Conditional Approval | CARLOS MATAMOROS |
| Green Building Final | 9/1/2021 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 9/1/2021 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 9/1/2021 | Approved | CARLOS MATAMOROS |