740 S WARNER AVE 90024

Certificate Information: 740 S WARNER AVE 90024

Application / Permit
19010-30000-06155
Plan Check / Job No.
B19WL07281
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) SFD 2-STORY WITH BASEMENT AND ATTACHED GARAGE (METHANE BUFFER ZONE)
Permit Issued
Issued on 11/24/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2019 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 KAVIAN REFAHI
Corrections Issued 1/27/2020 KAVIAN REFAHI
Quality Review Completed 2/7/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 4/6/2020 KAVIAN REFAHI
Applicant returned to address corrections 6/9/2020 KAVIAN REFAHI
Green Plans Picked Up 8/21/2020 APPLICANT
Plan Check Approved 9/23/2020 KAVIAN REFAHI
Issued 11/24/2020 APPLICANT
Building Plans Picked Up 11/24/2020 APPLICANT
CofO in Progress 5/10/2023 MICHAEL PELHAM
Permit Finaled 5/12/2023 DANIEL ORRANTE
CofO Issued 5/12/2023 DANIEL ORRANTE
Permit Finaled 5/12/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/12/2020 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 2/12/2020 ANTHONY MAINEZ
Permit Cleared 2/12/2020 ANTHONY MAINEZ
Sewer availability Cleared 2/12/2020 ANTHONY MAINEZ
CPC Cleared 2/13/2020 SARAH GOLDMAN
ZA Case Cleared 2/13/2020 SARAH GOLDMAN
Hydrant and Access approval Cleared 2/14/2020 JOHN CONNEALLY
Trees in Parkway Cleared 4/27/2020 JOHN KIM
Low Impact Development Cleared 6/30/2020 ANDRES COVARRUBIAS
Green Code Cleared 8/21/2020 RICHARD GARCIA
Miscellaneous Cleared 8/25/2020 NIKTA MOUSAVI
Roof/Waste drainage to street Cleared 8/28/2020 NIKTA MOUSAVI
Excavation more than 5-ft deep Cleared 9/23/2020 CALOSHA APPROVED
GPI Written Notices Cleared 9/23/2020 KAVIAN REFAHI
Grading Pre-Inspection Cleared 9/23/2020 KAVIAN REFAHI

Contact Information

Contractor Pillar Building Group Llc; Lic. No.: 1017041-B 8109 ORION AVE      VAN NUYS, CA 91406
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Valencia,, Byron Steve; Lic. No.: C87372 13719 OXNARD ST 101      VAN NUYS, CA 91401

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 12/18/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 12/21/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Piling/Pier/Caisson 12/21/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 12/22/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 2/23/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 2/24/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 2/25/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 2/25/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 2/25/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
METHANE-Barrier 2/25/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Subgrade 2/25/2021 Approved GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 2/25/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 3/26/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 4/13/2021 Partial Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 4/28/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 5/19/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 5/20/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 5/26/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 5/26/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 5/26/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 6/11/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 7/26/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 8/3/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 8/3/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 8/5/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 8/5/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 8/16/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 8/17/2021 Approved DANIEL ORRANTE
Excavation/Setback/Form/Re-Bar 8/17/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 8/17/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 8/17/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 8/18/2021 Approved DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 10/12/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 11/10/2021 Partial Approval BRENDAN LOONEY
Deputy Wood Construction 1/28/2022 Conditional Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 1/31/2022 Partial Approval CARLOS MATAMOROS
HVAC-Rough 3/9/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 3/9/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 3/15/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 3/15/2022 Approved GERMAN RODRIGUEZ MENDOZA
Shower Pan 3/29/2022 Approved BRENDAN LOONEY
ELECTRICAL-Rough 3/31/2022 Corrections Issued BRENDAN LOONEY
Green Building Rough 3/31/2022 Approved BRENDAN LOONEY
Interior/Exterior Lathing 3/31/2022 Partial Approval BRENDAN LOONEY
METHANE-Rough 3/31/2022 Approved BRENDAN LOONEY
ELECTRICAL-Rough 4/4/2022 Approved BRENDAN LOONEY
HVAC-Rough 4/4/2022 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 4/5/2022 Corrections Issued BRENDAN LOONEY
Verify Sprinkler Sign Off 4/5/2022 Not Ready for Inspection BRENDAN LOONEY
Interior/Exterior Lathing 4/12/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 4/19/2022 Approved BRENDAN LOONEY
Deputy Wood Construction 4/19/2022 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 4/19/2022 Approved BRENDAN LOONEY
Insulation 4/19/2022 Corrections Issued BRENDAN LOONEY
Verify Sprinkler Sign Off 4/19/2022 Approved BRENDAN LOONEY
Insulation 4/21/2022 Not Ready for Inspection CHRISTOPHER WILSON
Insulation 4/26/2022 Conditional Approval BRENDAN LOONEY
Drywall Nailing 5/6/2022 Approved RYAN SALAZAR
Sewer 7/29/2022 Approved PATRICK QUALEY
Gas Test 8/29/2022 Corrections Issued STEPHANIE SWANSON
Gas Test 8/29/2022 Not Ready for Inspection STEPHANIE SWANSON
Gas Test 8/30/2022 Corrections Issued STEPHANIE SWANSON
Special/Order Compliance 8/30/2022 Approved ANDREW NAVE
Final 2/13/2023 Corrections Issued STEPHANIE SWANSON
HVAC-Final 2/13/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 2/13/2023 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 2/27/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 2/27/2023 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 3/1/2023 Corrections Issued STEPHANIE SWANSON
Gas Test 3/1/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 3/1/2023 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 3/6/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 3/6/2023 Approved STEPHANIE SWANSON
Service/Power Release 3/6/2023 Not Ready for Inspection STEPHANIE SWANSON
Service/Power Release 3/15/2023 Approved STEPHANIE SWANSON
Final 5/3/2023 Corrections Issued STEPHANIE SWANSON
Green Building Final 5/3/2023 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 5/3/2023 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 5/3/2023 Approved STEPHANIE SWANSON
Final 5/4/2023 Partial Approval STEPHANIE SWANSON