12012 W CLOVER AVE 90066
Certificate Information: 12012 W CLOVER AVE 90066
- Application / Permit
- 19010-30000-06057
- Plan Check / Job No.
- B19WL07232
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ ATT. 2-CAR GARAGE
- Permit Issued
- Issued on 11/25/2020
- Issuing Office
- Current Status
- CofO Issued on 11/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | REZA HAGHIGHAT |
| Corrections Issued | 1/21/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 1/30/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 2/3/2020 | APPLICANT |
| Plan Check Approved | 4/17/2020 | REZA HAGHIGHAT |
| Building Plans Picked Up | 4/17/2020 | APPLICANT |
| Issued | 11/25/2020 | APPLICANT |
| CofO in Progress | 11/8/2021 | KENNETH NAGLE |
| Permit Finaled | 11/8/2021 | KENNETH NAGLE |
| CofO Issued | 11/8/2021 | KENNETH NAGLE |
| Permit Finaled | 11/8/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2020 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 3/18/2020 | PATRICK MISCHLICH |
| Hydrant and Access approval | Cleared | 3/18/2020 | JEREMY CARTER |
| Low Impact Development | Cleared | 3/18/2020 | MITESH PATEL |
| Permit | Cleared | 3/18/2020 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 3/18/2020 | WALLIE JONG |
| Sewer availability | Cleared | 3/18/2020 | WALLIE JONG |
| Green Code | Cleared | 3/31/2020 | RICHARD GARCIA |
| Trees in Parkway | Cleared | 4/8/2020 | JOHN KIM |
| GPI Written Notices | Cleared | 4/17/2020 | REZA HAGHIGHAT |
Contact Information
| Architect | Paddock,, Stephen G; Lic. No.: C27018 | 3929 TIVOLI AVE LOS ANGELES, CA 90066 |
| Contractor | Local Construction Remodeling; Lic. No.: 966738-B | 14901 TUBA STREET MISSION HILLS, CA 91345 |
| Engineer | Varela, Olivas, Benjamin; Lic. No.: S5714 | 12831 PANAMA STREET LOS ANGELES, CA 90066 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/3/2020 | Partial Approval | RICHARD ROBLES |
| Footing/Foundation/Slab | 12/14/2020 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 12/18/2020 | Partial Approval | RICHARD ROBLES |
| Structural Steel Frame | 12/23/2020 | Partial Approval | RICHARD ROBLES |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2021 | Corrections Issued | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2021 | Corrections Issued | RICHARD ROBLES |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2021 | Partial Approval | RICHARD ROBLES |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2021 | Approved | RICHARD ROBLES |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2021 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 3/12/2021 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/12/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 4/14/2021 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/14/2021 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2021 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/4/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 5/4/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/4/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 5/4/2021 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 5/4/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/11/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 5/11/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/11/2021 | No Access for Inspection | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 5/11/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Insulation | 5/19/2021 | Corrections Issued | AMY COLIN |
| Interior/Exterior Lathing | 5/19/2021 | Not Ready for Inspection | AMY COLIN |
| Insulation | 5/25/2021 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 5/25/2021 | Partial Approval | ADAM ESCOTO |
| Drywall Nailing | 6/4/2021 | Approved | EVAN COOPER |
| Green Building Rough | 6/4/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/4/2021 | Approved | EVAN COOPER |
| HVAC-Final | 7/19/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/23/2021 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 9/23/2021 | Approved | EVAN COOPER |
| Final | 9/23/2021 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 9/23/2021 | Approved | EVAN COOPER |
| Gas Test | 9/23/2021 | Approved | EVAN COOPER |
| Green Building Final | 9/23/2021 | Approved | EVAN COOPER |
| HVAC-Final | 9/23/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 9/23/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 9/23/2021 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 9/23/2021 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 9/23/2021 | Approved | EVAN COOPER |
| Verify Rec and Parks Fee Memo | 9/23/2021 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 9/23/2021 | Approved | EVAN COOPER |
| Final | 10/1/2021 | Conditional Approval | EVAN COOPER |
| Service/Power Release | 10/1/2021 | Approved | EVAN COOPER |