8762 W CADILLAC AVE 90034

Certificate Information: 8762 W CADILLAC AVE 90034

Application / Permit
19010-30000-06071
Plan Check / Job No.
B19WL07244
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) single family dwelling with attached garage. Equipped with fire sprinkler system NFPA-13D.
Permit Issued
Issued on 2/10/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/7/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2019 APPLICANT
Green Plans Picked Up 1/15/2020 APPLICANT
Assigned to Plan Check Engineer 1/16/2020 ALFREDO JARA
Corrections Issued 1/22/2020 ALFREDO JARA
Quality Review Completed 1/31/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 2/3/2020 APPLICANT
Plan Check Approved 2/10/2020 ALFREDO JARA
Issued 2/10/2020 LADBS
CofO in Progress 11/24/2020 EVAN COOPER
CofO Issued 12/7/2020 VINCENT COTTON
Permit Finaled 12/7/2020 VINCENT COTTON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/4/2020 CELINA MORENO
Hydrant and Access approval Cleared 2/4/2020 GEORGE SUCHAND
Low Impact Development Cleared 2/4/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 2/4/2020 CELINA MORENO
Sewer availability Cleared 2/4/2020 CELINA MORENO
Green Code Cleared 2/6/2020 RICHARD GARCIA

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/15/2020 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 4/20/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 4/20/2020 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 4/23/2020 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 4/29/2020 Approved EVAN COOPER
Footing/Foundation/Slab 4/29/2020 Approved EVAN COOPER
Deputy Wood Construction 5/14/2020 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/14/2020 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/2/2020 Partial Approval CRAIG DAVIS
PLUMBING-Rough 6/18/2020 Approved EVAN COOPER
Sewer 6/18/2020 Approved EVAN COOPER
ELECTRICAL-Rough 6/22/2020 Approved EVAN COOPER
HVAC-Rough 6/25/2020 Approved EVAN COOPER
Interior/Exterior Lathing 6/25/2020 Partial Approval EVAN COOPER
Interior/Exterior Lathing 7/6/2020 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 7/28/2020 Approved EVAN COOPER
Green Building Rough 7/28/2020 Approved EVAN COOPER
MERV13>=Rough 7/28/2020 Approved EVAN COOPER
Verify Sprinkler Sign Off 7/28/2020 Approved EVAN COOPER
Insulation 8/3/2020 Approved EVAN COOPER
Drywall Nailing 8/10/2020 Approved EVAN COOPER
Interior/Exterior Lathing 8/10/2020 Approved EVAN COOPER
Gas Test 9/17/2020 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/17/2020 SGSOV Approved EVAN COOPER
ELECTRICAL-Final 9/25/2020 Approved EVAN COOPER
Service/Power Release 9/25/2020 Not Ready for Inspection EVAN COOPER
PLUMBING-Final 9/29/2020 Approved EVAN COOPER
Service/Power Release 9/29/2020 Approved KENNETH NAGLE
Final 11/13/2020 Partial Approval EVAN COOPER
Green Building Final 11/13/2020 Approved EVAN COOPER
HVAC-Final 11/13/2020 Approved EVAN COOPER
MERV13>=Final 11/13/2020 Approved EVAN COOPER
Smoke Detectors 11/13/2020 Approved EVAN COOPER