2238 S DUNSMUIR AVE 90016
Certificate Information: 2238 S DUNSMUIR AVE 90016
- Application / Permit
- 19010-30000-06072
- Plan Check / Job No.
- B19WL07245
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2 STORY ACCESSORY DWELLING UNIT AT REAR OF LOT
- Permit Issued
- Issued on 1/14/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 2/17/2020 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 2/23/2020 | YOUNG KIM |
| Green Plans Picked Up | 9/21/2020 | APPLICANT |
| Applicant returned to address corrections | 9/22/2020 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 10/4/2020 | FARSHAD ALIMOHAMADI |
| Building Plans Picked Up | 11/9/2020 | APPLICANT |
| Issued | 1/14/2021 | APPLICANT |
| CofO in Progress | 10/26/2022 | JOSE AVILA |
| Permit Finaled | 2/17/2023 | DANIEL ORRANTE |
| CofO Issued | 2/17/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/17/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 3/20/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 3/23/2020 | JEREMY CARTER |
| Construction near power lines | Cleared | 5/27/2020 | RIDWAN HARDY |
| Green Code | Cleared | 8/12/2020 | DONALD CRICHLOW |
| Low Impact Development | Cleared | 8/27/2020 | JORGE MEJIA LEMUS |
| Address approval | Cleared | 9/3/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 9/9/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/26/2021 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2021 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 3/18/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Insulation | 3/18/2021 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 3/18/2021 | Partial Approval | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 3/18/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2021 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2021 | Partial Approval | STUART CHAPMAN |
| Wood Frame | 4/27/2021 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 7/27/2021 | Partial Approval | JOAQUIN GREENOUGH |
| HVAC-Rough | 7/27/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 7/27/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 7/27/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 9/27/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 9/27/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 9/27/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 9/27/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 9/27/2021 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 9/27/2021 | Approved | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 9/27/2021 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 9/27/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 10/1/2021 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 10/8/2021 | Approved | LILIANA PORTILLO |
| Shower Pan | 11/10/2021 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 2/22/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 6/23/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 6/23/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 6/23/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 10/12/2022 | Approved | JOSE AVILA |
| Final | 10/12/2022 | Corrections Issued | JOSE AVILA |
| Green Building Final | 10/12/2022 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 10/12/2022 | SGSOV Not Ready | JOSE AVILA |
| Smoke Detectors | 10/12/2022 | Corrections Issued | JOSE AVILA |
| Final | 10/24/2022 | OK to Issue CofO | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 10/24/2022 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 10/24/2022 | Approved | JOSE AVILA |
| Smoke Detectors | 10/24/2022 | Approved | JOSE AVILA |