740 S WARNER AVE 90024

Certificate Information: 740 S WARNER AVE 90024

Application / Permit
19010-30000-06156
Plan Check / Job No.
B19WL07281
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
(N) RECREATION ROOM
Permit Issued
Issued on 11/24/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2019 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 KAVIAN REFAHI
Corrections Issued 1/27/2020 KAVIAN REFAHI
Quality Review Completed 2/7/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 4/6/2020 KAVIAN REFAHI
Applicant returned to address corrections 6/9/2020 KAVIAN REFAHI
Green Plans Picked Up 8/21/2020 APPLICANT
Plan Check Approved 9/23/2020 KAVIAN REFAHI
Issued 11/24/2020 APPLICANT
Building Plans Picked Up 11/24/2020 APPLICANT
CofO in Progress 5/26/2026 RYAN SALAZAR
Permit Finaled 5/27/2026 RICHARD STEINBACH
CofO Issued 5/27/2026 RICHARD STEINBACH
Permit Finaled 5/27/2026 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/12/2020 ANTHONY MAINEZ
CPC Cleared 2/13/2020 SARAH GOLDMAN
ZA Case Cleared 2/13/2020 SARAH GOLDMAN
Hydrant and Access approval Cleared 2/14/2020 JOHN CONNEALLY
Low Impact Development Cleared 6/30/2020 ANDRES COVARRUBIAS
Green Code Cleared 8/21/2020 RICHARD GARCIA
Miscellaneous Cleared 8/25/2020 NIKTA MOUSAVI
Roof/Waste drainage to street Cleared 8/28/2020 NIKTA MOUSAVI
GPI Written Notices Cleared 9/23/2020 KAVIAN REFAHI
Grading Pre-Inspection Cleared 9/23/2020 KAVIAN REFAHI

Contact Information

Contractor Pillar Building Group Llc; Lic. No.: 1017041-B 8109 ORION AVE      VAN NUYS, CA 91406

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/5/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 8/5/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
METHANE-Barrier 8/5/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Subgrade 8/5/2021 Approved GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 8/18/2021 Not Ready for Inspection DANIEL ORRANTE
Footing/Foundation/Slab 8/18/2021 Not Ready for Inspection DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 3/9/2022 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/29/2022 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 3/31/2022 Approved BRENDAN LOONEY
Footing/Foundation/Slab 3/31/2022 Approved BRENDAN LOONEY
Interior/Exterior Lathing 4/12/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 6/10/2022 Approved JOHN KIDWELL
PLUMBING-Rough 6/10/2022 Approved JOHN KIDWELL
HVAC-Final 2/13/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 2/13/2023 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 3/1/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 3/1/2023 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 4/30/2026 Partial Approval RYAN SALAZAR
Final 4/30/2026 Corrections Issued RYAN SALAZAR
Green Building Final 4/30/2026 Approved RYAN SALAZAR
Green Building Rough 4/30/2026 Approved RYAN SALAZAR
METHANE-Final 4/30/2026 Approved RYAN SALAZAR
METHANE-Rough 4/30/2026 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 4/30/2026 SGSOV Approved RYAN SALAZAR
Service/Power Release 4/30/2026 Approved RYAN SALAZAR
Smoke Detectors 4/30/2026 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 4/30/2026 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 5/22/2026 Approved RYAN SALAZAR
Final 5/22/2026 OK to Issue CofO RYAN SALAZAR
Verify Sprinkler Sign Off 5/22/2026 Approved RYAN SALAZAR