12012 W CLOVER AVE 90066

Certificate Information: 12012 W CLOVER AVE 90066

Application / Permit
19010-30000-06057
Plan Check / Job No.
B19WL07232
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATT. 2-CAR GARAGE
Permit Issued
Issued on 11/25/2020
Issuing Office
Current Status
CofO Issued on 11/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Assigned to Plan Check Engineer 1/16/2020 REZA HAGHIGHAT
Corrections Issued 1/21/2020 REZA HAGHIGHAT
Quality Review Completed 1/30/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 2/3/2020 APPLICANT
Plan Check Approved 4/17/2020 REZA HAGHIGHAT
Building Plans Picked Up 4/17/2020 APPLICANT
Issued 11/25/2020 APPLICANT
CofO in Progress 11/8/2021 KENNETH NAGLE
Permit Finaled 11/8/2021 KENNETH NAGLE
CofO Issued 11/8/2021 KENNETH NAGLE
Permit Finaled 11/8/2021 KENNETH NAGLE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/18/2020 WALLIE JONG
Grading Pre-Inspection Cleared 3/18/2020 PATRICK MISCHLICH
Hydrant and Access approval Cleared 3/18/2020 JEREMY CARTER
Low Impact Development Cleared 3/18/2020 MITESH PATEL
Permit Cleared 3/18/2020 WALLIE JONG
Roof/Waste drainage to street Cleared 3/18/2020 WALLIE JONG
Sewer availability Cleared 3/18/2020 WALLIE JONG
Green Code Cleared 3/31/2020 RICHARD GARCIA
Trees in Parkway Cleared 4/8/2020 JOHN KIM
GPI Written Notices Cleared 4/17/2020 REZA HAGHIGHAT

Contact Information

Architect Paddock,, Stephen G; Lic. No.: C27018 3929 TIVOLI AVE      LOS ANGELES, CA 90066
Contractor Local Construction Remodeling; Lic. No.: 966738-B 14901 TUBA STREET      MISSION HILLS, CA 91345
Engineer Varela, Olivas, Benjamin; Lic. No.: S5714 12831 PANAMA STREET      LOS ANGELES, CA 90066

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/3/2020 Partial Approval RICHARD ROBLES
Footing/Foundation/Slab 12/14/2020 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 12/18/2020 Partial Approval RICHARD ROBLES
Structural Steel Frame 12/23/2020 Partial Approval RICHARD ROBLES
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Corrections Issued PIERRE VEGA
Floor/Roof Diaphrgm/Shear Wall 1/26/2021 Corrections Issued RICHARD ROBLES
Floor/Roof Diaphrgm/Shear Wall 1/28/2021 Partial Approval RICHARD ROBLES
Floor/Roof Diaphrgm/Shear Wall 2/23/2021 Approved RICHARD ROBLES
Floor/Roof Diaphrgm/Shear Wall 3/12/2021 Approved OGANES TARAKHCHYAN
HVAC-Rough 3/12/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 3/12/2021 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 4/14/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 4/14/2021 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/15/2021 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/4/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 5/4/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 5/4/2021 Partial Approval OGANES TARAKHCHYAN
Shower Pan 5/4/2021 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 5/4/2021 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/11/2021 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 5/11/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 5/11/2021 No Access for Inspection OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 5/11/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Insulation 5/19/2021 Corrections Issued AMY COLIN
Interior/Exterior Lathing 5/19/2021 Not Ready for Inspection AMY COLIN
Insulation 5/25/2021 Approved ADAM ESCOTO
Interior/Exterior Lathing 5/25/2021 Partial Approval ADAM ESCOTO
Drywall Nailing 6/4/2021 Approved EVAN COOPER
Green Building Rough 6/4/2021 Approved EVAN COOPER
Interior/Exterior Lathing 6/4/2021 Approved EVAN COOPER
HVAC-Final 7/19/2021 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 9/23/2021 Approved EVAN COOPER
ELECTRICAL-Final 9/23/2021 Approved EVAN COOPER
Final 9/23/2021 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 9/23/2021 Approved EVAN COOPER
Gas Test 9/23/2021 Approved EVAN COOPER
Green Building Final 9/23/2021 Approved EVAN COOPER
HVAC-Final 9/23/2021 Approved EVAN COOPER
PLUMBING-Final 9/23/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/23/2021 SGSOV Approved EVAN COOPER
Service/Power Release 9/23/2021 Not Ready for Inspection EVAN COOPER
Smoke Detectors 9/23/2021 Approved EVAN COOPER
Verify Rec and Parks Fee Memo 9/23/2021 Not Ready for Inspection EVAN COOPER
Verify Sprinkler Sign Off 9/23/2021 Approved EVAN COOPER
Final 10/1/2021 Conditional Approval EVAN COOPER
Service/Power Release 10/1/2021 Approved EVAN COOPER