10434 W WYTON DR 90024

Certificate Information: 10434 W WYTON DR 90024

Application / Permit
19010-30000-06137
Plan Check / Job No.
B19WL07278
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(n) 3-story SFD with attached garage.
Permit Issued
Issued on 2/19/2021
Issuing Office
Current Status
CofO Issued on 10/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2019 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 KAVIAN REFAHI
Corrections Issued 1/27/2020 KAVIAN REFAHI
Quality Review Completed 2/7/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/27/2020 KAVIAN REFAHI
Applicant returned to address corrections 3/16/2020 KAVIAN REFAHI
Applicant returned to address corrections 4/14/2020 KAVIAN REFAHI
Green Plans Picked Up 8/4/2020 APPLICANT
Applicant returned to address corrections 8/12/2020 KAVIAN REFAHI
Plan Check Approved 8/18/2020 KAVIAN REFAHI
Building Plans Picked Up 9/9/2020 APPLICANT
Issued 2/19/2021 APPLICANT
CofO in Progress 10/25/2024 STEPHANIE SWANSON
CofO Issued 10/26/2024 RICHARD STEINBACH
Permit Finaled 10/26/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 2/19/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 2/19/2020 THOMAS LANG
CPC Cleared 2/25/2020 ANNA VIDAL
Disturb/Remove Protected Trees Cleared 4/10/2020 STEPHEN DUPREY
Trees in Parkway Cleared 4/10/2020 STEPHEN DUPREY
Permit Cleared 4/30/2020 DINAH GARIN
Sewer availability Cleared 5/1/2020 DINAH GARIN
Hydrant and Access approval Cleared 5/5/2020 KURT CORRAL
Low Impact Development Cleared 5/21/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 5/29/2020 DINAH GARIN
Green Code Cleared 8/11/2020 RICHARD GARCIA
GPI Written Notices Cleared 8/12/2020 KAVIAN REFAHI
Grading Pre-Inspection Cleared 8/12/2020 KAVIAN REFAHI

Contact Information

Architect Driscoll,, Christopher; Lic. No.: C36073 1502 1/2 S SYCAMORE AVENUE      LOS ANGELES, CA 90019
Contractor J L M Development; Lic. No.: 1025019-B 1301 WEST 35TH PLACE      LOS ANGELES, CA 90007
Engineer Mcgrath,, Michael John; Lic. No.: C86488 2420 ROYCROFT AVE      LONG BEACH, CA 90815
Engineer Pukkanasut,, Jirayus; Lic. No.: C73728 15038 CLARK AVE      HACIENDA HEIGHTS, CA 91745
Engineer Wavering,, Derek Evan; Lic. No.: S6239 1371 COLE LANE      UPLAND, CA 91784

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/25/2021 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 3/25/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 3/25/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 4/7/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 4/8/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 4/8/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 5/17/2021 Corrections Issued MATT KELLERMAN
Footing/Foundation/Slab 5/17/2021 Corrections Issued MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 5/19/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 5/19/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 5/25/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Deputy Shotcrete 5/28/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 5/28/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 5/28/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Shotcrete 6/1/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 7/20/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 7/30/2021 Partial Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 7/30/2021 Partial Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 9/16/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 10/18/2021 Partial Approval BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 11/4/2021 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 11/4/2021 Not Ready for Inspection BRENDAN LOONEY
Deputy Wood Construction 11/19/2021 Conditional Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 11/22/2021 Partial Approval BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 12/17/2021 Corrections Issued BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 12/20/2021 Approved BRENDAN LOONEY
HVAC-Rough 1/20/2022 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 1/20/2022 Approved BRENDAN LOONEY
Sewer 1/20/2022 Approved BRENDAN LOONEY
ELECTRICAL-Rough 1/25/2022 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 3/23/2022 Corrections Issued BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 3/23/2022 Partial Approval BRENDAN LOONEY
Green Building Rough 3/23/2022 Not Ready for Inspection BRENDAN LOONEY
Verify Sprinkler Sign Off 3/23/2022 Not Ready for Inspection BRENDAN LOONEY
Deputy Wood Construction 3/24/2022 Approved MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 4/7/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 4/18/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 4/18/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 4/26/2022 Corrections Issued BRENDAN LOONEY
Green Building Rough 4/26/2022 Not Ready for Inspection BRENDAN LOONEY
Verify Sprinkler Sign Off 4/26/2022 Approved BRENDAN LOONEY
Pre-Inspection 6/30/2022 Partial Inspection STEPHANIE SWANSON
Special/Order Compliance 6/30/2022 Partial Inspection HERBERT GIRON
Interior/Exterior Lathing 7/26/2022 Corrections Issued CHRISTOPHER WILSON
Shower Pan 7/26/2022 Not Ready for Inspection CHRISTOPHER WILSON
Shower Pan 8/5/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 8/12/2022 Corrections Issued KENNETH NAGLE
BUILDING-Rough-Frame 8/22/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Green Building Rough 8/22/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 8/22/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Wood Frame 8/22/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 8/24/2022 Partial Approval MICHAEL PELHAM
Insulation 9/2/2022 Corrections Issued STEPHANIE SWANSON
Insulation 9/21/2022 Corrections Issued STEPHANIE SWANSON
Insulation 10/5/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 10/18/2022 Partial Approval STEPHANIE SWANSON
Shower Pan 10/18/2022 Approved STEPHANIE SWANSON
Drywall Nailing 11/1/2022 Conditional Approval STEPHANIE SWANSON
Interior/Exterior Lathing 12/29/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 10/11/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Final 10/11/2023 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 10/11/2023 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 10/11/2023 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 10/19/2023 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 11/28/2023 Approved STEPHANIE SWANSON
HVAC-Final 11/28/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Final 11/28/2023 Partial Approval STEPHANIE SWANSON
Gas Test 12/4/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 12/4/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Final 12/12/2023 Approved STEPHANIE SWANSON
HVAC-Final 12/13/2023 Approved STEPHANIE SWANSON
HVAC-Final 12/13/2023 Partial Approval STEPHANIE SWANSON
BUILDING-Rough-Frame 3/26/2024 Not Ready for Inspection STEPHANIE SWANSON
Enclosure/Fence 3/26/2024 Corrections Issued STEPHANIE SWANSON
Final 3/26/2024 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 3/26/2024 Approved STEPHANIE SWANSON
Green Building Final 3/26/2024 Approved STEPHANIE SWANSON
Green Building Rough 3/26/2024 Approved STEPHANIE SWANSON
Pool Piping 3/26/2024 Approved STEPHANIE SWANSON
Pool/Spa Cover 3/26/2024 Not Ready for Inspection STEPHANIE SWANSON
Service/Power Release 3/26/2024 Not Ready for Inspection STEPHANIE SWANSON
Smoke Detectors 3/26/2024 Not Ready for Inspection STEPHANIE SWANSON
Service/Power Release 8/28/2024 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 9/4/2024 Approved STEPHANIE SWANSON
Final 9/4/2024 Corrections Issued STEPHANIE SWANSON
Smoke Detectors 9/4/2024 Approved STEPHANIE SWANSON
Final 9/6/2024 Corrections Issued STEPHANIE SWANSON
Final 9/12/2024 Corrections Issued STEPHANIE SWANSON
Final 10/25/2024 OK to Issue CofO STEPHANIE SWANSON