869 N TOYOPA DR 90272

Certificate Information: 869 N TOYOPA DR 90272

Application / Permit
19010-30000-06306
Plan Check / Job No.
B19WL07313
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story SFD w/ attached garage and basement.
Permit Issued
Issued on 3/26/2021
Issuing Office
Current Status
CofO Issued on 5/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2019 APPLICANT
Assigned to Plan Check Engineer 2/3/2020 MANUEL GARCIA
Plans on Hold 2/3/2020 KAMRAN GHOTBI RAVANDI
Hold Released 5/18/2020 KAMRAN GHOTBI RAVANDI
Corrections Issued 6/12/2020 MANUEL GARCIA
Quality Review Completed 6/19/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 6/23/2020 APPLICANT
Applicant returned to address corrections 8/28/2020 MANUEL GARCIA
Applicant returned to address corrections 9/1/2020 MANUEL GARCIA
Applicant returned to address corrections 11/15/2020 MANUEL GARCIA
Applicant returned to address corrections 1/13/2021 MANUEL GARCIA
Applicant returned to address corrections 3/3/2021 MANUEL GARCIA
Building Plans Picked Up 3/3/2021 APPLICANT
Applicant returned to address corrections 3/12/2021 MANUEL GARCIA
Plan Check Approved 3/19/2021 MANUEL GARCIA
Issued 3/26/2021 APPLICANT
CofO in Progress 5/22/2023 GERMAN RODRIGUEZ MENDOZA
Permit Finaled 5/24/2023 DANIEL ORRANTE
CofO Issued 5/24/2023 DANIEL ORRANTE
Permit Finaled 5/24/2023 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 12/22/2020 ROBERT DUFF
Address approval Cleared 1/6/2021 DINAH GARIN
Low Impact Development Cleared 1/6/2021 MARTIN FRAGOSO
Permit Cleared 1/6/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 1/6/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/11/2021 DINAH GARIN
Sewer availability Cleared 1/11/2021 DINAH GARIN
Excavation more than 5-ft deep Cleared 3/3/2021 CALOSHA APPROVED
GPI Written Notices Cleared 3/18/2021 MANUEL GARCIA
Grading Pre-Inspection Cleared 3/18/2021 MANUEL GARCIA
Green Code Cleared 3/18/2021 DONALD CRICHLOW

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/6/2021 Corrections Issued ANDREW NAVE
Grounding or Bonding 5/6/2021 Partial Inspection ANDREW NAVE
Excavation/Setback/Form/Re-Bar 5/7/2021 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 5/10/2021 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 5/24/2021 Partial Approval ANDREW NAVE
Reinforced Concrete Frame 5/24/2021 Partial Approval ANDREW NAVE
Deputy Shotcrete 5/25/2021 Partial Approval ANDREW NAVE
Deputy Shotcrete 5/26/2021 Conditional Approval ANDREW NAVE
PLUMBING-Rough 6/7/2021 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 6/29/2021 Partial Approval ANDREW NAVE
Deputy Steel/Welding 8/6/2021 Partial Approval ANDREW NAVE
Deputy Wood Construction 8/16/2021 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 8/16/2021 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 9/1/2021 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 11/2/2021 Corrections Issued ANDREW NAVE
Deputy Wood Construction 11/8/2021 Conditional Approval ANDREW NAVE
PLUMBING-Rough 12/17/2021 Approved ANDREW NAVE
HVAC-Rough 1/10/2022 Corrections Issued ANDREW NAVE
Shower Pan 1/10/2022 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 1/20/2022 Partial Approval ANDREW NAVE
ELECTRICAL-Rough 2/2/2022 Corrections Issued ANDREW NAVE
HVAC-Rough 2/2/2022 Approved ANDREW NAVE
BUILDING-Rough-Frame 2/14/2022 Not Ready for Inspection ANDREW NAVE
ELECTRICAL-Rough 2/14/2022 Approved ANDREW NAVE
Green Building Rough 2/14/2022 Not Ready for Inspection ANDREW NAVE
Verify Sprinkler Sign Off 2/14/2022 Approved ANDREW NAVE
Interior/Exterior Lathing 3/17/2022 Partial Approval ANDREW NAVE
BUILDING-Rough-Frame 3/22/2022 Conditional Approval ANDREW NAVE
Green Building Rough 3/22/2022 Approved ANDREW NAVE
Interior/Exterior Lathing 3/22/2022 Not Ready for Inspection ANDREW NAVE
Interior/Exterior Lathing 4/1/2022 Partial Approval KRISTEN CAUSEY
Insulation 4/25/2022 Approved JOHN KIDWELL
Drywall Nailing 5/9/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 5/16/2022 Approved RYAN SALAZAR
Gas Test 7/8/2022 Approved HERBERT GIRON
Sewer 7/8/2022 Approved HERBERT GIRON
Special/Order Compliance 10/11/2022 No Access for Inspection KENNETH NAGLE
Service/Power Release 2/7/2023 Not Ready for Inspection BRENDAN LOONEY
Underground Mechanical 2/7/2023 Partial Approval BRENDAN LOONEY
ELECTRICAL-Final 2/24/2023 Not Ready for Inspection KENNETH NAGLE
Service/Power Release 2/24/2023 Approved KENNETH NAGLE
PLUMBING-Final 3/21/2023 Corrections Issued BRENDAN LOONEY
HVAC-Final 3/29/2023 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Final 3/29/2023 Approved BRENDAN LOONEY
ELECTRICAL-Final 3/30/2023 Not Ready for Inspection KENNETH NAGLE
BUILDING-Rough-Frame 3/31/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Final 3/31/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 3/31/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 3/31/2023 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/31/2023 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 3/31/2023 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 4/19/2023 Approved BRENDAN LOONEY
HVAC-Final 4/19/2023 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 4/21/2023 Approved BRENDAN LOONEY
Final 4/21/2023 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 4/21/2023 Approved BRENDAN LOONEY
Green Building Final 4/21/2023 Approved BRENDAN LOONEY
Smoke Detectors 4/21/2023 Approved BRENDAN LOONEY
Final 5/18/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA