869 N TOYOPA DR 90272
Certificate Information: 869 N TOYOPA DR 90272
- Application / Permit
- 19010-30000-06306
- Plan Check / Job No.
- B19WL07313
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story SFD w/ attached garage and basement.
- Permit Issued
- Issued on 3/26/2021
- Issuing Office
- Current Status
- CofO Issued on 5/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2020 | MANUEL GARCIA |
| Plans on Hold | 2/3/2020 | KAMRAN GHOTBI RAVANDI |
| Hold Released | 5/18/2020 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 6/12/2020 | MANUEL GARCIA |
| Quality Review Completed | 6/19/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 6/23/2020 | APPLICANT |
| Applicant returned to address corrections | 8/28/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 9/1/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 11/15/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 1/13/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 3/3/2021 | MANUEL GARCIA |
| Building Plans Picked Up | 3/3/2021 | APPLICANT |
| Applicant returned to address corrections | 3/12/2021 | MANUEL GARCIA |
| Plan Check Approved | 3/19/2021 | MANUEL GARCIA |
| Issued | 3/26/2021 | APPLICANT |
| CofO in Progress | 5/22/2023 | GERMAN RODRIGUEZ MENDOZA |
| Permit Finaled | 5/24/2023 | DANIEL ORRANTE |
| CofO Issued | 5/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 12/22/2020 | ROBERT DUFF |
| Address approval | Cleared | 1/6/2021 | DINAH GARIN |
| Low Impact Development | Cleared | 1/6/2021 | MARTIN FRAGOSO |
| Permit | Cleared | 1/6/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 1/6/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2021 | DINAH GARIN |
| Sewer availability | Cleared | 1/11/2021 | DINAH GARIN |
| Excavation more than 5-ft deep | Cleared | 3/3/2021 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 3/18/2021 | MANUEL GARCIA |
| Grading Pre-Inspection | Cleared | 3/18/2021 | MANUEL GARCIA |
| Green Code | Cleared | 3/18/2021 | DONALD CRICHLOW |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/6/2021 | Corrections Issued | ANDREW NAVE |
| Grounding or Bonding | 5/6/2021 | Partial Inspection | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 5/7/2021 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 5/10/2021 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 5/24/2021 | Partial Approval | ANDREW NAVE |
| Reinforced Concrete Frame | 5/24/2021 | Partial Approval | ANDREW NAVE |
| Deputy Shotcrete | 5/25/2021 | Partial Approval | ANDREW NAVE |
| Deputy Shotcrete | 5/26/2021 | Conditional Approval | ANDREW NAVE |
| PLUMBING-Rough | 6/7/2021 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 6/29/2021 | Partial Approval | ANDREW NAVE |
| Deputy Steel/Welding | 8/6/2021 | Partial Approval | ANDREW NAVE |
| Deputy Wood Construction | 8/16/2021 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2021 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2021 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2021 | Corrections Issued | ANDREW NAVE |
| Deputy Wood Construction | 11/8/2021 | Conditional Approval | ANDREW NAVE |
| PLUMBING-Rough | 12/17/2021 | Approved | ANDREW NAVE |
| HVAC-Rough | 1/10/2022 | Corrections Issued | ANDREW NAVE |
| Shower Pan | 1/10/2022 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2022 | Partial Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 2/2/2022 | Corrections Issued | ANDREW NAVE |
| HVAC-Rough | 2/2/2022 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 2/14/2022 | Not Ready for Inspection | ANDREW NAVE |
| ELECTRICAL-Rough | 2/14/2022 | Approved | ANDREW NAVE |
| Green Building Rough | 2/14/2022 | Not Ready for Inspection | ANDREW NAVE |
| Verify Sprinkler Sign Off | 2/14/2022 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 3/17/2022 | Partial Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 3/22/2022 | Conditional Approval | ANDREW NAVE |
| Green Building Rough | 3/22/2022 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 3/22/2022 | Not Ready for Inspection | ANDREW NAVE |
| Interior/Exterior Lathing | 4/1/2022 | Partial Approval | KRISTEN CAUSEY |
| Insulation | 4/25/2022 | Approved | JOHN KIDWELL |
| Drywall Nailing | 5/9/2022 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 5/16/2022 | Approved | RYAN SALAZAR |
| Gas Test | 7/8/2022 | Approved | HERBERT GIRON |
| Sewer | 7/8/2022 | Approved | HERBERT GIRON |
| Special/Order Compliance | 10/11/2022 | No Access for Inspection | KENNETH NAGLE |
| Service/Power Release | 2/7/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Underground Mechanical | 2/7/2023 | Partial Approval | BRENDAN LOONEY |
| ELECTRICAL-Final | 2/24/2023 | Not Ready for Inspection | KENNETH NAGLE |
| Service/Power Release | 2/24/2023 | Approved | KENNETH NAGLE |
| PLUMBING-Final | 3/21/2023 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Final | 3/29/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Final | 3/29/2023 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 3/30/2023 | Not Ready for Inspection | KENNETH NAGLE |
| BUILDING-Rough-Frame | 3/31/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 3/31/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 3/31/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 3/31/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 3/31/2023 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 3/31/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 4/19/2023 | Approved | BRENDAN LOONEY |
| HVAC-Final | 4/19/2023 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 4/21/2023 | Approved | BRENDAN LOONEY |
| Final | 4/21/2023 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 4/21/2023 | Approved | BRENDAN LOONEY |
| Green Building Final | 4/21/2023 | Approved | BRENDAN LOONEY |
| Smoke Detectors | 4/21/2023 | Approved | BRENDAN LOONEY |
| Final | 5/18/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |